* Type B Past Week Summary * Mark and Hirata-san worked at Kamioka, with valuable help from Enzo (on loan from Type Bp team). * We got all the adapter cables for the BF made (Hirata-san did some work on Monday at Mitaka). * We installed the extension for the BF yaw pico on the IM pico adapter cable. * We got all the in-vacuum and in-air cabling for the IM OSEMs done. * We tried to install the stepper and LVDT adapter cables but realized we didn't have enough information on which wires was which. (We later tracked this info down but did not have time to do anything with it - we would have needed to do the rest of the in-vacuum and in-air cabling and set up the stepper motor and LVDT drivers, so we concentrated on the OSEMs.) * We plugged in the IM OSEMs, set gains and offsets, and did a noise test (analysis and klog pending). * We mounted the OSEMs on the IRM and routed the cabling neatly. * We released the suspension. * We adjusted the OSEM mounting plates to center the OSEMs on the flags. * We adjusted the OSEMs in/out to midrange. * The suspension is now ready for OSEM-OSEM TFs! |
=== Type B (Mark) === ==== Past week report ==== At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun): * We solved the problem with the OSEMs: cables had been plugged into the LED current monitor outputs, not the PD outputs. * We solved a problem with the real-time model freezing which turned out to be the IO chassis having lost power. * We took some mass off the IM to allow for the weight of the cables, and readjusted it in pitch and roll. * We aligned the IM ==== Plan for week of 8/28 ==== Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri). * Fix/adjust IRM OSEMs. * Add BF cap; cable and test BF-1 and BF-2 picos. * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass. * Crane in SF. * Suspend BF/IRM/IM/RM/BS. ==== Plan for week of 9/4 ==== * Install SF cap; route cables. * Lift and weigh SF/BF/IRM/IM/RM/BS. * Adjust SF ballast. ==== Vacation Info ==== Mark: TBD Mid-Oct |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
- We solved the problem with the OSEMs: cables had been plugged into the LED current monitor outputs, not the PD outputs.
- We solved a problem with the real-time model freezing which turned out to be the IO chassis having lost power.
- We took some mass off the IM to allow for the weight of the cables, and readjusted it in pitch and roll.
- We aligned the IM
Plan for week of 8/28
Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri).
- Fix/adjust IRM OSEMs.
- Add BF cap; cable and test BF-1 and BF-2 picos.
- Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
- Crane in SF.
- Suspend BF/IRM/IM/RM/BS.
Plan for week of 9/4
- Install SF cap; route cables.
- Lift and weigh SF/BF/IRM/IM/RM/BS.
- Adjust SF ballast.
Vacation Info
Mark: TBD Mid-Oct