 * Type B Past Week Summary
  * Fabian, Mark and Liu-kun did BS installation at Kamioka:
   * Built up the security structure to the ring below the BF.
   * Adjusted the crossbeams below the BF and installed the jacks and pushrods to support the BF.
   * Craned in the BF.
   * Took TFs from L and P actuation at the RM to all DOFs at the BS. (Y actuation still to be done.)
  * Hirata-san:
   * Made 3D models of (revised) stub flag gluing jigs.
   * (For other groups)
    * Assembled two BFs.
    * Made drawings of PRM inner frame.
  * Mark checked lots of drawings by Hirata-san.
  * Mark worked on schedule.
  * Mark added the DIO card to a draft of the BS electronics diagram, D1503600. At first it appeared that the pinouts of the LPCD DIO connectors was completely incompatible with the DIO card cables, but it turns out (according to Miyakawa) that the LPCD chassis has a secret interface board (JGW-D1504332) not shown in the chassis drawing which corrects them.
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama) - TM/IM/BF level DONE
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):
 * We set things up again after the floor coating work.
 * We moved the PI into the second floor of the cleanbooth:
  * We cleared a path for the forklift (moving the portable cleanroom, worktable, power cables, vacuum pumps and other obstacles).
  * We got Saito-sensei to move the PI to the +Y side of the cleanbooth.
  * We washed and cling-wrapped a pallet.
  * We got Miyoki-san to disconnect the cables and curtain blocking the crane slot (and reconnect them afterwards).
  * We added some temporary crossbars in the top of the assembly frame and stored the SF cap on them to get it out of the way.
  * We craned in the pallet and set it up to bridge three floor joists.
  * We craned in the PI using Saito-san's adapter.
   * We couldn't find the original screws for the three PI transport plates so we substituted some others - fortunately there was no galling.
   * We had to connect the adapter to the crane with a sling because the ring for the hook was slightly too small).
 * We did a lot of cabling work:
  * We routed all the BF cables over the BF cap, up through the cable clamp on the SF-BF rod and up to the SF. (We had to redo a few because the Type 3 cable was at the flange end instead of the Type 1.)
  * We connected up the SF LVDT and FR stepper.
  * We started on rebalancing the BF (which had been perturbed by the weight and tension of all the cables). We got it rather better, but it needs more work.
  * We made another batch of anti-feedthrough adapters.
Line 32: Line 25:
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].

Week of 4/10:
 * Hirata-san does scissor lift training 4/10.
 * Perry in Tokyo 4/10.
 * Debug/fix dead OSEM channel, TM-H4.
 * Debug BF/SF LVDTs.
 * Adjust BF pitch/roll.
 * Do TF from SF LVDT actuation.
 * Install temporary ballast mass in SF.
 * Lift SF/BF/... section and check total weight and SF balance.
 * Continue swap of PI LVDT connectors (female->male)
 * Start preparing LBB spring units.
 * Install pico drivers in rack, create MEDM interface (with Miyo-kun), and undo temporary connection of picos to old controller and joystick.
Week of 4/17:
 * Crane in PI.
 * Connect SF/BF... section.
 * Temporarily remove PI and adjust SF ballast if necessary.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):

  • We set things up again after the floor coating work.
  • We moved the PI into the second floor of the cleanbooth:
    • We cleared a path for the forklift (moving the portable cleanroom, worktable, power cables, vacuum pumps and other obstacles).
    • We got Saito-sensei to move the PI to the +Y side of the cleanbooth.
    • We washed and cling-wrapped a pallet.
    • We got Miyoki-san to disconnect the cables and curtain blocking the crane slot (and reconnect them afterwards).
    • We added some temporary crossbars in the top of the assembly frame and stored the SF cap on them to get it out of the way.
    • We craned in the pallet and set it up to bridge three floor joists.
    • We craned in the PI using Saito-san's adapter.
      • We couldn't find the original screws for the three PI transport plates so we substituted some others - fortunately there was no galling.
      • We had to connect the adapter to the crane with a sling because the ring for the hook was slightly too small).
  • We did a lot of cabling work:
    • We routed all the BF cables over the BF cap, up through the cable clamp on the SF-BF rod and up to the SF. (We had to redo a few because the Type 3 cable was at the flange end instead of the Type 1.)
    • We connected up the SF LVDT and FR stepper.
    • We started on rebalancing the BF (which had been perturbed by the weight and tension of all the cables). We got it rather better, but it needs more work.
    • We made another batch of anti-feedthrough adapters.

Plan for coming weeks

For more detail, see KAGRA/Subgroups/VIS/TypeB/ToDo.

Week of 4/10:

  • Hirata-san does scissor lift training 4/10.
  • Perry in Tokyo 4/10.
  • Debug/fix dead OSEM channel, TM-H4.
  • Debug BF/SF LVDTs.
  • Adjust BF pitch/roll.
  • Do TF from SF LVDT actuation.
  • Install temporary ballast mass in SF.
  • Lift SF/BF/... section and check total weight and SF balance.
  • Continue swap of PI LVDT connectors (female->male)

  • Start preparing LBB spring units.
  • Install pico drivers in rack, create MEDM interface (with Miyo-kun), and undo temporary connection of picos to old controller and joystick.

Week of 4/17:

  • Crane in PI.
  • Connect SF/BF... section.
  • Temporarily remove PI and adjust SF ballast if necessary.