Differences between revisions 86 and 136 (spanning 50 versions)
Revision 86 as of 2016-11-25 10:37:25
Size: 2146
Editor: MarkBarton
Comment:
Revision 136 as of 2017-04-07 13:21:26
Size: 2491
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Mark (with Enzo) did initial TFs on the BF.
   * Did fixed-sine TFs on individual OSEMs at low frequency to check actuator polarity (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2176 | 2176]] and [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2182|2182]]).
   * Set gains in the COILOUTF block to compensate for actuator polarity.
  * Mark (with Enzo) did a free-swing measurement on the BS after earthquake of 11/22 (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2182|2182]]).
   * Results suspicious (noted by Shoda-san): too much difference between OSEMs - horizontal showing much less motion than vertical.
   * Possible rubbing in horizontal.
   * May need a trip to Kamioka.
  * Mark (with Enzo) made corrections and improvements to many of the MEDM screens (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2176 | 2176]] and [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2182|2182]]).
   * Main overview screen was not generic in many places, and links to GDS_TP screens were broken.
   * ADC monitor screen referenced bad channels with LIGO-style names.
   * DAC monitor screen was not generic and did not support IM OSEMs.
   * Watchdog IM OSEM AC band limit filter screen was a copy of the TM one.
   * Watchdog TM OSEM AC band limit filter screen appears to be getting OL signals as input - needs model changes to fix.
   * The zoomed screens for IM OSEM centering were called incorrectly and did not work.
   * Various screens had LIGO-style channel names as labels.
  * Mark did a draft of D1603600-v12, including:
   * New assignment of IM OSEMs to DAQ channels (#4-9 are now V1, V2, V3, H1, H2, H3 rather than H1, H2, ...) from last Friday (the wiring was changed to reflect the model).
   * Information on how to identify the wires from the steppers and LVDTs so that the adapter cables can be plugged in properly.
  * Mark worked on schedule.
  * Hirata-san did drawings for new 8-mm maraging wires for Type A.
  * Hirata-san worked on PR/SR mirror box modifications with Shoda-san.
  
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):
 * We set things up again after the floor coating work.
 * We moved the PI into the second floor of the cleanbooth:
  * We cleared a path for the forklift (moving the portable cleanroom, worktable, power cables, vacuum pumps and other obstacles).
  * We got Saito-sensei to move the PI to the +Y side of the cleanbooth.
  * We washed and cling-wrapped a pallet.
  * We got Miyoki-san to disconnect the cables and curtain blocking the crane slot (and reconnect them afterwards).
  * We added some temporary crossbars in the top of the assembly frame and stored the SF cap on them to get it out of the way.
  * We craned in the pallet and set it up to bridge three floor joists.
  * We craned in the PI using Saito-san's adapter.
   * We couldn't find the original screws for the three PI transport plates so we substituted some others - fortunately there was no galling.
   * We had to connect the adapter to the crane with a sling because the ring for the hook was slightly too small).
 * We did a lot of cabling work:
  * We routed all the BF cables over the BF cap, up through the cable clamp on the SF-BF rod and up to the SF. (We had to redo a few because the Type 3 cable was at the flange end instead of the Type 1.)
  * We connected up the SF LVDT and FR stepper.
  * We started on rebalancing the BF (which had been perturbed by the weight and tension of all the cables). We got it rather better, but it needs more work.
  * We made another batch of anti-feedthrough adapters.

==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].

Week of 4/10:
 * Hirata-san does scissor lift training 4/10.
 * Perry in Tokyo 4/10.
 * Debug/fix dead OSEM channel, TM-H4.
 * Debug BF/SF LVDTs.
 * Adjust BF pitch/roll.
 * Do TF from SF LVDT actuation.
 * Install temporary ballast mass in SF.
 * Lift SF/BF/... section and check total weight and SF balance.
 * Continue swap of PI LVDT connectors (female->male)
 * Start preparing LBB spring units.
 * Install pico drivers in rack, create MEDM interface (with Miyo-kun), and undo temporary connection of picos to old controller and joystick.
Week of 4/17:
 * Crane in PI.
 * Connect SF/BF... section.
 * Temporarily remove PI and adjust SF ballast if necessary.
 

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):

  • We set things up again after the floor coating work.
  • We moved the PI into the second floor of the cleanbooth:
    • We cleared a path for the forklift (moving the portable cleanroom, worktable, power cables, vacuum pumps and other obstacles).
    • We got Saito-sensei to move the PI to the +Y side of the cleanbooth.
    • We washed and cling-wrapped a pallet.
    • We got Miyoki-san to disconnect the cables and curtain blocking the crane slot (and reconnect them afterwards).
    • We added some temporary crossbars in the top of the assembly frame and stored the SF cap on them to get it out of the way.
    • We craned in the pallet and set it up to bridge three floor joists.
    • We craned in the PI using Saito-san's adapter.
      • We couldn't find the original screws for the three PI transport plates so we substituted some others - fortunately there was no galling.
      • We had to connect the adapter to the crane with a sling because the ring for the hook was slightly too small).
  • We did a lot of cabling work:
    • We routed all the BF cables over the BF cap, up through the cable clamp on the SF-BF rod and up to the SF. (We had to redo a few because the Type 3 cable was at the flange end instead of the Type 1.)
    • We connected up the SF LVDT and FR stepper.
    • We started on rebalancing the BF (which had been perturbed by the weight and tension of all the cables). We got it rather better, but it needs more work.
    • We made another batch of anti-feedthrough adapters.

Plan for coming weeks

For more detail, see KAGRA/Subgroups/VIS/TypeB/ToDo.

Week of 4/10:

  • Hirata-san does scissor lift training 4/10.
  • Perry in Tokyo 4/10.
  • Debug/fix dead OSEM channel, TM-H4.
  • Debug BF/SF LVDTs.
  • Adjust BF pitch/roll.
  • Do TF from SF LVDT actuation.
  • Install temporary ballast mass in SF.
  • Lift SF/BF/... section and check total weight and SF balance.
  • Continue swap of PI LVDT connectors (female->male)

  • Start preparing LBB spring units.
  • Install pico drivers in rack, create MEDM interface (with Miyo-kun), and undo temporary connection of picos to old controller and joystick.

Week of 4/17:

  • Crane in PI.
  • Connect SF/BF... section.
  • Temporarily remove PI and adjust SF ballast if necessary.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)