* Type B Past Week Summary * Mark and Hirata-san at Mitaka * Gathered parts for cable making. * Mark and Hirata-san at Kamioka: * Replaced the floor panels that had been taken from the PR2 area (filling in the hole in the floor) and found/installed two new panels to act as bridges near the BS assembly frame. * Installed two more LPCDs and the stepper motor driver in the PR2 rack. * Ran cables from the rack to the second and third sat amps (for the IRM OSEMs). * Added a second DIO card in the rack and connected it to the BIO inputs and outputs of the new LPCDs. * Started making extension cables for RM-H2 and -H3 OSEMs but gave up due to complicated grounding arrangement. * Washed four 40-cm D-Sub-9 ribbon cables to use as temporary extensions (maybe also for H1/H4). * Added extension to the IM pico cable for the BF yaw pico. * Made LVDT adapter cable. * Mark worked on schedule. |
=== Type B (Mark) === ==== Past week report ==== At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun): * ==== Plan for week of 9/4 ==== Mark, Fabian, Enzo (Tue-Fri), Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun (Thu, Fri) * Retrieve PEEK piece from BF. * Crane SF back in. * Suspend BF/IRM/IM/RM/BS. * Test SF FR. * Calibrate SF LVDT. * Install SF cap; route cables. * Lift and weigh SF/BF/IRM/IM/RM/BS. * Adjust SF ballast. ==== Plan for week of 9/13 ==== Mark (except Wed), Fabian (except ASJ), Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun * Prepare magnet ring. * Bring in PI. * Route cables. * Suspend SF/..., adjust tilt of SF and total mass. * Adjust damper gap. ==== Vacation Info ==== Mark: 10/16-24 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
Plan for week of 9/4
Mark, Fabian, Enzo (Tue-Fri), Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun (Thu, Fri)
- Retrieve PEEK piece from BF.
- Crane SF back in.
- Suspend BF/IRM/IM/RM/BS.
- Test SF FR.
- Calibrate SF LVDT.
- Install SF cap; route cables.
- Lift and weigh SF/BF/IRM/IM/RM/BS.
- Adjust SF ballast.
Plan for week of 9/13
Mark (except Wed), Fabian (except ASJ), Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun
- Prepare magnet ring.
- Bring in PI.
- Route cables.
- Suspend SF/..., adjust tilt of SF and total mass.
- Adjust damper gap.
Vacation Info
Mark: 10/16-24