* Type B Past Week Summary * Mark worked on task lists and schedule. * Mark worked on an update of the BS Electronic Items doc ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5111|E1505111]]) and started a SRx Electronics Items doc ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5886|E1605886]]). * Mark worked on an update of the In-Vacuum Cable doc ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3901|E1503901]]), including information on lengths that. * Fabian worked on a redesign of the EQ stops for the BS (2 of 4 screws under the RM are opposite large holes and there are no screws to restrain the RM front/back at either top or bottom). * Hirata-san worked on PR/SR mirror box modifications with Shoda-san. |
=== Type B (Mark) === ==== Past week report ==== At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun): * ==== Plan for week of 9/4 ==== Mark, Fabian, Enzo (Tue-Fri), Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun (Thu, Fri) * Retrieve PEEK piece from BF. * Crane SF back in. * Suspend BF/IRM/IM/RM/BS. * Test SF FR. * Calibrate SF LVDT. * Install SF cap; route cables. * Lift and weigh SF/BF/IRM/IM/RM/BS. * Adjust SF ballast. ==== Plan for week of 9/13 ==== Mark (except Wed), Fabian (except ASJ), Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun * Prepare magnet ring. * Bring in PI. * Route cables. * Suspend SF/..., adjust tilt of SF and total mass. * Adjust damper gap. |
Line 12: | Line 28: |
==== Vacation Info ==== Mark: 10/16-24 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
Plan for week of 9/4
Mark, Fabian, Enzo (Tue-Fri), Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun (Thu, Fri)
- Retrieve PEEK piece from BF.
- Crane SF back in.
- Suspend BF/IRM/IM/RM/BS.
- Test SF FR.
- Calibrate SF LVDT.
- Install SF cap; route cables.
- Lift and weigh SF/BF/IRM/IM/RM/BS.
- Adjust SF ballast.
Plan for week of 9/13
Mark (except Wed), Fabian (except ASJ), Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun
- Prepare magnet ring.
- Bring in PI.
- Route cables.
- Suspend SF/..., adjust tilt of SF and total mass.
- Adjust damper gap.
Vacation Info
Mark: 10/16-24