 * Type B Past Week Summary
  * Mark and Hirata-san worked at Kamioka, with valuable help from Enzo (on loan from Type Bp team).
  * We got all the adapter cables for the BF made (Hirata-san did some work on Monday at Mitaka).
  * We installed the extension for the BF yaw pico on the IM pico adapter cable.
  * We got all the in-vacuum and in-air cabling for the IM OSEMs done.
  * We tried to install the stepper and LVDT adapter cables but realized we didn't have enough information on which wires was which. (We later tracked this info down but did not have time to do anything with it - we would have needed to do the rest of the in-vacuum and in-air cabling and set up the stepper motor and LVDT drivers, so we concentrated on the OSEMs.)
  * We plugged in the IM OSEMs, set gains and offsets, and did a noise test (analysis and klog pending).
  * We mounted the OSEMs on the IRM and routed the cabling neatly.
  * We released the suspension.
  * We adjusted the OSEM mounting plates to center the OSEMs on the flags.
  * We adjusted the OSEMs in/out to midrange.
  * The suspension is now ready for OSEM-OSEM TFs!
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):
 * We removed the BF cap to debug the stepper motor. We checked the cabling but didn't find a problem. Eventually toggling the power to the driver box seemed to fix it.
 * We got the wheels removed from the two tall stepladders.
 * We started to rebalance the IM but came to realize that it was unstable for more than trivial pitch and roll (and had been for some time). We moved trim mass from top to bottom and it became unconditionally stable.
 * We rebalance the IM, put back the IRM and adjusted the OSEMs.
 * We took a successful TF in IM-L.
 * We added the security structure ring for below the SF and then added the SF. We noticed the cap is on at the wrong angle (so the keystone lock screws are inaccessible) but we can easily fix that.
 
==== Plan for coming weeks ====
Next week:
 * Everyone (Mark, Fabian, Enzo, Perry Hirata-san) at Kamioka, Monday-Friday except for Hirata-san Wednesday-Friday).
 * Finish SF installation.
 * Finish BF cabling, hang BF/IRM/IM/RM/BS from SF and confirm weight matches load capacity.
 * Re-trim BF as necessary.
 * Get picomotor driver working.
Week after next:
 * Everyone (Mark, Fabian, Enzo, Hirata-san) at Kamioka, Monday-Friday.
 * Prepare for PI installation.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):

  • We removed the BF cap to debug the stepper motor. We checked the cabling but didn't find a problem. Eventually toggling the power to the driver box seemed to fix it.
  • We got the wheels removed from the two tall stepladders.
  • We started to rebalance the IM but came to realize that it was unstable for more than trivial pitch and roll (and had been for some time). We moved trim mass from top to bottom and it became unconditionally stable.
  • We rebalance the IM, put back the IRM and adjusted the OSEMs.
  • We took a successful TF in IM-L.
  • We added the security structure ring for below the SF and then added the SF. We noticed the cap is on at the wrong angle (so the keystone lock screws are inaccessible) but we can easily fix that.

Plan for coming weeks

Next week:

  • Everyone (Mark, Fabian, Enzo, Perry Hirata-san) at Kamioka, Monday-Friday except for Hirata-san Wednesday-Friday).
  • Finish SF installation.
  • Finish BF cabling, hang BF/IRM/IM/RM/BS from SF and confirm weight matches load capacity.
  • Re-trim BF as necessary.
  • Get picomotor driver working.

Week after next:

  • Everyone (Mark, Fabian, Enzo, Hirata-san) at Kamioka, Monday-Friday.
  • Prepare for PI installation.