 * Type B Past Week Summary
  * Mark (with Enzo) did initial TFs on the BF.
   * Did fixed-sine TFs on individual OSEMs at low frequency to check actuator polarity (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2176 | 2176]] and [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2182|2182]]).
   * Set gains in the COILOUTF block to compensate for actuator polarity.
  * Mark (with Enzo) did a free-swing measurement on the BS after earthquake of 11/22 (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2182|2182]]).
   * Results suspicious (noted by Shoda-san): too much difference between OSEMs - horizontal showing much less motion than vertical.
   * Possible rubbing in horizontal.
   * May need a trip to Kamioka.
  * Mark (with Enzo) made corrections and improvements to many of the MEDM screens (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2176 | 2176]] and [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2182|2182]]).
   * Main overview screen was not generic in many places, and links to GDS_TP screens were broken.
   * ADC monitor screen referenced bad channels with LIGO-style names.
   * DAC monitor screen was not generic and did not support IM OSEMs.
   * Watchdog IM OSEM AC band limit filter screen was a copy of the TM one.
   * Watchdog TM OSEM AC band limit filter screen appears to be getting OL signals as input - needs model changes to fix.
   * The zoomed screens for IM OSEM centering were called incorrectly and did not work.
   * Various screens had LIGO-style channel names as labels.
  * Mark did a draft of D1603600-v12, including:
   * New assignment of IM OSEMs to DAQ channels (#4-9 are now V1, V2, V3, H1, H2, H3 rather than H1, H2, ...) from last Friday (the wiring was changed to reflect the model so as to remain consistent with PRx).
   * Information on how to identify the wires from the steppers and LVDTs so that the adapter cables can be plugged in properly.
  * Mark worked on schedule.
  * Hirata-san did drawings for new 8-mm maraging wires for Type A.
  * Hirata-san worked on PR/SR mirror box modifications with Shoda-san.
  
=== Type B (Mark) ===
==== Report for week of 4/2 ====

 * Fujii-kun and Yamamoto-kun got the SR3 real time model running.
 * We received the SR3.
 * However Mark and Tanioka-kun found Hirose-san had applied the First Contact patterns on the wrong sides, so we took it to Yamamoto-san's lab and Toyama University and re-applied the FC properly. We also bounced a 1064 nm beam off it to verify that the HR and AR coatings were not also swapped (they were OK).
 * We made magnet-standoff assemblies for both SR3 and SRM, and set up for gluing the prisms and magnets. We will attach the prisms and magnet-standoffs on Monday.
 * Hirata-san did inventory of the SR3/SRM payload parts received last week and started on the inventory of screws.
 * Fujii-kun, Enzo and team finished the preparation, adjustment of the SFs and BFs.
 * They calibrated one SF and BF. (The remaining one SF and BF will take about another day. Also, the FR stops need to be checked.)
 * Enzo and Kozu-kun finished setting up the SR3 and SRM racks. (The SRM rack still lacks a front-end, and power and network connections, but the SR3 is now ready for testing.)
 * Shoda-san worked on getting quotes for the ballast masses, on design of the SRM metal mass, and on splitting the BS model to reduce the load on the front-end computer.

==== Plan for week of 4/9 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka
 * Tanioka-san at Kamioka, but possibly doing PEM stuff.
 * Others at Kamioka
 * --
 * Finish SRM BF and SF calibration
 * Finish IMs and IRMs
 * Glue SR3 mirror

==== Plan for week of 4/16 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka
 * Tanioka-san at Mitaka?
 * Others at Kamioka
 * --
 * Build 1xRM
 * Start SR3 Hang
  * Align assembly frame.

==== Plan for week of 4/23 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka?
 * Mark, Enzo at Kamioka
 * Hirata-san at Mitaka
 * Tanioka-san at Mitaka?
 * --
 * Clean parts (cable clamp bases, etc, etc).
 * Observe KAGRA Phase 1 operations, assist if problems arise.

==== Plan for week of 4/30 ====
  * Golden Week!

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]

==== Vacation Info ====
 * Fabian vacation, 3/26-4/27 (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 4/2

  • Fujii-kun and Yamamoto-kun got the SR3 real time model running.
  • We received the SR3.
  • However Mark and Tanioka-kun found Hirose-san had applied the First Contact patterns on the wrong sides, so we took it to Yamamoto-san's lab and Toyama University and re-applied the FC properly. We also bounced a 1064 nm beam off it to verify that the HR and AR coatings were not also swapped (they were OK).
  • We made magnet-standoff assemblies for both SR3 and SRM, and set up for gluing the prisms and magnets. We will attach the prisms and magnet-standoffs on Monday.
  • Hirata-san did inventory of the SR3/SRM payload parts received last week and started on the inventory of screws.
  • Fujii-kun, Enzo and team finished the preparation, adjustment of the SFs and BFs.
  • They calibrated one SF and BF. (The remaining one SF and BF will take about another day. Also, the FR stops need to be checked.)
  • Enzo and Kozu-kun finished setting up the SR3 and SRM racks. (The SRM rack still lacks a front-end, and power and network connections, but the SR3 is now ready for testing.)
  • Shoda-san worked on getting quotes for the ballast masses, on design of the SRM metal mass, and on splitting the BS model to reduce the load on the front-end computer.

Plan for week of 4/9

  • Shoda-san at Mitaka
  • Fujii-san at Mitaka
  • Tanioka-san at Kamioka, but possibly doing PEM stuff.
  • Others at Kamioka
  • --
  • Finish SRM BF and SF calibration
  • Finish IMs and IRMs
  • Glue SR3 mirror

Plan for week of 4/16

  • Shoda-san at Mitaka
  • Fujii-san at Mitaka
  • Tanioka-san at Mitaka?
  • Others at Kamioka
  • --
  • Build 1xRM
  • Start SR3 Hang
    • Align assembly frame.

Plan for week of 4/23

  • Shoda-san at Mitaka
  • Fujii-san at Mitaka?
  • Mark, Enzo at Kamioka
  • Hirata-san at Mitaka
  • Tanioka-san at Mitaka?
  • --
  • Clean parts (cable clamp bases, etc, etc).
  • Observe KAGRA Phase 1 operations, assist if problems arise.

Plan for week of 4/30

  • Golden Week!

To-Do Lists, Schedule

Vacation Info

  • Fabian vacation, 3/26-4/27 (then gone).

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)