Differences between revisions 81 and 302 (spanning 221 versions)
Revision 81 as of 2016-11-04 11:08:28
Size: 1472
Editor: MarkBarton
Comment:
Revision 302 as of 2018-07-06 14:12:21
Size: 3632
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Mark
   * Updated the BS circuit diagram [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600|D1503600]]:
    * Added information on the binary IO.
    * Renamed channels to conform to Okutomi-kun's new scheme.
    * Made the ADC/DAC channel assignment consistent and more logical.
    * Updated the stepper motor sections with info about the new driver chassis.
   * Worked on schedule.
   * Updated the installation procedure with lessons learned from the last few weeks.
   * Downloaded Hirata-san's Inventor model of the BS in the tank and starting thinking about installation of the suspension and lower bread board.
   * Mark and Hirata-san worked on collecting parts and tools that will be needed for cabling of the BS next week. (11 special-purpose cables need to be made for the picos/steppers/OSEMs/LVDT on the RM/IRM/IM/BF and, time permitting, 2 more for the SF.)
  * Hirata-san
   * Updated the BS 3D Assembly with the new rods and receptacles.
   * Made 2D drawings of SR2 and SR3 (ongoing).
   * Made SRM 3D assembly (ongoing)
   * Asked for and got quotes for hexagon cable clamps. Takahashi-san ordered the PEEK components. Next week Hirata-san will look for parts that should already be at Kamioka.
   * Washed screws for hexagon cable clamps and shim rings for Fabian.
=== Type B (Mark) ===
==== Report for week of 7/2 ====
 * We double-checked the bounce frequency and it was indeed around 0.5 Hz with the CuBe auxiliary spring installed.
 * We prepared (but did not yet install) 6 arc weights for tuning the IP.
 * We unlocked the security structure from the assembly frame, and raised the whole system on the top jacks. We then unlocked the IP and adjusted the leveling so the IP was centered. We then had to loosen two of the poles at the top level of the security structure to make it vertical again, because it turns out that the jack receptacles (which also serve as the IP leg bases) are welded at very uneven depths in the bottom surface of the PI, so the IP and the bottom surface can't be level at once.
 * We debugged an issue with the height of the payload. It turns out that due to a buildup of errors (especially an extra 3 mm between the SF and BF), the payload is some 5-6 mm low with the F0 keystone at CAD height. Since the frequency is roughly independent of height around 0.5 Hz, we decided to go with a higher F0 keystone.
 * Enzo and Eleonora routed all the SF/... cables up to the PI.
 * We found we needed 4.7 kg of extra mass to get the desired keystone height, so we decided to put the third Cu segment (3.3 kg) back on, purely as ballast.
 * We put some extra small masses on the SF cap to level it. The suspension is now fully ballasted and trimmed except for 1 Promec mass (455 g) standing in for the new PI yaw stepper motor assembly (estimated 330 g) which is yet to arrive.
 * We took all the SR sat amps back to Mozumi to get new capacitors installed, and grabbed three spares for use while that is being done.
 * We investigated and documented Tanaka-san's watchdog for the BS, to see if the BIO Converter chassis that it uses could also drive reset lines for stepper motor driver boxes.
 * Hirata-san and Terrence characterized the last 4 F0 blades.
 * Hirata-san and Terrence installed blades in the top filter for SR2 and tuned it to 0.5 Hz (with the CuBe auxiliary spring) over three rounds of compression.


==== Plan for week of 7/9 ====
 * Mark, Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.
===== Main Sequence =====
 * Check/restore alignment of payload, especially optic pitch.
 * Install and cable geophones.
 * Install arc weights.
 * Tune IP.
 * Install, cable PI yaw stepper.
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM.
 * Calibrate PI LVDTs and FRs.
 * Cabling, testing, TFs.

===== F0/LBB Stuff =====
 * Finalize PI #1 for SR2; crane into SR2 cleanbooth.
 * Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position.
 * Set tank jacks to nominal height.
 * Clear space for PI #2 (SRM) work.

==== Plan for week of 7/16 ====
 * Monday 7/16 is Sea Day.
 * Mark, Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri.
===== Main Sequence =====
 * Lock suspension.
 * Crane into tank.
 * Unlock suspension.
 * Rearrange cables.
 * Test.
===== F0/LBB Stuff =====
 * Install correct IP in PI #2.
 * Crane PI #2 to second floor.
 * Rebuild top filter of PI #2.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Vacation Info ====
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 7/2

  • We double-checked the bounce frequency and it was indeed around 0.5 Hz with the CuBe auxiliary spring installed.

  • We prepared (but did not yet install) 6 arc weights for tuning the IP.
  • We unlocked the security structure from the assembly frame, and raised the whole system on the top jacks. We then unlocked the IP and adjusted the leveling so the IP was centered. We then had to loosen two of the poles at the top level of the security structure to make it vertical again, because it turns out that the jack receptacles (which also serve as the IP leg bases) are welded at very uneven depths in the bottom surface of the PI, so the IP and the bottom surface can't be level at once.
  • We debugged an issue with the height of the payload. It turns out that due to a buildup of errors (especially an extra 3 mm between the SF and BF), the payload is some 5-6 mm low with the F0 keystone at CAD height. Since the frequency is roughly independent of height around 0.5 Hz, we decided to go with a higher F0 keystone.
  • Enzo and Eleonora routed all the SF/... cables up to the PI.
  • We found we needed 4.7 kg of extra mass to get the desired keystone height, so we decided to put the third Cu segment (3.3 kg) back on, purely as ballast.
  • We put some extra small masses on the SF cap to level it. The suspension is now fully ballasted and trimmed except for 1 Promec mass (455 g) standing in for the new PI yaw stepper motor assembly (estimated 330 g) which is yet to arrive.
  • We took all the SR sat amps back to Mozumi to get new capacitors installed, and grabbed three spares for use while that is being done.
  • We investigated and documented Tanaka-san's watchdog for the BS, to see if the BIO Converter chassis that it uses could also drive reset lines for stepper motor driver boxes.
  • Hirata-san and Terrence characterized the last 4 F0 blades.
  • Hirata-san and Terrence installed blades in the top filter for SR2 and tuned it to 0.5 Hz (with the CuBe auxiliary spring) over three rounds of compression.

Plan for week of 7/9

  • Mark, Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.

Main Sequence
  • Check/restore alignment of payload, especially optic pitch.
  • Install and cable geophones.
  • Install arc weights.
  • Tune IP.
  • Install, cable PI yaw stepper.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM.
  • Calibrate PI LVDTs and FRs.
  • Cabling, testing, TFs.

F0/LBB Stuff
  • Finalize PI #1 for SR2; crane into SR2 cleanbooth.
  • Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position.
  • Set tank jacks to nominal height.
  • Clear space for PI #2 (SRM) work.

Plan for week of 7/16

  • Monday 7/16 is Sea Day.
  • Mark, Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri.

Main Sequence
  • Lock suspension.
  • Crane into tank.
  • Unlock suspension.
  • Rearrange cables.
  • Test.

F0/LBB Stuff
  • Install correct IP in PI #2.
  • Crane PI #2 to second floor.
  • Rebuild top filter of PI #2.

To-Do Lists, Schedule

Vacation Info

  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)