Line 5: Line 5:
 * Mark and Fabian debugged the rubbing issue with the BS. It turns out the EQ stops between the IRM and IM are so misaligned that they can't be used at all. This misalignment was noted on 10/27 klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=2090|2090]] but seems to have gotten worse. With the stops removed, the OSEMs (adjusted on 10/27) are still fairly well centered, so the problem probably predates the earthquake of 11/1.
 * The IMM/IRM stops were removed, and Fabian installed the brackets that have EQ stop screws for the IRM. (Thus both the IM and IRM can be restrained independently, but not relatively.)
 * Mark worked on the PR2 rack:
  * Rearranged the items in the rack to make space for new AA and AI chassis at the bottom near the IO chassis.
  * Replaced the AA chassis, which had had a group of channels marked as bad by Michimura-san.
  * Installed a second AA chassis and a second AI chassis in the rack.
  * Installed a second ADC card and a second DAC card in the IO chassis.
  * Modified the k1ioppr2 real-time model to recognize the new ADC/DAC cards and also the extra DIO cards installed previously.
  * Attempted to modify the k1visbs real-time model to recognize the new ADC/DAC cards. Unfortunately, apparently due to changes to library parts made by Okutomi-san, neither the original model or Okutomi-san's new model can be successfully compiled and installed anymore! Debugging is ongoing.
 * Mark and Fabian did a stocktake of all the unused in-vacuum cables. There should be enough for the BS test hang.
 * Fabian finished the redesign of the EQ stops for the BS RM. Hirata-san will refine the 3D design and do drawings.
 * Fabian redesigned the cable clamp on top of the multi-purpose cube (on the BS RM) to avoid the need for clips. (These are too easily moved when the cables are moved during installation and removal of the safety bar between the RM and IM, which has to be done many times.) He will do a similar one for SR.
 * Mark and Fabian reviewed the previous IJECT payload parts order and flagged the items that need updating.
 * Mark worked on task lists and schedule, but the server still won't allow logins to upload anything.
 * Hirata-san finished the PR/SR mirror box modifications.
 * Hirata-san washed parts (screws and collets).
=== Type B (Mark) ===
==== Report for week of 2/26 ====
 * We routed all the cables from the BF level up via the flying saucer to the SF.
 * Hirata-san tried filing the SF cap to improve the fit, but without much success.
 * Hirata-san installed the Cu segments and cable clamps on the SF cap and the SF LVDT and FR cables.
 * We cabled and tested the BF cap picos and the SF LVDT and FR. (The LVDT still needs a full calibration.)
 * We worked on recovering the IM OSEM alignment.
Line 22: Line 13:
   ==== Plan for week of 2/26 ====
 * Shoda-san at Mitaka.
 * -
 * Enzo at Mitaka Mon 2/26.
 * '''Remove LBB temporary ballast masses from BS chamber.'''
 * Route cables up to under SF.
 * Check/adjust total mass and balance of BF/... section, especially IM OSEMs.
 * Cable and calibrate SF LVDT.
 * Add Cu segments to SF cap.
 * Install cap.
 * Lift SF/... section and check total mass and balance.

==== Plan for week of 3/5 ====
 * Shoda-san at Mitaka.
 * Hirata-san vacation Mon 3/5, then Kamioka
 * Others at Kamioka.
 * -
 * Finish recovering IM OSEM alignment.
 * Calibrate SF LVDT.
 * Weigh SF/... section.
 * Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
 * Set up for rebuilding of two BFs.

==== Plan for week of 3/12 ====
 * Shoda-san at Mitaka.
 * Mark at ASJ (Chiba) Fri, then Mitaka.
 * Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri
 * Others Kamioka Mon-Thu
 * Install boxes in SR3 and SRM racks.
 * Lay SR3 in-air cabling.
 * Continue rebuild of BFs.

==== Plan for week of 3/19 ====
 * Mark at LVC meeting
 * All others at Mitaka
 * Make two sets of IM OSEMs
 * Make last in-air pico adapter cable
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM.
 * Set up Dummy BS prism removal.

==== Plan for week of 3/26 ====
 * Mark vacation.
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * F0 Prototype Blade Test
  * Characterize blades.
  * Choose best set of three.
  * Remove cracked blades from filter in SRM area.
  * Set up test weights in SRM area, first floor.
  * Remove floor panel in SRM area, second floor.
  * Install chosen blades.
  * Measure load capacity.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]

==== Vacation Info ====
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Hirata-san vacation, Mon 3/5.
 * Fabian vacation, 3/26-4/27 (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 2/26

  • We routed all the cables from the BF level up via the flying saucer to the SF.
  • Hirata-san tried filing the SF cap to improve the fit, but without much success.
  • Hirata-san installed the Cu segments and cable clamps on the SF cap and the SF LVDT and FR cables.
  • We cabled and tested the BF cap picos and the SF LVDT and FR. (The LVDT still needs a full calibration.)
  • We worked on recovering the IM OSEM alignment.

Plan for week of 2/26

  • Shoda-san at Mitaka.
  • -
  • Enzo at Mitaka Mon 2/26.
  • Remove LBB temporary ballast masses from BS chamber.

  • Route cables up to under SF.
  • Check/adjust total mass and balance of BF/... section, especially IM OSEMs.
  • Cable and calibrate SF LVDT.
  • Add Cu segments to SF cap.
  • Install cap.
  • Lift SF/... section and check total mass and balance.

Plan for week of 3/5

  • Shoda-san at Mitaka.
  • Hirata-san vacation Mon 3/5, then Kamioka
  • Others at Kamioka.
  • -
  • Finish recovering IM OSEM alignment.
  • Calibrate SF LVDT.
  • Weigh SF/... section.
  • Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
  • Set up for rebuilding of two BFs.

Plan for week of 3/12

  • Shoda-san at Mitaka.
  • Mark at ASJ (Chiba) Fri, then Mitaka.
  • Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri
  • Others Kamioka Mon-Thu
  • Install boxes in SR3 and SRM racks.
  • Lay SR3 in-air cabling.
  • Continue rebuild of BFs.

Plan for week of 3/19

  • Mark at LVC meeting
  • All others at Mitaka
  • Make two sets of IM OSEMs
  • Make last in-air pico adapter cable
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM.
  • Set up Dummy BS prism removal.

Plan for week of 3/26

  • Mark vacation.
  • Shoda-san at Mitaka
  • Others at Kamioka
  • --
  • F0 Prototype Blade Test
    • Characterize blades.
    • Choose best set of three.
    • Remove cracked blades from filter in SRM area.
    • Set up test weights in SRM area, first floor.
    • Remove floor panel in SRM area, second floor.
    • Install chosen blades.
    • Measure load capacity.

To-Do Lists, Schedule

Vacation Info

  • Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
  • Hirata-san vacation, Mon 3/5.
  • Fabian vacation, 3/26-4/27 (then gone).