 * Type B Past Week Summary
  * Fabian, Mark and Liu-kun did BS installation at Kamioka:
   * Built up the security structure to the ring below the BF.
   * Adjusted the crossbeams below the BF and installed the jacks and pushrods to support the BF.
   * Craned in the BF.
   * Took TFs from L and P actuation at the RM to all DOFs at the BS. (Y actuation still to be done.)
  * Hirata-san:
   * Made 3D models of (revised) stub flag gluing jigs.
   * (For other groups)
    * Assembled two BFs.
    * Made drawings of PRM inner frame.
  * Mark checked lots of drawings by Hirata-san.
  * Mark worked on schedule.
  * Mark added the DIO card to a draft of the BS electronics diagram, D1503600. At first it appeared that the pinouts of the LPCD DIO connectors were completely incompatible with the DIO card cables, but it turns out (according to Miyakawa) that the LPCD chassis has a secret interface board (JGW-D1504332) not shown in the chassis drawing which should make everything work.
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama) - TM/IM/BF level DONE
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
 * We solved the problem with the OSEMs: cables had been plugged into the LED current monitor outputs, not the PD outputs.
 * We solved a problem with the real-time model freezing which turned out to be the IO chassis having lost power.
 * We took some mass off the IM to allow for the weight of the cables, and readjusted it in pitch and roll.
 * We aligned the IM
Line 32: Line 13:
  ==== Plan for week of 8/28 ====
Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri).
 * Fix/adjust IRM OSEMs.
 * Add BF cap; cable and test BF-1 and BF-2 picos.
 * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
 * Crane in SF.
 * Suspend BF/IRM/IM/RM/BS.

==== Plan for week of 9/4 ====
 * Install SF cap; route cables.
 * Lift and weigh SF/BF/IRM/IM/RM/BS.
 * Adjust SF ballast.

==== Vacation Info ====
Mark: TBD Mid-Oct

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):

  • We solved the problem with the OSEMs: cables had been plugged into the LED current monitor outputs, not the PD outputs.
  • We solved a problem with the real-time model freezing which turned out to be the IO chassis having lost power.
  • We took some mass off the IM to allow for the weight of the cables, and readjusted it in pitch and roll.
  • We aligned the IM

Plan for week of 8/28

Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri).

  • Fix/adjust IRM OSEMs.
  • Add BF cap; cable and test BF-1 and BF-2 picos.
  • Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
  • Crane in SF.
  • Suspend BF/IRM/IM/RM/BS.

Plan for week of 9/4

  • Install SF cap; route cables.
  • Lift and weigh SF/BF/IRM/IM/RM/BS.
  • Adjust SF ballast.