 * Type B Past Week Summary
  * Fabian, Mark and Liu-kun did BS installation at Kamioka:
   * Debugged the issue with the BF keystone being tilted enough to cause rubbing on the yoke for the magnets. It was solved by moving the yoke ≈1 mm taking advantage of the oversized holes.
   * Measured the height of the payload as a function of trim mass. The BF spring seems to have a slightly lower load capacity and a rather higher spring constant than when it was remeasured by Hirata-san.
   * Removed IM trim mass to set the average height of the keystone to the CAD value.
   * Moved IM trim mass around to set the pitch of the dummy BS.
  * Hirata-san
   * TBD.
 
 * Hirata-san:
  * Updated the 3D assembly model for BS (among other issues, it turned out that parts were not correctly mated near where the suspension sits on the hydraulic jacks in the tank).
  * Liaised with IJECT.
  * Made an inventory for Type B (BS and SR).
  * Packed and shipped second winch to Kamioka.
  * Packed some jigs for adjusting BF blades.
  * Attended NINS information security seminar.
  * Attended the public hearing for the Opt-IR Research Division Chief Election.
 * Mark, Fabian, Enzo
  * Cabled IM picos and used IM yaw pico for adjusting RM. (Later, a wire broke at the connector, disabling the IM yaw, but we were able to continue by manually rotting the pic.)
  * Helped Takahashi-san in adjusting BF.
  * Initial round of adjustment made transverse perfect but overshot in longitudinal and made vertical unstable.
  * Second round of adjustment made vertical stable but left longitudinal offset.
  * Concluded that we can probably manage without bringing the BF back to Mitaka, but it will take some careful surveying of the existing offset and several more days of adjustment.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Hirata-san:
    • Updated the 3D assembly model for BS (among other issues, it turned out that parts were not correctly mated near where the suspension sits on the hydraulic jacks in the tank).
    • Liaised with IJECT.
    • Made an inventory for Type B (BS and SR).
    • Packed and shipped second winch to Kamioka.
    • Packed some jigs for adjusting BF blades.
    • Attended NINS information security seminar.
    • Attended the public hearing for the Opt-IR Research Division Chief Election.
  • Mark, Fabian, Enzo
    • Cabled IM picos and used IM yaw pico for adjusting RM. (Later, a wire broke at the connector, disabling the IM yaw, but we were able to continue by manually rotting the pic.)
    • Helped Takahashi-san in adjusting BF.
    • Initial round of adjustment made transverse perfect but overshot in longitudinal and made vertical unstable.
    • Second round of adjustment made vertical stable but left longitudinal offset.
    • Concluded that we can probably manage without bringing the BF back to Mitaka, but it will take some careful surveying of the existing offset and several more days of adjustment.