Line 5: Line 5:
 * Mark and Fabian debugged the rubbing issue with the BS. It turns out the EQ stops between the IRM and IM are so misaligned that they can't be used at all. This misalignment was noted on 10/27 klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2090|2090]] but seems to have gotten worse. With the stops removed, the OSEMs (adjusted on 10/27) are still fairly well centered, so the problem probably predates the earthquake of 11/1.
 * Mark worked on the PR2 rack:
  * Rearranged the items in the rack to make space for new AA and AI chassis at the bottom near the IO chassis.
  * Replaced the AA chassis, which had had a group of channels marked as bad by Michimura-san.
  * Installed a second AA chassis and a second AI chassis in the rack.
  * Installed a second ADC card and a second DAC card in the IO chassis.
  * Modified the k1ioppr2 real-time model to recognize the new ADC/DAC cards and also the extra DIO cards installed previously.
  * Attempted to modify the k1visbs real-time model to recognize the new ADC/DAC cards. Unfortunately, apparently due to changes to library parts made by Okutomi-san, neither the original model or Okutomi-san's new model can be successfully compiled and installed anymore! Debugging is ongoing.
 * Fabian finished the redesign of the EQ stops for the BS RM. Hirata-san will refine the 3D design and do drawings (estimated 1/2 day).
 * Fabian redesigned the cable clamp on top of the multi-purpose cube (on the RM) to avoid the need for clips. (These are too easily moved if the cables are moved during installation and removal of the safety bar between the RM and IM, which has to be done many times.)
 * Mark and Fabian reviewed the previous iJect payload parts order and flagged the items that need updating.
 * Mark worked on task lists and schedule.
 * Hirata-san finished the PR/SR mirror box modifications.
 * Hirata-san washed parts (screws and collets).
=== Type B (Mark) ===
==== Past week report ====
 * Hirata-san:
  * Worked on the PR optic removal jig.
  * Worked on getting modified quotes for PR/SR/BS parts.
 * Enzo-san
  * Worked on getting his drivers license.
  * Worked on getting familiar with the Type B circuit diagram.
 * Mark, Fabian (at Kamioka):
  * Tried different strategies for getting the IRM-IM EQ stops and IRM OSEMs to line up simultaneously.
  * Realized that the main problem was that the pitch of the BS had changed relative to the IM (presumably due to slight slippage of the wires) so the IM had to be pitched up by 16 mrad to get the BS pitched slightly down (4.7 mrad).
  * Took the sides off the IRM to get access to the clamps and tightened them to prevent further slips.
  * Rebalanced the IM to be level in pitch (and roll).
  * Reassembled the IRM and aligned the IRM-IM EQ stops - this time it was easy.
  * Adjusted the IRM and RM OSEMs to mid-range.
  * Got Kokeyama's new real-time model working and started TFs.
Line 21: Line 22:
==== Plan for coming weeks ====
 * Mark and Enzo come to Kamioka and work on rack and cabling.
 * Fabian works on design, including SR assembly frame.
 * Hirata-san works on procurement.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • Hirata-san:
    • Worked on the PR optic removal jig.
    • Worked on getting modified quotes for PR/SR/BS parts.
  • Enzo-san
    • Worked on getting his drivers license.
    • Worked on getting familiar with the Type B circuit diagram.
  • Mark, Fabian (at Kamioka):
    • Tried different strategies for getting the IRM-IM EQ stops and IRM OSEMs to line up simultaneously.
    • Realized that the main problem was that the pitch of the BS had changed relative to the IM (presumably due to slight slippage of the wires) so the IM had to be pitched up by 16 mrad to get the BS pitched slightly down (4.7 mrad).
    • Took the sides off the IRM to get access to the clamps and tightened them to prevent further slips.
    • Rebalanced the IM to be level in pitch (and roll).
    • Reassembled the IRM and aligned the IRM-IM EQ stops - this time it was easy.
    • Adjusted the IRM and RM OSEMs to mid-range.
    • Got Kokeyama's new real-time model working and started TFs.

Plan for coming weeks

  • Mark and Enzo come to Kamioka and work on rack and cabling.
  • Fabian works on design, including SR assembly frame.
  • Hirata-san works on procurement.