1699
Comment:
|
2433
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Hirata-san produced a near-final Inventor assembly of the BS on the assembly frame, for use in writing the assembly procedure. * Includes assembly frame modifications suggested by Mirapro, including feet, wheels, lifting eyes, thicker crossbars under BF, IM etc. * Includes final rail system except for interface plate to mirror box. * Includes full PI with ballast masses. * Includes cable clamps. * Includes correct versions of BF and SF. * Includes new BF pushrod parts to work around different placement of blade screws in new version of BF. * Includes cleanbag support bars. * Includes key parts of mirror box (enough to check for interference) - needs more work. * Does not include various invisible duplicate assemblies that had been present due to cut and paste. * After a few more improvements, the new assembly will be sent back to Mirapro. * Got status from Miyakawa-san on electronics - there should be enough of the boxes AEL is supplying. * Cleanbag design was finalized; Aso-san is ordering: [[attachment:160419-チャンバーカバーⅡ型.pdf]] * Quote for flags and prisms was received, but expensive - may drop rigid flag design. * The mirror box will require only very minor modifications for flags and prisms - Tatsumi-san will arrange immediately. * Fabian worked on understanding Sekiguchi-san's control design to help decide optimum wire thickness. * Mark worked on install procedure and schedule. * Takahashi-san enquired with NIKHEF about oscillator cards for LVDT chassis - lead time would be 3-4 months. * |
=== Type B (Mark) === ==== Report for week of 4/2 ==== * We received the SR3 but found Hirose-san had applied the First Contact patterns on the wrong sides, so we took it to Yamamoto-san's lab and Toyama University and re-applied the FC properly. We also bounced a 1064 nm beam off it to verify that the HR and AR coatings were not also swapped (they were OK). * We made magnet-standoff assemblies for both SR3 and SRM, and set up for gluing the prisms and magnets. We will attach the prisms and magnet-standoffs on Monday. * Hirata-san did inventory of the SR3/SRM payload parts received last week and started on the inventory of screws. * Fujii-kun, Enzo and team finished the preparation, adjustment and calibration of the SFs and BFs. * Fujii-kun and Yamamoto-kun got the SR3 real time model running. * Enzo finished setting up the SR3 and SRM racks. (The SRM rack still lacks a front-end, and power and network connections, but the SR3 is now ready for testing.) * Shoda-san worked on getting quotes for the ballast masses, on design of the SRM metal mass, and on splitting the BS model to reduce the load on the front-end computer. ==== Plan for week of 4/9 ==== * Shoda-san at Mitaka * Fujii-san at Mitaka * Tanioka-san at Mitaka? * Others at Kamioka * -- * Finish IMs and IRMs * Glue SR3 mirror ==== Plan for week of 4/16 ==== * Shoda-san at Mitaka * Fujii-san at Mitaka * Tanioka-san at Mitaka? * Others at Kamioka * -- * Build 1xRM * Start SR3 Hang * Align assembly frame. ==== Plan for week of 4/23 ==== * Shoda-san at Mitaka * Fujii-san at Mitaka? * Mark, Enzo at Kamioka * Hirata-san at Mitaka * Tanioka-san at Mitaka? * -- * Clean parts (cable clamp bases, etc, etc). * Observe KAGRA Phase 1 operations, assist if problems arise. ==== Plan for week of 4/30 ==== * Golden Week! ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] ==== Vacation Info ==== * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun) * Fabian vacation, 3/26-4/27 (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 4/2
- We received the SR3 but found Hirose-san had applied the First Contact patterns on the wrong sides, so we took it to Yamamoto-san's lab and Toyama University and re-applied the FC properly. We also bounced a 1064 nm beam off it to verify that the HR and AR coatings were not also swapped (they were OK).
- We made magnet-standoff assemblies for both SR3 and SRM, and set up for gluing the prisms and magnets. We will attach the prisms and magnet-standoffs on Monday.
- Hirata-san did inventory of the SR3/SRM payload parts received last week and started on the inventory of screws.
- Fujii-kun, Enzo and team finished the preparation, adjustment and calibration of the SFs and BFs.
- Fujii-kun and Yamamoto-kun got the SR3 real time model running.
- Enzo finished setting up the SR3 and SRM racks. (The SRM rack still lacks a front-end, and power and network connections, but the SR3 is now ready for testing.)
- Shoda-san worked on getting quotes for the ballast masses, on design of the SRM metal mass, and on splitting the BS model to reduce the load on the front-end computer.
Plan for week of 4/9
- Shoda-san at Mitaka
- Fujii-san at Mitaka
- Tanioka-san at Mitaka?
- Others at Kamioka
- --
- Finish IMs and IRMs
- Glue SR3 mirror
Plan for week of 4/16
- Shoda-san at Mitaka
- Fujii-san at Mitaka
- Tanioka-san at Mitaka?
- Others at Kamioka
- --
- Build 1xRM
- Start SR3 Hang
- Align assembly frame.
Plan for week of 4/23
- Shoda-san at Mitaka
- Fujii-san at Mitaka?
- Mark, Enzo at Kamioka
- Hirata-san at Mitaka
- Tanioka-san at Mitaka?
- --
- Clean parts (cable clamp bases, etc, etc).
- Observe KAGRA Phase 1 operations, assist if problems arise.
Plan for week of 4/30
- Golden Week!
To-Do Lists, Schedule
Vacation Info
- Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
- Fabian vacation, 3/26-4/27 (then gone).