Line 5: | Line 5: |
* Type B Past Week Summary * Mark (with Enzo) did initial TFs on the BF. * Did fixed-sine TFs on individual OSEMs at low frequency to check actuator polarity (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2176 | 2176]] and [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2182|2182]]). * Set gains in the COILOUTF block to compensate for actuator polarity. * Mark (with Enzo) did a free-swing measurement on the BS after earthquake of 11/22 (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2182|2182]]). * Results suspicious (noted by Shoda-san): too much difference between OSEMs - horizontal showing much less motion than vertical. * Possible rubbing in horizontal. * May need a trip to Kamioka. * Mark (with Enzo) made corrections and improvements to many of the MEDM screens (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2176 | 2176]] and [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2182|2182]]). * Main overview screen was not generic in many places, and links to GDS_TP screens were broken. * ADC monitor screen referenced bad channels with LIGO-style names. * DAC monitor screen was not generic and did not support IM OSEMs. * Watchdog IM OSEM AC band limit filter screen was a copy of the TM one. * Watchdog TM OSEM AC band limit filter screen appears to be getting OL signals as input - needs model changes to fix. * The zoomed screens for IM OSEM centering were called incorrectly and did not work. * Various screens had LIGO-style channel names as labels. * Mark did a draft of D1603600-v12, including: * New assignment of IM OSEMs to DAQ channels (#4-9 are now V1, V2, V3, H1, H2, H3 rather than H1, H2, ...) from last Friday (the wiring was changed to reflect the model). * Information on how to identify the wires from the steppers and LVDTs so that the adapter cables can be plugged in properly. * Mark worked on schedule. * Hirata-san did drawings for new 8-mm maraging wires for Type A. * Hirata-san worked on PR/SR mirror box modifications with Shoda-san. |
=== Type B (Mark) === ==== Past week report ==== At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun): * We installed the cut-down ballast mass under the IM and tweaked the IM height and balance. * We checked the range of the BF FR. * We adjusted the BF yoke by 2.5 mm to make it give ≈0 output for nominal height. * We found a good gain setting for the LVDT driver and calibrated the BF LVDT. * We set up the optical sensors facing the RM. * We assembled the IRM (with OSEMs) around the IM and got it mostly adjusted. * We changed the k1visbs model to restore the as-designed mapping of OSEMs to DAQ channels. * We confirmed that the BF LVDT actuation coil and the TM OSEM coils were working. * We connected up the IRM OSEMs (with the new Type 5-1.7 cables) but found there was an electrical issue: all the OSEMs are reading back the same constant value, around 1115. * We left the suspension in a state suitable for TFs from BF GAS actuation to sensing (in vertical) and from RM OSEM actuation to the optical sensors (in horizontal) over the weekend. At Mitaka (Hirata-san): * Hirata-san did 2D drawings of the SR LBB rods and sent off an RFQ. * Hirata-san did several cost-reduction negotiations with Mirapro. ==== Plan for week of 8/28 ==== Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri). * Fix/adjust IRM OSEMs. * Add BF cap; cable and test BF-1 and BF-2 picos. * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass. * Crane in SF. * Suspend BF/IRM/IM/RM/BS. ==== Plan for week of 9/4 ==== * Install SF cap; route cables. * Lift and weigh SF/BF/IRM/IM/RM/BS. * Adjust SF ballast. ==== Vacation Info ==== Mark: TBD Mid-Oct |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun):
- We installed the cut-down ballast mass under the IM and tweaked the IM height and balance.
- We checked the range of the BF FR.
- We adjusted the BF yoke by 2.5 mm to make it give ≈0 output for nominal height.
- We found a good gain setting for the LVDT driver and calibrated the BF LVDT.
- We set up the optical sensors facing the RM.
- We assembled the IRM (with OSEMs) around the IM and got it mostly adjusted.
- We changed the k1visbs model to restore the as-designed mapping of OSEMs to DAQ channels.
- We confirmed that the BF LVDT actuation coil and the TM OSEM coils were working.
- We connected up the IRM OSEMs (with the new Type 5-1.7 cables) but found there was an electrical issue: all the OSEMs are reading back the same constant value, around 1115.
- We left the suspension in a state suitable for TFs from BF GAS actuation to sensing (in vertical) and from RM OSEM actuation to the optical sensors (in horizontal) over the weekend.
At Mitaka (Hirata-san):
- Hirata-san did 2D drawings of the SR LBB rods and sent off an RFQ.
- Hirata-san did several cost-reduction negotiations with Mirapro.
Plan for week of 8/28
Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri).
- Fix/adjust IRM OSEMs.
- Add BF cap; cable and test BF-1 and BF-2 picos.
- Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
- Crane in SF.
- Suspend BF/IRM/IM/RM/BS.
Plan for week of 9/4
- Install SF cap; route cables.
- Lift and weigh SF/BF/IRM/IM/RM/BS.
- Adjust SF ballast.
Vacation Info
Mark: TBD Mid-Oct