 * Type B Past Week Summary
  * Fabian, Mark and Liu-kun did BS installation at Kamioka:
   * Built up the security structure to the ring below the BF.
   * Adjusted the crossbeams below the BF and installed the jacks and pushrods to support the BF.
   * Craned in the BF.
   * Took TFs from L and P actuation at the RM to all DOFs at the BS. (Y actuation still to be done.)
  * Hirata-san:
   * Made 3D models of (revised) stub flag gluing jigs.
   * (For other groups)
    * Assembled two BFs.
    * Made drawings of PRM inner frame.
  * Mark checked lots of drawings by Hirata-san.
  * Mark worked on schedule.
  * Mark added the DIO card to a draft of the BS electronics diagram, D1503600. At first it appeared that the pinouts of the LPCD DIO connectors were completely incompatible with the DIO card cables, but it turns out (according to Miyakawa) that the LPCD chassis has a secret interface board (JGW-D1504332) not shown in the chassis drawing which should make everything work.
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do BS Simulink model (Mark, Kokeyama) - TM/IM/BF level DONE
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
 * We disconnected the SF/... section and reinstalled the F0-SF rod with the hex cable clamp attached.
 * We debugged an issue with the actuation (the real-time model needed rebooting).
 * We routed all the SF/... cables up to the bottom of the PI, and then to the feedthroughs.
 * We unlocked the F0 keystone and experimented to find the amount of mass needed on the SF (≈845 g).
 * We attached the SF trim mass, adjusting it laterally so that the SF was level in pitch and roll.
 * We corrected some errors on the MEDM screens (some broken links and Take/Restore Safe.snap buttons).
 * We cabled all the PI items through to the rack and did very basic testing.
 * We disconnected the security structure from the assembly frame and adjusted the PI till the SS was vertical.
 * We unlocked the IP and adjusted the PI jacks and FRs till the IP was centered.
 * We passed the halves of the LBB Cu damping ring (less the Cu) into the chamber and joined them.
 * We put the magnets on the LBB damper ring using the template.
 * We locked various combinations of keystones and measured the vertical resonance frequencies of the unlocked filters.
 * We spent time on getting the geophones working. The original descrambler adapters had gone missing, so Enzo created three new ones. We borrowed a cable to replace one that had broken. The geophone distributor (S1402167) failed (no power on the negative rail), and a replacement borrowed from SR3 (S1605513) kept switching off.
Line 32: Line 22:
  ==== Plan for week of 9/13 ====
==== Plan for week of 9/19 ====
No work Mon 9/18 (敬老の日)<<BR>>
Mark, Fabian, Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Thu, Fri), Kozu-kun
 * Install LBB damper magnet rings in tank.
 * Remove tank lid.
 *
 * Install suspension.

==== Vacation Info ====
Mark: 10/16-24

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):

  • We disconnected the SF/... section and reinstalled the F0-SF rod with the hex cable clamp attached.
  • We debugged an issue with the actuation (the real-time model needed rebooting).
  • We routed all the SF/... cables up to the bottom of the PI, and then to the feedthroughs.
  • We unlocked the F0 keystone and experimented to find the amount of mass needed on the SF (≈845 g).
  • We attached the SF trim mass, adjusting it laterally so that the SF was level in pitch and roll.
  • We corrected some errors on the MEDM screens (some broken links and Take/Restore Safe.snap buttons).
  • We cabled all the PI items through to the rack and did very basic testing.
  • We disconnected the security structure from the assembly frame and adjusted the PI till the SS was vertical.
  • We unlocked the IP and adjusted the PI jacks and FRs till the IP was centered.
  • We passed the halves of the LBB Cu damping ring (less the Cu) into the chamber and joined them.
  • We put the magnets on the LBB damper ring using the template.
  • We locked various combinations of keystones and measured the vertical resonance frequencies of the unlocked filters.
  • We spent time on getting the geophones working. The original descrambler adapters had gone missing, so Enzo created three new ones. We borrowed a cable to replace one that had broken. The geophone distributor (S1402167) failed (no power on the negative rail), and a replacement borrowed from SR3 (S1605513) kept switching off.

Plan for week of 9/13

Plan for week of 9/19

No work Mon 9/18 (敬老の日)
Mark, Fabian, Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Thu, Fri), Kozu-kun

  • Install LBB damper magnet rings in tank.
  • Remove tank lid.
  • Install suspension.

Vacation Info