* Type B Past Week Summary * Mark and Hirata-san at Mitaka * Gathered parts for cable making. * Mark and Hirata-san at Kamioka: * Replaced the floor panels that had been taken from the PR2 area (filling in the hole in the floor) and found/installed two new panels to act as bridges near the BS assembly frame. * Installed two more LPCDs and the stepper motor driver in the PR2 rack. * Ran cables from the rack to the second and third sat amps (for the IRM OSEMs). * Added a second DIO card in the rack and connected it to the BIO inputs and outputs of the new LPCDs. * Started making extension cables for RM-H2 and -H3 OSEMs but gave up due to complicated grounding arrangement. * Washed four 40-cm D-Sub-9 ribbon cables to use as temporary extensions (maybe also for H1/H4). * Added extension to the IM pico cable for the BF yaw pico. * Made LVDT adapter cable. * Mark worked on schedule. |
=== Type B (Mark) === ==== Report for week of 5/28 ==== * Enzo redid the SR3 BIO connections to match the now-working BS setup. He also fixed PR2, which had a similar problem. * Enzo replaced LPCDs with HPCDs in the SR3. * Hirata-san and Kozu-kun continued tuning the filter in PI #3. Un ==== Plan for week of 6/11 ==== * Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri (Mon is compensation day for f2f.) * -- * Route cables through SF-BF flying saucer up to bottom of SF. * Add minimal ballast mass to SF (rough balance only) and weigh SF/... section. * Adjust BF trim mass. * Readjust payload. * Take TFs. * Cable, test SF LVDT and FR. * Add calculated ballast to SF. * Finish tuning F0 #3 for SR3. * Park F0 #1 (for SR2) in top of SR3 assembly frame. * Move F0 #3 behind SR3. * Move F0 #1 to "factory" area (in front of SRM) and start rebuild. ==== Plan for week of 6/18 ==== * Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri. * -- * Install PI. * Suspend SF/... section. * Lots of cabling. ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] ==== Vacation Info ==== |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 5/28
- Enzo redid the SR3 BIO connections to match the now-working BS setup. He also fixed PR2, which had a similar problem.
- Enzo replaced LPCDs with HPCDs in the SR3.
- Hirata-san and Kozu-kun continued tuning the filter in PI #3. Un
Plan for week of 6/11
- Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri (Mon is compensation day for f2f.)
- --
- Route cables through SF-BF flying saucer up to bottom of SF.
- Add minimal ballast mass to SF (rough balance only) and weigh SF/... section.
- Adjust BF trim mass.
- Readjust payload.
- Take TFs.
- Cable, test SF LVDT and FR.
- Add calculated ballast to SF.
- Finish tuning F0 #3 for SR3.
- Park F0 #1 (for SR2) in top of SR3 assembly frame.
- Move F0 #3 behind SR3.
- Move F0 #1 to "factory" area (in front of SRM) and start rebuild.
Plan for week of 6/18
- Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.
- --
- Install PI.
- Suspend SF/... section.
- Lots of cabling.