 * Type B Past Week Summary
  * Fabian, Mark and Liu-kun did BS installation at Kamioka:
   * Replaced the thrust bearing in the BF with a stainless version. While replacing the picomotor spring, they found several issues with screws.
   * Removed the sheet metal cable clamp on the bottom of the BF and installed a redesigned one.
   * They installed the "flying saucer" cable clamp on the maraging rod between the IM and BF, and attached the cables. There was an issue with the cables from the bottom OSEMs, which are too short by about 300 mm.
   * Ruspended the IM. Relative to the mass budget, about 700 g of trim mass had to be taken off to get good balance. There was also a problem with rubbing. It turned out that the keystone and the attached central PEEK coil former for the LVDT were at an angle, and the inside of the coil former was fouling on the outside of the pole piece for the magnets. It's not yet clear why the keystone was misaligned.
  * Hirata-san:
   * Made drawings of (revised) stub flag gluing jigs.
   * Worked on BS full-assembly drawings for Saito-sensei.
   * (For other groups)
    * Made a 3D model of maraging wires.
    * Finished making drawings of PRM inner frame.
    * Worked on re-setting up PC after crash.
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Fabian, Enzo, Hirata-san):
 * We disconnected the in-vacuum and in-air cabling from the feedthroughs.
 * We removed crossbars below BF and SF.
 * We set the SF damper to 4 mm clearance.
 * We adjusted the jacks to nominal height.
 * We removed the geophones and PI yaw stepper for craning.
 * We craned the suspension into the tank, and hooked the LBB Cu ring.
 * We replaced the geophones etc.
 * We unlocked all but the IP and adjusted the jacks until the pendulum was centered in the security structure.
 * We unlocked the IP and adjusted to to center with the jacks and fishing rods.
 * We craned the vacuum tank lid+ring back on, and then removed just the lid (only).
 * We unclamped the LBB damper rings and removed the spacers.
 * We removed the blocks and shims supporting the LBB, inserted the long screw feet and hooked the LBB to the Cu damper ring.
 * We added 2*31.5 kg of ballast to the LBB, which got the blades to the point where firm pressure would depress the tips.
 * We reconnected the in-vacuum cabling. In ≈15 places we opted to omit the Type 1 cable and use a F-F gender bender.
 * We reconnected all but four of the in-air cables.
Line 30: Line 24:
  ==== Plan for week of 6/26 ====
Mark and Enzo at Kamioka:
 * Double-check where gender-benders were used.
 * Finish connecting in-air cabling.
 * Debug all cabling.
 * Work with Simon to set up LSOL.
Fabian at Mitaka:
 * Design final ballast masses for IM, BF and SF assuming no BF rebuild (needs to be adaptable).
 * Check all items for BS flag/prism gluing are available (prisms, flags, jigs, mirror box, glue, scale, mixing tools etc).
Hirata-san at Mitaka:
 * Do new 3D CAD:
  * BS Test Hang build, with top of tank, full suspension, and LBB damper all reversed.
  * Final BS build, as above, but with everything BF down rotated back to original.
   * In-tank version.
   * On-assembly-frame version. (Adjust jack positions if possible, or leave for Mark to do.)
  * SR2 on BS assembly frame. (Adjust jack positions if possible, or leave for Mark to do.)

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Enzo, Hirata-san):

  • We disconnected the in-vacuum and in-air cabling from the feedthroughs.
  • We removed crossbars below BF and SF.
  • We set the SF damper to 4 mm clearance.
  • We adjusted the jacks to nominal height.
  • We removed the geophones and PI yaw stepper for craning.
  • We craned the suspension into the tank, and hooked the LBB Cu ring.
  • We replaced the geophones etc.
  • We unlocked all but the IP and adjusted the jacks until the pendulum was centered in the security structure.
  • We unlocked the IP and adjusted to to center with the jacks and fishing rods.
  • We craned the vacuum tank lid+ring back on, and then removed just the lid (only).
  • We unclamped the LBB damper rings and removed the spacers.
  • We removed the blocks and shims supporting the LBB, inserted the long screw feet and hooked the LBB to the Cu damper ring.
  • We added 2*31.5 kg of ballast to the LBB, which got the blades to the point where firm pressure would depress the tips.
  • We reconnected the in-vacuum cabling. In ≈15 places we opted to omit the Type 1 cable and use a F-F gender bender.
  • We reconnected all but four of the in-air cables.

Plan for week of 6/26

Mark and Enzo at Kamioka:

  • Double-check where gender-benders were used.
  • Finish connecting in-air cabling.
  • Debug all cabling.
  • Work with Simon to set up LSOL.

Fabian at Mitaka:

  • Design final ballast masses for IM, BF and SF assuming no BF rebuild (needs to be adaptable).
  • Check all items for BS flag/prism gluing are available (prisms, flags, jigs, mirror box, glue, scale, mixing tools etc).

Hirata-san at Mitaka:

  • Do new 3D CAD:
    • BS Test Hang build, with top of tank, full suspension, and LBB damper all reversed.
    • Final BS build, as above, but with everything BF down rotated back to original.
      • In-tank version.
      • On-assembly-frame version. (Adjust jack positions if possible, or leave for Mark to do.)
    • SR2 on BS assembly frame. (Adjust jack positions if possible, or leave for Mark to do.)

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)