Differences between revisions 8 and 301 (spanning 293 versions)
Revision 8 as of 2016-04-21 15:09:12
Size: 1699
Editor: MarkBarton
Comment:
Revision 301 as of 2018-07-06 14:10:34
Size: 3541
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Hirata-san produced a near-final Inventor assembly of the BS on the assembly frame, for use in writing the assembly procedure.
  * Includes assembly frame modifications suggested by Mirapro, including feet, wheels, lifting eyes, thicker crossbars under BF, IM etc.
  * Includes final rail system except for interface plate to mirror box.
  * Includes full PI with ballast masses.
  * Includes cable clamps.
  * Includes correct versions of BF and SF.
  * Includes new BF pushrod parts to work around different placement of blade screws in new version of BF.
  * Includes cleanbag support bars.
  * Includes key parts of mirror box (enough to check for interference) - needs more work.
  * Does not include various invisible duplicate assemblies that had been present due to cut and paste.
  * After a few more improvements, the new assembly will be sent back to Mirapro.
 * Got status from Miyakawa-san on electronics - there should be enough of the boxes AEL is supplying.
 * Cleanbag design was finalized; Aso-san is ordering: [[attachment:160419-チャンバーカバーⅡ型.pdf]]
 * Quote for flags and prisms was received, but expensive - may drop rigid flag design.
 * The mirror box will require only very minor modifications for flags and prisms - Tatsumi-san will arrange immediately.
 * Fabian worked on understanding Sekiguchi-san's control design to help decide optimum wire thickness.
 * Mark worked on install procedure and schedule.
 * Takahashi-san enquired with NIKHEF about oscillator cards for LVDT chassis - lead time would be 3-4 months.
 *
=== Type B (Mark) ===
==== Report for week of 7/2 ====
 * We double-checked the bounce frequency and it was indeed around 0.5 Hz with the CuBe auxiliary spring installed.
 * We prepared (but did not yet install) 6 arc weights for tuning the IP.
 * We unlocked the security structure from the assembly frame, and raised the whole system on the top jacks. We then unlocked the IP and adjusted the leveling so the IP was centered. We then had to loosen two of the poles at the top level of the security structure to make it vertical again, because it turns out that the jack receptacles (which also serve as the IP leg bases) are welded at very uneven depths in the bottom surface of the PI, so the IP and the bottom surface can't be level at once.
 * We debugged an issue with the height of the payload. It turns out that due to a buildup of errors (especially an extra 3 mm between the SF and BF), the payload is some 5-6 mm low with the F0 keystone at CAD height. Since the frequency is roughly independent of height around 0.5 Hz, we decided to go with a higher F0 keystone.
 * Enzo and Eleonora routed all the SF/... cables up to the PI.
 * We found we needed 4.7 kg of extra mass to get the desired keystone height, so we decided to put the third Cu segment (3.3 kg) back on, purely as ballast.
 * We put some extra small masses on the SF cap to level it. The suspension is now fully ballasted and trimmed except for 1 Promec mass (455 g) standing in for the new PI yaw stepper motor assembly (estimated 330 g) which is yet to arrive.
 * We took all the SR sat amps back to Mozumi to get new capacitors installed, and grabbed three spares for use while that is being done.
 * We investigated and documented Tanaka-san's watchdog for the BS, to see if the BIO Converter chassis that it uses could also drive reset lines for stepper motor driver boxes.
 * Hirata-san and Terrence characterized the last 4 F0 blades.
 * Hirata-san and Terrence installed blades in the top filter for SR2 and tuned it to 0.5 Hz (with the CuBe auxiliary spring) over three rounds of compression.


==== Plan for week of 7/9 ====
 * Mark, Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.
 * --
===== Main Sequence =====
 * Check/restore alignment of payload, especially optic pitch.
 * Install and cable geophones.
 * Install arc weights.
 * Tune IP.
 * Install, cable PI yaw stepper.
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM.
 * Calibrate PI LVDTs and FRs.
 * Cabling, testing, TFs.

===== F0/LBB Stuff ====
 * Finalize PI #1 for SR2; crane into SR2 cleanbooth.
 * Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position.
 * Set tank jacks to nominal height.
 * Clear space for PI #2 (SRM) work.

=== Plan for week of 7/16 ===
===== Main Sequence =====
 * Lock suspension.
 * Crane into tank.
 * Unlock suspension.
 * Rearrange cables.
 * Test.
===== F0/LBB Stuff =====
 * Install correct IP in PI #2.
 * Crane PI #2 to second floor.
 * Rebuild top filter of PI #2.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Vacation Info ====
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 7/2

  • We double-checked the bounce frequency and it was indeed around 0.5 Hz with the CuBe auxiliary spring installed.

  • We prepared (but did not yet install) 6 arc weights for tuning the IP.
  • We unlocked the security structure from the assembly frame, and raised the whole system on the top jacks. We then unlocked the IP and adjusted the leveling so the IP was centered. We then had to loosen two of the poles at the top level of the security structure to make it vertical again, because it turns out that the jack receptacles (which also serve as the IP leg bases) are welded at very uneven depths in the bottom surface of the PI, so the IP and the bottom surface can't be level at once.
  • We debugged an issue with the height of the payload. It turns out that due to a buildup of errors (especially an extra 3 mm between the SF and BF), the payload is some 5-6 mm low with the F0 keystone at CAD height. Since the frequency is roughly independent of height around 0.5 Hz, we decided to go with a higher F0 keystone.
  • Enzo and Eleonora routed all the SF/... cables up to the PI.
  • We found we needed 4.7 kg of extra mass to get the desired keystone height, so we decided to put the third Cu segment (3.3 kg) back on, purely as ballast.
  • We put some extra small masses on the SF cap to level it. The suspension is now fully ballasted and trimmed except for 1 Promec mass (455 g) standing in for the new PI yaw stepper motor assembly (estimated 330 g) which is yet to arrive.
  • We took all the SR sat amps back to Mozumi to get new capacitors installed, and grabbed three spares for use while that is being done.
  • We investigated and documented Tanaka-san's watchdog for the BS, to see if the BIO Converter chassis that it uses could also drive reset lines for stepper motor driver boxes.
  • Hirata-san and Terrence characterized the last 4 F0 blades.
  • Hirata-san and Terrence installed blades in the top filter for SR2 and tuned it to 0.5 Hz (with the CuBe auxiliary spring) over three rounds of compression.

Plan for week of 7/9

  • Mark, Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.
  • --

Main Sequence
  • Check/restore alignment of payload, especially optic pitch.
  • Install and cable geophones.
  • Install arc weights.
  • Tune IP.
  • Install, cable PI yaw stepper.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM.
  • Calibrate PI LVDTs and FRs.
  • Cabling, testing, TFs.

===== F0/LBB Stuff ====

  • Finalize PI #1 for SR2; crane into SR2 cleanbooth.
  • Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position.
  • Set tank jacks to nominal height.
  • Clear space for PI #2 (SRM) work.

Plan for week of 7/16

Main Sequence
  • Lock suspension.
  • Crane into tank.
  • Unlock suspension.
  • Rearrange cables.
  • Test.

F0/LBB Stuff
  • Install correct IP in PI #2.
  • Crane PI #2 to second floor.
  • Rebuild top filter of PI #2.

To-Do Lists, Schedule

Vacation Info

  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)