Differences between revisions 91 and 145 (spanning 54 versions)
Revision 91 as of 2016-12-08 16:02:18
Size: 2006
Editor: MarkBarton
Comment:
Revision 145 as of 2017-05-19 13:20:59
Size: 3540
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Mark and Fabian debugged the rubbing issue with the BS. It turns out the EQ stops between the IRM and IM are so misaligned that they can't be used at all. This misalignment was noted on 10/17 klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2090|2090]] but seems to have gotten worse. With the stops removed, the OSEMs are still fairly well centered, so the problem probably predates the earthquake of 11/1.
 * Mark worked on the PR2 rack:
  * Rearranged the items in the rack to make space for new AA and AI chassis at the bottom near the IO chassis.
  * Replaced the AA chassis, which had had a group of channels marked as bad by Michimura-san.
  * Installed a second AA chassis and a second AI chassis in the rack.
  * Installed a second ADC card and a second DAC card in the IO chassis.
  * Modified the k1ioppr2 real-time model to recognize the new ADC/DAC cards and also the extra DIO cards installed previously.
  * Attempted to modify the k1visbs real-time model to recognize the new ADC/DAC cards. Unfortunately, apparently due to changes to library parts made by Okutomi-san, neither the original model or Okutomi-san's new model can be successfully compiled and installed anymore! Debugging is ongoing.
 * Fabian finished the redesign of the EQ stops for the BS RM. Hirata-san will refine the 3D design and do drawings (estimated 1/2 day).
 * Fabian redesigned the cable clamp on top of the multi-purpose cube (on the RM) to avoid the need for clips. (These are too easily moved if the cables are moved during installation and removal of the safety bar between the RM and IM, which has to be done many times.)
 * Mark and Fabian reviewed the previous iJect payload parts order and flagged the items that need updating.
 * Mark worked on task lists and schedule.
 * Hirata-san finished the PR/SR mirror box modifications.
 * Hirata-san washed parts (screws and collets).
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):
Line 20: Line 9:
    * We cleared space for the PR2 team to remove a bellows from their tank.
 * We installed safety bars on the pillars near the assembly frame at about waist height for someone on the tall ladder. We reinforced the clamps with cable ties.
 * We bridged a gap in the second floor on the -X side of the SF2 tank with spare floor panels.
 * We removed the PI from the assembly frame.
 * We encountered a problem with the PI-SF rod jamming in the SF. We finally got it out by clamping a pair of vice grips to the rod and hammering. We found that the receptacle part was the right size (7.0 mm) but had been deformed around the edge. Hirata-san used a knife and sandpaper to lean up the edge and then ultrasonically cleaned it.
 * We removed the LLB blade units from the PI, removed the blades from the clamps and sent the blades away for more rework to fix the length problem. Fortunately the tab section at the tip is fairly long, so we can just add a second hole further from the end.
 * We tested the SR fishing rod again, but it would only go up, not down. We found that reseting the driver fixed it, but we also moved the driver boxes into the cleanbooth to reduce the length of the motor cables. (To support the drivers, we had to run some long DC and LAN cables.)
 * We adjusted the limit nut on the SF fishing rod to increase the range.
 * We debugged an issue with the SF keystone sitting lower than previously and found we had accidentally left two eyebolts on top of the BF. We retrimmed the BF/... section to reset the keystone to nominal (65.5 mm) with the fishing rod at mid-range.
 * We removed one segment of the Cu ring on the SF cap and reconfigured the other two to be symmetrical.
 * Fabian designed a layout for the SF damper ring magnets that would work with the modified Cu ring, and placed the magnets with the template. The poles of the magnets were not on the expected faces so we had to stand the magnets up, with the 12x12 faces sideways and the 10x12 mm pole faces up/down. We will need to raise the magnet ring by 2 mm to allow for the extra height.
 * Hirata-san made an adapter cable for the PI vertical LVDT to let it connect to a standard Type 1 cable.
 * Enzo made a PI yaw/vertical stepper adapter cable and a trial geophone descrambler cable (one of three).
 * We placed the geophones on the PI but discovered we didn't have some mounting brackets called out in the 3D CAD.
 * Fabian added the remaining cable clamps to the PI.
 * We found that part of the problem with the SF LVDT was that the actuation had not been enabled for SF or F0 in the real-time model. We fixed the model and are now able to drive the LVDT actuator and see input at the LVDT sensor. However there is apparently a lot of coupling directly from output to input (presumably from transformer action between the sensing and actuation coils), so we're investigating.

==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].

Weeks of 5/22, 5/29:
 * Retest SF stepper every day, to see if problems recur.
 * Find/install geophone adapter plates or improvise replacement.
 * Reinstall PI, this time with rods and damper ring.
 * Reinstall PI-SF rod, this time with hex cable clamp.
 * Cable/test PI geophones LVDTs and steppers.
 * Reinstall LBB blade units.

 
 

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):

  • We cleared space for the PR2 team to remove a bellows from their tank.
  • We installed safety bars on the pillars near the assembly frame at about waist height for someone on the tall ladder. We reinforced the clamps with cable ties.
  • We bridged a gap in the second floor on the -X side of the SF2 tank with spare floor panels.
  • We removed the PI from the assembly frame.
  • We encountered a problem with the PI-SF rod jamming in the SF. We finally got it out by clamping a pair of vice grips to the rod and hammering. We found that the receptacle part was the right size (7.0 mm) but had been deformed around the edge. Hirata-san used a knife and sandpaper to lean up the edge and then ultrasonically cleaned it.
  • We removed the LLB blade units from the PI, removed the blades from the clamps and sent the blades away for more rework to fix the length problem. Fortunately the tab section at the tip is fairly long, so we can just add a second hole further from the end.
  • We tested the SR fishing rod again, but it would only go up, not down. We found that reseting the driver fixed it, but we also moved the driver boxes into the cleanbooth to reduce the length of the motor cables. (To support the drivers, we had to run some long DC and LAN cables.)
  • We adjusted the limit nut on the SF fishing rod to increase the range.
  • We debugged an issue with the SF keystone sitting lower than previously and found we had accidentally left two eyebolts on top of the BF. We retrimmed the BF/... section to reset the keystone to nominal (65.5 mm) with the fishing rod at mid-range.
  • We removed one segment of the Cu ring on the SF cap and reconfigured the other two to be symmetrical.
  • Fabian designed a layout for the SF damper ring magnets that would work with the modified Cu ring, and placed the magnets with the template. The poles of the magnets were not on the expected faces so we had to stand the magnets up, with the 12x12 faces sideways and the 10x12 mm pole faces up/down. We will need to raise the magnet ring by 2 mm to allow for the extra height.
  • Hirata-san made an adapter cable for the PI vertical LVDT to let it connect to a standard Type 1 cable.
  • Enzo made a PI yaw/vertical stepper adapter cable and a trial geophone descrambler cable (one of three).
  • We placed the geophones on the PI but discovered we didn't have some mounting brackets called out in the 3D CAD.
  • Fabian added the remaining cable clamps to the PI.
  • We found that part of the problem with the SF LVDT was that the actuation had not been enabled for SF or F0 in the real-time model. We fixed the model and are now able to drive the LVDT actuator and see input at the LVDT sensor. However there is apparently a lot of coupling directly from output to input (presumably from transformer action between the sensing and actuation coils), so we're investigating.

Plan for coming weeks

For more detail, see KAGRA/Subgroups/VIS/TypeB/ToDo.

Weeks of 5/22, 5/29:

  • Retest SF stepper every day, to see if problems recur.
  • Find/install geophone adapter plates or improvise replacement.
  • Reinstall PI, this time with rods and damper ring.
  • Reinstall PI-SF rod, this time with hex cable clamp.
  • Cable/test PI geophones LVDTs and steppers.
  • Reinstall LBB blade units.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)