Line 6: Line 6:
  * Fabian, Mark and Liu-kun did BS installation at Kamioka:
   * Replaced the thrust bearing in the BF with a stainless version. While replacing the picomotor spring, they found several issues with screws.
   * Removed the sheet metal cable clamp on the bottom of the BF and installed a redesigned one.
   * They installed the "flying saucer" cable clamp on the maraging rod between the IM and BF, and attached the cables. There was an issue with the cables from the bottom OSEMs, which are too short by about 300 mm.
   * Ruspended the IM. Relative to the mass budget, about 700 g of trim mass had to be taken off to get good balance. There was also a problem with rubbing. It turned out that the keystone and the attached central PEEK coil former for the LVDT were at an angle, and the inside of the coil former was fouling on the outside of the pole piece for the magnets. It's not yet clear why the keystone was misaligned.
  * Hirata-san:
   * Made drawings of (revised) stub flag gluing jigs.
   * Worked on BS full-assembly drawings for Saito-sensei.
   * (For other groups)
    * Made a 3D model of maraging wires.
    * Finished making drawings of PRM inner frame.
    * Worked on re-setting up PC after crash.
 * Longer term to-do list
  * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
   * Part "disk security" top has to be modified - screw positions do not match.
  * Write more of payload assembly procedure (Fabian) - ONGOING
  * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING
  * Lower breadboard installation to be incorporated into the procedure document.
  * Work on BS simulation (Fabian)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)

 
  * Mark updated the BS circuit diagram [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600|D1503600]]:
   * Added information on the binary IO.
   * Renamed channels to conform to Okutomi-kun's new scheme.
   * Made the ADC/DAC channel assignment consistent and more logical.
   * Updated the stepper motor sections with info about the new driver chassis.
  * Mark and Hirata-san worked on collecting parts and tools that will be needed for cabling of the BS next week. (11 special-purpose cables need to be made for the picos/steppers/OSEMs/LVDT on the RM/IRM/IM/BF and, time permitting, 2 more for the SF.)
  * Mark worked on schedule.
  * Mark updated the installation procedure with lessons learned from the last few weeks.
  * Mark downloaded Hirata-san's Inventor model of the BS in the tank and starting thinking about installation of the suspension and lower bread board.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary
    • Mark updated the BS circuit diagram D1503600:

      • Added information on the binary IO.
      • Renamed channels to conform to Okutomi-kun's new scheme.
      • Made the ADC/DAC channel assignment consistent and more logical.
      • Updated the stepper motor sections with info about the new driver chassis.
    • Mark and Hirata-san worked on collecting parts and tools that will be needed for cabling of the BS next week. (11 special-purpose cables need to be made for the picos/steppers/OSEMs/LVDT on the RM/IRM/IM/BF and, time permitting, 2 more for the SF.)
    • Mark worked on schedule.
    • Mark updated the installation procedure with lessons learned from the last few weeks.
    • Mark downloaded Hirata-san's Inventor model of the BS in the tank and starting thinking about installation of the suspension and lower bread board.