Line 5: | Line 5: |
* Type B Past Week Summary * Mark (with Enzo) did initial TFs on the BF. * Did fixed-sine TFs on individual OSEMs at low frequency to check actuator polarity (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2176 | 2176]] and [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2182|2182]]). * Set gains in the COILOUTF block to compensate for actuator polarity. * Mark (with Enzo) did a free-swing measurement on the BS after earthquake of 11/22 (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2182|2182]]). * Results suspicious (noted by Shoda-san): too much difference between OSEMs - horizontal showing much less motion than vertical. * Possible rubbing in horizontal. * May need a trip to Kamioka. * Mark (with Enzo) made corrections and improvements to many of the MEDM screens (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2176 | 2176]] and [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2182|2182]]). * Main overview screen was not generic in many places, and links to GDS_TP screens were broken. * ADC monitor screen referenced bad channels with LIGO-style names. * DAC monitor screen was not generic and did not support IM OSEMs. * Watchdog IM OSEM AC band limit filter screen was a copy of the TM one. * Watchdog TM OSEM AC band limit filter screen appears to be getting OL signals as input - needs model changes to fix. * The zoomed screens for IM OSEM centering were called incorrectly and did not work. * Various screens had LIGO-style channel names as labels. * Mark did a draft of D1603600-v12, including: * New assignment of IM OSEMs to DAQ channels (#4-9 are now V1, V2, V3, H1, H2, H3 rather than H1, H2, ...) from last Friday (the wiring was changed to reflect the model). * Information on how to identify the wires from the steppers and LVDTs so that the adapter cables can be plugged in properly. * Mark worked on schedule. * Hirata-san did drawings for new 8-mm maraging wires for Type A. * Hirata-san worked on PR/SR mirror box modifications with Shoda-san. |
=== Type B (Mark) === ==== Report for week of 2/19 ==== * We did TFs from the IM OSEMs. * We secured the cables inside the BF, added the cap and anchored the cables from below the BF to the cap. * We lifted the BF/... section with the load gauge adapter and measured the weight, which was about as expected. * Based on the measured weight, Fabian prepared an 800 g set of masses for the top of the BF. * We added the AF crossbars and the section of the SS below the SF and craned in the SF. * We installed the SF-BF rod and flying saucer and suspended the BF/... section. With the 800 g placed temporarily on the BF, the SF keystone floated at about mid-range. ==== Plan for week of 2/26 ==== * Shoda-san at Mitaka. * - * Enzo at Mitaka Mon 2/26. * '''Remove LBB temporary ballast masses from BS chamber.''' * Route cables up to under SF. * Check/adjust total mass and balance of BF/... section, especially IM OSEMs. * Cable and calibrate SF LVDT. * Add Cu segments to SF cap. * Install cap. * Lift SF/... section and check total mass and balance. ==== Plan for week of 3/5 ==== * Shoda-san at Mitaka. * Hirata-san vacation Mon 3/5, then Kamioka * Others at Kamioka. * - * Get SRM tank mushroom section installed (Hirata-san, Kimura-san) * SR3 rack setup. * Other tasks TBD. ==== Plan for week of 3/12 ==== * Shoda-san at Mitaka. * Mark at ASJ (Chiba) Fri 3/16. * Hirata-san vacation Mon 3/5, then Kamioka ==== Plan for week of 3/19 ==== * Mark at LVC meeting * Shoda-san, Fabian at Mitaka ==== Plan for week of 3/26 ==== * Mark vacation. * Others ??? ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] ==== Vacation Info ==== * Enzo Mitaka day 2/26 * Hirata-san vacation 3/5 * Hirata-san vacation Mon 3/5 * Fabian 3/26-4/27 vacation (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 2/19
- We did TFs from the IM OSEMs.
- We secured the cables inside the BF, added the cap and anchored the cables from below the BF to the cap.
- We lifted the BF/... section with the load gauge adapter and measured the weight, which was about as expected.
- Based on the measured weight, Fabian prepared an 800 g set of masses for the top of the BF.
- We added the AF crossbars and the section of the SS below the SF and craned in the SF.
- We installed the SF-BF rod and flying saucer and suspended the BF/... section. With the 800 g placed temporarily on the BF, the SF keystone floated at about mid-range.
Plan for week of 2/26
- Shoda-san at Mitaka.
- -
- Enzo at Mitaka Mon 2/26.
Remove LBB temporary ballast masses from BS chamber.
- Route cables up to under SF.
- Check/adjust total mass and balance of BF/... section, especially IM OSEMs.
- Cable and calibrate SF LVDT.
- Add Cu segments to SF cap.
- Install cap.
- Lift SF/... section and check total mass and balance.
Plan for week of 3/5
- Shoda-san at Mitaka.
- Hirata-san vacation Mon 3/5, then Kamioka
- Others at Kamioka.
- -
- Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
- SR3 rack setup.
- Other tasks TBD.
Plan for week of 3/12
- Shoda-san at Mitaka.
- Mark at ASJ (Chiba) Fri 3/16.
- Hirata-san vacation Mon 3/5, then Kamioka
Plan for week of 3/19
- Mark at LVC meeting
- Shoda-san, Fabian at Mitaka
Plan for week of 3/26
- Mark vacation.
- Others ???
To-Do Lists, Schedule
Vacation Info
- Enzo Mitaka day 2/26
- Hirata-san vacation 3/5
- Hirata-san vacation Mon 3/5
- Fabian 3/26-4/27 vacation (then gone).