* Type B Past Week Summary * Mark and Hirata-san at Mitaka * Gathered parts for cable making. * Mark and Hirata-san at Kamioka: * Replaced the floor panels that had been taken from the PR2 area (filling in the hole in the floor) and found/installed two new panels to act as bridges near the BS assembly frame. * Installed two more LPCDs and the stepper motor driver in the PR2 rack. * Ran cables from the rack to the second and third sat amps (for the IRM OSEMs). * Added a second DIO card in the rack and connected it to the BIO inputs and outputs of the new LPCDs. * Started making extension cables for RM-H2 and -H3 OSEMs but gave up due to complicated grounding arrangement. * Washed four 40-cm D-Sub-9 ribbon cables to use as temporary extensions (maybe also for H1/H4). * Added extension to the IM pico cable for the BF yaw pico. * Made LVDT adapter cable. * Mark worked on schedule. |
=== Type B (Mark) === ==== Past week report ==== * Mark and Fabian did a huge cleanup of the SR2 area and prepared a workspace for assembling the IM. * Fabian did a stocktake of the screws for the SR. * We have all we need for the IM, except one type that can be added after the rest of the IP is assembled. * We have most of what we need for the rest of the payload, and Hirata-san has ordered the others. * Hirata-san worked on SR procurement: * Suspension wire * SR additional parts (compensation masses, clamps etc) * Regular, SDC and BUMAX screws. * Additional machining on the BS sapphire prism jig to allow it to be used on the PR/SR mirror box. * LBB blade design. * Enzo and Kozu-kun (with help from Fujii-kun) worked on export from SUMCON to Matlab, and on filter design). ==== Plan for week of 11/20 ==== * Holiday on Thu 3/23 * All at Mitaka. * SR procurement, planning (Mark, Hirata-san) * SR mass budget (Fabian) * BS modeling filter design (Enzo, Kozu-kun) ==== Plan for week of 11/27 ==== * Fabian at commissioning workshop * |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
- Mark and Fabian did a huge cleanup of the SR2 area and prepared a workspace for assembling the IM.
- Fabian did a stocktake of the screws for the SR.
- We have all we need for the IM, except one type that can be added after the rest of the IP is assembled.
- We have most of what we need for the rest of the payload, and Hirata-san has ordered the others.
- Hirata-san worked on SR procurement:
- Suspension wire
- SR additional parts (compensation masses, clamps etc)
- Regular, SDC and BUMAX screws.
- Additional machining on the BS sapphire prism jig to allow it to be used on the PR/SR mirror box.
- LBB blade design.
- Enzo and Kozu-kun (with help from Fujii-kun) worked on export from SUMCON to Matlab, and on filter design).
Plan for week of 11/20
- Holiday on Thu 3/23
- All at Mitaka.
- SR procurement, planning (Mark, Hirata-san)
- SR mass budget (Fabian)
- BS modeling filter design (Enzo, Kozu-kun)
Plan for week of 11/27
- Fabian at commissioning workshop