Line 5: Line 5:
 * Type B Past Week Summary
  * Mark and Hirata-san at Mitaka
   * Gathered parts for cable making.
  * Mark and Hirata-san at Kamioka:
   * Replaced the floor panels that had been taken from the PR2 area (filling in the hole in the floor) and found/installed two new panels to act as bridges near the BS assembly frame.
   * Installed two more LPCDs and the stepper motor driver in the PR2 rack.
   * Ran cables from the rack to the second and third sat amps (for the IRM OSEMs).
   * Added a second DIO card in the rack and connected it to the BIO inputs and outputs of the new LPCDs.
   * Started making extension cables for RM-H2 and -H3 OSEMs but gave up due to complicated grounding arrangement.
   * Washed four 40-cm D-Sub-9 ribbon cables to use as temporary extensions (maybe also for H1/H4).
   * Added extension to the IM pico cable for the BF yaw pico.
   * Made LVDT adapter cable.
  * Mark worked on schedule.
 * Hirata-san:
  * Made cables for LVDT.
  * Made drawings for new wire clamps.
  * Asked ATC for manufacturing parts.(and modified drawings.)
  * Asked quotes for SDC coating for hooks.
  * Sent packing tools for BF.
  * Talked with i-ject about quotes for payload.
 * Mark and Fabian at Kamioka (plus Enzo for 2 days):
  * Finished rebalance of IM
  * Reinstalled IRM, adjusted OSEMs
  * Replaced broken Type 3 cable on IM-H1 OSEM.
  * Fixed issues with k1visbs real-time model.
  * Started TFs from IRM OSEMs to IRM and IM OSEMs.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Hirata-san:
    • Made cables for LVDT.
    • Made drawings for new wire clamps.
    • Asked ATC for manufacturing parts.(and modified drawings.)
    • Asked quotes for SDC coating for hooks.
    • Sent packing tools for BF.
    • Talked with i-ject about quotes for payload.
  • Mark and Fabian at Kamioka (plus Enzo for 2 days):
    • Finished rebalance of IM
    • Reinstalled IRM, adjusted OSEMs
    • Replaced broken Type 3 cable on IM-H1 OSEM.
    • Fixed issues with k1visbs real-time model.
    • Started TFs from IRM OSEMs to IRM and IM OSEMs.