 * Type B Past Week Summary
  * Mark (with Enzo) did initial TFs on the BF.
   * Did fixed-sine TFs on individual OSEMs at low frequency to check actuator polarity (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2176 | 2176]] and [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2182|2182]]).
   * Set gains in the COILOUTF block to compensate for actuator polarity.
  * Mark (with Enzo) did a free-swing measurement on the BS after earthquake of 11/22 (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2182|2182]]).
   * Results suspicious (noted by Shoda-san): too much difference between OSEMs - horizontal showing much less motion than vertical.
   * Possible rubbing in horizontal.
   * May need a trip to Kamioka.
  * Mark (with Enzo) made corrections and improvements to many of the MEDM screens (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2176 | 2176]] and [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2182|2182]]).
   * Main overview screen was not generic in many places, and links to GDS_TP screens were broken.
   * ADC monitor screen referenced bad channels with LIGO-style names.
   * DAC monitor screen was not generic and did not support IM OSEMs.
   * Watchdog IM OSEM AC band limit filter screen was a copy of the TM one.
   * Watchdog TM OSEM AC band limit filter screen appears to be getting OL signals as input - needs model changes to fix.
   * The zoomed screens for IM OSEM centering were called incorrectly and did not work.
   * Various screens had LIGO-style channel names as labels.
  * Mark did a draft of D1603600-v12, including:
   * New assignment of IM OSEMs to DAQ channels (#4-9 are now V1, V2, V3, H1, H2, H3 rather than H1, H2, ...) from last Friday (the wiring was changed to reflect the model so as to remain consistent with PRx).
   * Information on how to identify the wires from the steppers and LVDTs so that the adapter cables can be plugged in properly.
  * Mark worked on schedule.
  * Hirata-san did drawings for new 8-mm maraging wires for Type A.
  * Hirata-san worked on PR/SR mirror box modifications with Shoda-san.
  
=== Type B (Mark) ===
==== Report for week of 12/25 ====
 * Hirata-san got the L-brackets machined and washed, and installed them on the IM ring bars.
 * Shoda-san recovered the BS from the power outage on 12/25.
 * Miyakawa-san fixed an issue with the SR2 RTM which had prevented it from running.
 * Shoda-san, Hirata-san and Kozu-kun weighed the IM without ballast masses, and then added the lower masses and installed the IM on the assembly frame.
 * They cleaned the assembly frame and installed new jack receptacles on the load gauge adapter.
 * They installed the winch system on the IM, and inspected the clamp pieces for possible scratches.
 * They ran cables for the SR2 steppers and OSEMs.
 * They calibrated the BF LVDT.

==== Report for week of 1/4 ====
 * Mark fixed a number of errors with the Type B screens.

==== Report for week of 1/9 ====
 * We weighed the mirror in its box (and later the empty box), and the RM.
 * Fabian worked on the SR2/SR3/SRM mass budget and did an inventory of spare ballast masses.
 * We hung the SR2 and RM.
 * We assembled the bottom section of the security structure below the RM.
 * We cabled the RM OSEMs up to the IM.
 * Hirata-san gave up on waiting for a third quote for the blades and blade parts and started the ordering process.
 * Hirata-san got rod cable clamp parts from Takahashi-san and worked on drawings for the improved BS vertical and yaw adjusters.

==== Plan for week of 1/15 ====
 * Fabian at Mitaka Monday 1/15 to inspect filter load test items.
 * All at Kamioka.
 * Shoda-san to work on readjusting PR3 and also making OSEMs.
 * Enzo and Kozu-kun to help with making OSEMs.
 * Test RM OSEMs.
  * Check coil driver is successfully driving current.
  * Time permitting, do TF test from coils to optical sensor.
 * Suspend IM using load gauge adapter, and check/adjust total mass and balance.

==== Plan for week of 1/22 ====
 * All at Kamioka
 * Bring in BF and suspend IM.
 * Route final RM/IM cables up to below BF.
 * Recheck/adjust total mass and balance.
 * Route selected cables to flange.
 * Test IM picos and BF yaw pico.

==== Plan for week of 1/29 ====
 * Enzo at Mitaka 1/29 and most of 1/30, then vacation.
 * Kozu-kun away.
 * All others at Kamioka.
 * Build IRM around IM.
 * Cable/test/adjust IM OSEMs.
 * Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.

==== Vacation Info ====
 * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
 * Kozu-kun 1/29-2/2

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 12/25

  • Hirata-san got the L-brackets machined and washed, and installed them on the IM ring bars.
  • Shoda-san recovered the BS from the power outage on 12/25.
  • Miyakawa-san fixed an issue with the SR2 RTM which had prevented it from running.
  • Shoda-san, Hirata-san and Kozu-kun weighed the IM without ballast masses, and then added the lower masses and installed the IM on the assembly frame.
  • They cleaned the assembly frame and installed new jack receptacles on the load gauge adapter.
  • They installed the winch system on the IM, and inspected the clamp pieces for possible scratches.
  • They ran cables for the SR2 steppers and OSEMs.
  • They calibrated the BF LVDT.

Report for week of 1/4

  • Mark fixed a number of errors with the Type B screens.

Report for week of 1/9

  • We weighed the mirror in its box (and later the empty box), and the RM.
  • Fabian worked on the SR2/SR3/SRM mass budget and did an inventory of spare ballast masses.
  • We hung the SR2 and RM.
  • We assembled the bottom section of the security structure below the RM.
  • We cabled the RM OSEMs up to the IM.
  • Hirata-san gave up on waiting for a third quote for the blades and blade parts and started the ordering process.
  • Hirata-san got rod cable clamp parts from Takahashi-san and worked on drawings for the improved BS vertical and yaw adjusters.

Plan for week of 1/15

  • Fabian at Mitaka Monday 1/15 to inspect filter load test items.
  • All at Kamioka.
  • Shoda-san to work on readjusting PR3 and also making OSEMs.
  • Enzo and Kozu-kun to help with making OSEMs.
  • Test RM OSEMs.
    • Check coil driver is successfully driving current.
    • Time permitting, do TF test from coils to optical sensor.
  • Suspend IM using load gauge adapter, and check/adjust total mass and balance.

Plan for week of 1/22

  • All at Kamioka
  • Bring in BF and suspend IM.
  • Route final RM/IM cables up to below BF.
  • Recheck/adjust total mass and balance.
  • Route selected cables to flange.
  • Test IM picos and BF yaw pico.

Plan for week of 1/29

  • Enzo at Mitaka 1/29 and most of 1/30, then vacation.
  • Kozu-kun away.
  • All others at Kamioka.
  • Build IRM around IM.
  • Cable/test/adjust IM OSEMs.
  • Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.

Vacation Info

  • Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
  • Kozu-kun 1/29-2/2