Differences between revisions 74 and 257 (spanning 183 versions)
Revision 74 as of 2016-10-13 13:58:20
Size: 2032
Editor: MarkBarton
Comment:
Revision 257 as of 2018-03-23 12:10:14
Size: 1923
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian, Mark and Liu-kun did BS installation at Kamioka:
   * Built up the security structure to the ring below the BF.
   * Adjusted the crossbeams below the BF and installed the jacks and pushrods to support the BF.
   * Craned in the BF.
   * Took TFs from L and P actuation at the RM to all DOFs at the BS. (Y actuation still to be done.)
  * Hirata-san:
   * Made 3D models of (revised) stub flag gluing jigs.
   * (For other groups)
    * Assembled two BFs.
    * Made drawings of PRM inner frame.
  * Mark checked lots of drawings by Hirata-san.
  * Mark worked on schedule.
  * Mark added the DIO card to a draft of the BS electronics diagram, D1503600. At first it appeared that the pinouts of the LPCD DIO connectors were completely incompatible with the DIO card cables, but it turns out (according to Miyakawa) that the LPCD chassis has a secret interface board (JGW-D1504332) not shown in the chassis drawing which makes everything work.
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama) - TM/IM/BF level DONE
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Report for week of 3/19 ====
 * Fujii-kun successfully assembled and tested a geophone pod (klogs 4492, 4508).
 * Hirata-san set up the dummy BS to soak off the sapphire prisms (ongoing).
 * Shoda-san, Hirata-san and Enzo finished the assembly of 12 OSEMs. We still need to measure the maximum output (ongoing).
 * We will send the OSEMs to Kamioka today.
 * Enzo made 2 in-air picomotor cable.
Line 32: Line 13:
 
==== Plan for week of 3/26 ====
 * Tanioka-kun joins.
 * Mark vacation.
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * Lay SR3 in-air cabling (Enzo++).
 * Finish tuning of BFs (Hirata-san++).
 * SF check (Hirata-san++).
  * Check load capacity.
  * Check fit of caps.
  * Add cable clamps to bases.
  * Add cable clamps and Cu segments to caps (only if they fit well).
  * Cable LVDTs and steppers.

==== Plan for week of 4/2 ====
 * Mark at Mitaka Mon, Kamioka from Tue.
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * Glue SR3 (if available)
 * Build 2xIM, 2xIRM (if parts available - due 3/30)

==== Plan for week of 4/9 ====
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * Finish IMs and IRMs
 * Build 1xRM

==== Plan for week of 4/16 ====
 * Start SR3 Hang?

==== Plan for week of 4/23 ====
 * F0 blade prototype test

==== Plan for week of 4/30 ====
  * Golden Week!

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]

==== Vacation Info ====
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Fabian vacation, 3/26-4/27 (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 3/19

  • Fujii-kun successfully assembled and tested a geophone pod (klogs 4492, 4508).
  • Hirata-san set up the dummy BS to soak off the sapphire prisms (ongoing).
  • Shoda-san, Hirata-san and Enzo finished the assembly of 12 OSEMs. We still need to measure the maximum output (ongoing).
  • We will send the OSEMs to Kamioka today.
  • Enzo made 2 in-air picomotor cable.

Plan for week of 3/26

  • Tanioka-kun joins.
  • Mark vacation.
  • Shoda-san at Mitaka
  • Others at Kamioka
  • --
  • Lay SR3 in-air cabling (Enzo++).
  • Finish tuning of BFs (Hirata-san++).
  • SF check (Hirata-san++).
    • Check load capacity.
    • Check fit of caps.
    • Add cable clamps to bases.
    • Add cable clamps and Cu segments to caps (only if they fit well).
    • Cable LVDTs and steppers.

Plan for week of 4/2

  • Mark at Mitaka Mon, Kamioka from Tue.
  • Shoda-san at Mitaka
  • Others at Kamioka
  • --
  • Glue SR3 (if available)
  • Build 2xIM, 2xIRM (if parts available - due 3/30)

Plan for week of 4/9

  • Shoda-san at Mitaka
  • Others at Kamioka
  • --
  • Finish IMs and IRMs
  • Build 1xRM

Plan for week of 4/16

  • Start SR3 Hang?

Plan for week of 4/23

  • F0 blade prototype test

Plan for week of 4/30

  • Golden Week!

To-Do Lists, Schedule

Vacation Info

  • Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
  • Fabian vacation, 3/26-4/27 (then gone).

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)