Differences between revisions 80 and 112 (spanning 32 versions)
Revision 80 as of 2016-11-03 15:16:08
Size: 1053
Editor: MarkBarton
Comment:
Revision 112 as of 2016-12-22 13:34:03
Size: 2022
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Mark updated the BS circuit diagram [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600|D1503600]]:
   * Added information on the binary IO.
   * Renamed channels to conform to Okutomi-kun's new scheme.
   * Made the ADC/DAC channel assignment consistent and more logical.
   * Updated the stepper motor sections with info about the new driver chassis.
  * Mark and Hirata-san worked on collecting parts and tools that will be needed for cabling of the BS next week. (11 special-purpose cables need to be made for the picos/steppers/OSEMs/LVDT on the RM/IRM/IM/BF and, time permitting, 2 more for the SF.)
  * Mark worked on schedule.
  * Mark updated the installation procedure with lessons learned from the last few weeks.
  * Mark downloaded Hirata-san's Inventor model of the BS in the tank and starting thinking about installation of the suspension and lower bread board.
 * Activity report for week of 12/19
  * Hirata-san made (and Fabian and Mark checked) drawings and parts/fastener lists for the SRM/PRM order and various others: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5964| D1605964]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5965| D1605965]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5956| D1605956]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5963| D1605963]], [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5977|D1605977]], etc.
  * Fabian designed a simple two-piece hold-down device to immobilize the SRx IMs during the optic and RM hanging. It avoids having to remachine all the IM support bars to allow for hold-down screws. The Type Bp team might also want to use it.
  * Aso-san and Mark discussed the [[KAGRA/Subgroups/VIS/VISMinutes20161216#BFIssue|BF issue]] from last week.
   * It was decided to ask Takahashi-san to take a look at the BF while he's at Kamioka this week.
   * It was decided to have the BS bottom filter moved to Mitaka for tuneup and adjustment as soon as possible in the new year.
  * Raffaele, Aso-san, Mark and Fabian discussed having much smaller/shorter BS and SR stub flags plus longer, coil-only OSEMs.
   * Aso-san volunteered to do the OSEM design.
   * Hirata-san made Pack'n'Go archives of the existing designs as a baseline for Aso-san.
  * Hirata-san searched for missing PR mirror box parts.
  * Miyakawa-san finished recabling the PR2 rack and got the BS real-time model running again. (The problem had been a new requirement for a safe.snap file to be provided in the burt directory, which was imposed by RCG2.9.7.) The model still needs lots of work, but it has the OSEM functionality needed for the next test-hang stage, plus Okutomi-san's improvements.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Activity report for week of 12/19
    • Hirata-san made (and Fabian and Mark checked) drawings and parts/fastener lists for the SRM/PRM order and various others: D1605964, D1605965, D1605956, D1605963, D1605977, etc.

    • Fabian designed a simple two-piece hold-down device to immobilize the SRx IMs during the optic and RM hanging. It avoids having to remachine all the IM support bars to allow for hold-down screws. The Type Bp team might also want to use it.
    • Aso-san and Mark discussed the BF issue from last week.

      • It was decided to ask Takahashi-san to take a look at the BF while he's at Kamioka this week.
      • It was decided to have the BS bottom filter moved to Mitaka for tuneup and adjustment as soon as possible in the new year.
    • Raffaele, Aso-san, Mark and Fabian discussed having much smaller/shorter BS and SR stub flags plus longer, coil-only OSEMs.
      • Aso-san volunteered to do the OSEM design.
      • Hirata-san made Pack'n'Go archives of the existing designs as a baseline for Aso-san.
    • Hirata-san searched for missing PR mirror box parts.
    • Miyakawa-san finished recabling the PR2 rack and got the BS real-time model running again. (The problem had been a new requirement for a safe.snap file to be provided in the burt directory, which was imposed by RCG2.9.7.) The model still needs lots of work, but it has the OSEM functionality needed for the next test-hang stage, plus Okutomi-san's improvements.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)