* Fabian, Mark and Liu-kun did BS installation at Kamioka: * Connected the DIO card to the LPCD. (Simulink model changes will be needed to make use of it.) * Took TF data from the TM-H1 coil output to the voltage and current monitors and found that the response was approximately flat, meaning that meaningful TFs can be taken of the RM/BS stage with no DIO. * Used the 90° prism and the optical lever to set the pitch of the RM to match the dummy BS. * Removed the RM trolley and added the bottom section of the security structure. * Lifted the IM/RM/BS with the load gauge adapter and load gauge and measured its mass. * Hirata-san: * Modified drawing of maraging rods for BS [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5706| D1605706]] * Made 3D models of stub flag gluing jigs. * Made 3D models and 2D drawing of BS BF-IM hexagon cable clamp assembly and cone parts. [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5734| D1605734]] * Washed parts and screws. * (For Type A) Assembled and adjusted blades of BF #9. * Mark checked lots of drawings by Hirata-san. * Mark worked on schedule but only succeeded in completely garbling the Type B section of the VIS schedule on the server. * Longer term to-do list * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing. * Part "disk security" top has to be modified - screw positions do not match. * Write more of payload assembly procedure (Fabian) - ONGOING * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING * Lower breadboard installation to be incorporated into the procedure document. * Work on BS simulation (Fabian) * Do BS Simulink model (Mark, Kokeyama) - TM/IM/BF level DONE * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) |
* Mark updated the BS circuit diagram [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600|D1503600]]: * Added information on the binary IO. * Renamed channels to conform to Okutomi-kun's new scheme. * Made the ADC/DAC channel assignment consistent and more logical. * Updated the stepper motor sections with info about the new driver chassis. * Mark and Hirata-san worked on collecting parts and tools that will be needed for cabling of the BS next week. (11 special-purpose cables need to be made for the picos/steppers/OSEMs/LVDT on the RM/IRM/IM/BF and, time permitting, 2 more for the SF.) * Mark worked on schedule. * Mark updated the installation procedure with lessons learned from the last few weeks. * Mark downloaded Hirata-san's Inventor model of the BS in the tank and starting thinking about installation of the suspension and lower bread board. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
- Type B Past Week Summary
Mark updated the BS circuit diagram D1503600:
- Added information on the binary IO.
- Renamed channels to conform to Okutomi-kun's new scheme.
- Made the ADC/DAC channel assignment consistent and more logical.
- Updated the stepper motor sections with info about the new driver chassis.
- Mark and Hirata-san worked on collecting parts and tools that will be needed for cabling of the BS next week. (11 special-purpose cables need to be made for the picos/steppers/OSEMs/LVDT on the RM/IRM/IM/BF and, time permitting, 2 more for the SF.)
- Mark worked on schedule.
- Mark updated the installation procedure with lessons learned from the last few weeks.
- Mark downloaded Hirata-san's Inventor model of the BS in the tank and starting thinking about installation of the suspension and lower bread board.