 * Type B Past Week Summary
  * Fabian, Mark and Liu-kun did BS installation at Kamioka:
   * Built up the security structure to the ring below the BF.
   * Adjusted the crossbeams below the BF and installed the jacks and pushrods to support the BF.
   * Craned in the BF.
   * Took TFs from L and P actuation at the RM to all DOFs at the BS. (Y actuation still to be done.)
  * Hirata-san:
   * Made 3D models of (revised) stub flag gluing jigs.
   * (For other groups)
    * Assembled two BFs.
    * Made drawings of PRM inner frame.
  * Mark checked lots of drawings by Hirata-san.
  * Mark worked on schedule.
  * Mark added the DIO card to a draft of the BS electronics diagram, D1503600. At first it appeared that the pinouts of the LPCD DIO connectors was completely incompatible with the DIO card cables, but it turns out (according to Miyakawa) that the LPCD chassis has a secret interface board (JGW-D1504332) not shown in the chassis drawing which corrects them.
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama) - TM/IM/BF level DONE
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)

 
 * Hirata-san:
  * Updated the 3D assembly model for BS (among other issues, it turned out that parts were not correctly mated near where the suspension sits on the hydraulic jacks in the tank).
  * Liaised with IJECT.
  * Made an inventory for Type B (BS and SR).
  * Packed and shipped second winch to Kamioka.
  * Packed some jigs for adjusting BF blades.
  * Attended NINS information security seminar.
  * Attended the public hearing for the Opt-IR Research Division Chief Election.
 * Mark and Fabian at Kamioka (plus Enzo for 2 days):
  * Finished rebalance of IM
  * Reinstalled IRM, adjusted OSEMs
  * Replaced broken Type 3 cable on IM-H1 OSEM.
  * Fixed issues with k1visbs real-time model.
  * Started TFs from IRM OSEMs to IRM and IM OSEMs.
 * Mark, Fabian and Enzo
  *

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Hirata-san:
    • Updated the 3D assembly model for BS (among other issues, it turned out that parts were not correctly mated near where the suspension sits on the hydraulic jacks in the tank).
    • Liaised with IJECT.
    • Made an inventory for Type B (BS and SR).
    • Packed and shipped second winch to Kamioka.
    • Packed some jigs for adjusting BF blades.
    • Attended NINS information security seminar.
    • Attended the public hearing for the Opt-IR Research Division Chief Election.
  • Mark and Fabian at Kamioka (plus Enzo for 2 days):
    • Finished rebalance of IM
    • Reinstalled IRM, adjusted OSEMs
    • Replaced broken Type 3 cable on IM-H1 OSEM.
    • Fixed issues with k1visbs real-time model.
    • Started TFs from IRM OSEMs to IRM and IM OSEMs.
  • Mark, Fabian and Enzo