Differences between revisions 80 and 202 (spanning 122 versions)
Revision 80 as of 2016-11-03 15:16:08
Size: 1053
Editor: MarkBarton
Comment:
Revision 202 as of 2017-11-10 08:29:33
Size: 914
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Mark updated the BS circuit diagram [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600|D1503600]]:
   * Added information on the binary IO.
   * Renamed channels to conform to Okutomi-kun's new scheme.
   * Made the ADC/DAC channel assignment consistent and more logical.
   * Updated the stepper motor sections with info about the new driver chassis.
  * Mark and Hirata-san worked on collecting parts and tools that will be needed for cabling of the BS next week. (11 special-purpose cables need to be made for the picos/steppers/OSEMs/LVDT on the RM/IRM/IM/BF and, time permitting, 2 more for the SF.)
  * Mark worked on schedule.
  * Mark updated the installation procedure with lessons learned from the last few weeks.
  * Mark downloaded Hirata-san's Inventor model of the BS in the tank and starting thinking about installation of the suspension and lower bread board.
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Fabian, Enzo, Hirata-san):
 * Hirata-san published his inventory of SR parts on Dropbox.
 * Mark and Enzo finalized the geometry matrices for the IP, entered them in MEDM and updated the safe.snap.
 * Mark, Enzo and Fabian worked with Izumi-san et al. to align the BS. We got the +Y beam fairly close to aligned (to the second gate valve, near IY).

==== Plan for week of 11/13 ====

Kamioka: Mark
 * Attend commissioning workshop at U Toyama.
 * Be person-on-site for BF work.
 * Set up for mirror gluing.

Mitaka: Fabian and Hirata-san
 * SR procurement.
 * New PI GAS FR design.
 * BS LBB ballast mass design.
 * SR cable lamp design.

Mitaka: Enzo and Kozu-kun (Wed, Thu)
 * Servos
 * TFs of BF
 * Documentation

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Enzo, Hirata-san):

  • Hirata-san published his inventory of SR parts on Dropbox.
  • Mark and Enzo finalized the geometry matrices for the IP, entered them in MEDM and updated the safe.snap.
  • Mark, Enzo and Fabian worked with Izumi-san et al. to align the BS. We got the +Y beam fairly close to aligned (to the second gate valve, near IY).

Plan for week of 11/13

Kamioka: Mark

  • Attend commissioning workshop at U Toyama.
  • Be person-on-site for BF work.
  • Set up for mirror gluing.

Mitaka: Fabian and Hirata-san

  • SR procurement.
  • New PI GAS FR design.
  • BS LBB ballast mass design.
  • SR cable lamp design.

Mitaka: Enzo and Kozu-kun (Wed, Thu)

  • Servos
  • TFs of BF
  • Documentation

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)