 * Type B Past Week Summary
  * Fabian, Mark and Liu-kun did BS installation at Kamioka:
   * Connected the DIO card to the LPCD. (Simulink model changes will be needed to make use of it.)
   * Took TF data from the TM-H1 coil output to the voltage and current monitors and found that the response was approximately flat, meaning that meaningful TFs can be taken of the RM/BS stage with no DIO.
   * Used the 90° prism and the optical lever to set the pitch of the RM to match the dummy BS.
   * Removed the RM trolley and added the bottom section of the security structure.
   * Lifted the IM/RM/BS with the load gauge adapter and load gauge and measured its mass.
  * Hirata-san:
   * Modified drawing of maraging rods for BS [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5706| D1605706]]
   * Made 3D models of stub flag gluing jigs.
   * Made 3D models and 2D drawing of BS BF-IM hexagon cable clamp assembly and cone parts. [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5734| D1605734]]
   * Washed parts and screws.
   * (For Type A) Assembled and adjusted blades of BF #9.
  * Mark checked lots of drawings by Hirata-san.
  * Mark worked on schedule but only succeeded in completely garbling the Type B section of the VIS schedule on the server.
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama) - TM/IM/BF level DONE
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
 * Mark and Fabian debugged the rubbing issue with the BS. It turns out the EQ stops between the IRM and IM are so misaligned that they can't be used at all. This misalignment was noted on 10/17 klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2090|2090]] but seems to have gotten worse. With the stops removed, the OSEMs are still fairly well centered, so the problem probably predates the earthquake of 11/1.
 * Mark worked on the PR2 rack:
  * Rearranged the items in the rack to make space for new AA and AI chassis at the bottom near the IO chassis.
  * Replaced the AA chassis, which had had a group of channels marked as bad by Michimura-san.
  * Installed a second AA chassis and a second AI chassis in the rack.
  * Installed a second ADC card and a second DAC card in the IO chassis.
  * Modified the k1ioppr2 real-time model to recognize the new ADC/DAC cards and also the extra DIO cards installed previously.
  * Attempted to modify the k1visbs real-time model to recognize the new ADC/DAC cards. Unfortunately, apparently due to changes to library parts made by Okutomi-san, neither the original model or Okutomi-san's new model can be successfully compiled and installed anymore! Debugging is ongoing.
 * Fabian finished the redesign of the EQ stops for the BS RM. Hirata-san will refine the 3D design and do drawings (estimated 1/2 day).
 * Fabian redesigned the cable clamp on top of the multi-purpose cube (on the RM) to avoid the need for clips. (These are too easily moved if the cables are moved during installation and removal of the safety bar between the RM and IM, which has to be done many times.)
 * Mark and Fabian reviewed the previous iJect payload parts order and flagged the items that need updating.
 * Mark worked on task lists and schedule.
 * Hirata-san finished the PR/SR mirror box modifications.
 * Hirata-san washed parts (screws and collets).
Line 33: Line 20:
    

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Mark and Fabian debugged the rubbing issue with the BS. It turns out the EQ stops between the IRM and IM are so misaligned that they can't be used at all. This misalignment was noted on 10/17 klog 2090 but seems to have gotten worse. With the stops removed, the OSEMs are still fairly well centered, so the problem probably predates the earthquake of 11/1.

  • Mark worked on the PR2 rack:
    • Rearranged the items in the rack to make space for new AA and AI chassis at the bottom near the IO chassis.
    • Replaced the AA chassis, which had had a group of channels marked as bad by Michimura-san.
    • Installed a second AA chassis and a second AI chassis in the rack.
    • Installed a second ADC card and a second DAC card in the IO chassis.
    • Modified the k1ioppr2 real-time model to recognize the new ADC/DAC cards and also the extra DIO cards installed previously.
    • Attempted to modify the k1visbs real-time model to recognize the new ADC/DAC cards. Unfortunately, apparently due to changes to library parts made by Okutomi-san, neither the original model or Okutomi-san's new model can be successfully compiled and installed anymore! Debugging is ongoing.
  • Fabian finished the redesign of the EQ stops for the BS RM. Hirata-san will refine the 3D design and do drawings (estimated 1/2 day).
  • Fabian redesigned the cable clamp on top of the multi-purpose cube (on the RM) to avoid the need for clips. (These are too easily moved if the cables are moved during installation and removal of the safety bar between the RM and IM, which has to be done many times.)
  • Mark and Fabian reviewed the previous iJect payload parts order and flagged the items that need updating.
  • Mark worked on task lists and schedule.
  • Hirata-san finished the PR/SR mirror box modifications.
  • Hirata-san washed parts (screws and collets).