* Mark, Fabian and Enzo continued BS Test Hang work: * We installed the BF fishing rod stepper motor adaptor cable. * We tried to install the BF LVDT cable but first we encountered trouble routing it, and then several wires broke at the D-Sub end. * We laid 6 in-air cables from the tank to the PR2 rank for BF and SF picos, steppers and LVDTs. * We lifted the BF/IRM/IM/RM/BS section to weigh it and check its balance. * It was 195.6 kg, which is 18 kg(!) less than the capacity of the SF. * There was a major imbalance in roll: with all four built-in trim masses moved up the +Y end, it still needed 270 g of extra trim mass to be level. * Unfortunately when we put the payload, the IM was slightly yawed and ended up on the horizontal EQ stop screws. This let the IM-BF maraging rod go slack, which disturbed the leveling of the IM (because every time it is picked up the maraging rod settles in a different place, giving a different suspension point). We may have to partly disassemble the IRM and rearrange the time mass on the the IM. * We shipped BS mirror box parts to Shoda-san and components for a new LVDT cable to Hirata-san. * We posed for pictures of the BS by a team from National Geographic. * Hirata-san * Did parts and fastener lists for the SR payload. * Did a 3D model with the SR suspension on the BS assembly frame (to help Mark make adjustments to the frame design). * Did 2D drawings of Fabian's concept for BS EQ stop parts. * Did a 3D model of a wire clamp with replaceable jaw parts (to avoid having to reuse parts with scars from pressure). * Did 2D drawings of a new wire clamps for on top of the BS and SR RMs. |
=== Type B (Mark) === ==== Past week report ==== At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun): * We installed the cut-down ballast mass under the IM and tweaked the IM height and balance. * We checked the range of the BF FR. * We adjusted the BF yoke by 2.5 mm to make it give ≈0 output for nominal height. * We found a good gain setting for the LVDT driver and calibrated the BF LVDT. * We set up the optical sensors facing the RM. * We assembled the IRM (with OSEMs) around the IM and got it mostly adjusted. * We changed the k1visbs model to restore the as-designed mapping of OSEMs to DAQ channels. * We confirmed that the BF LVDT actuation coil and the TM OSEM coils were working. * We connected up the IRM OSEMs (with the new Type 5-1.7 cables) but found there was an electrical issue: all the OSEMs are reading back the same constant value, around 1115. * We left the suspension in a state suitable for TFs from BF GAS actuation to sensing (in vertical) and from RM OSEM actuation to the optical sensors (in horizontal) over the weekend. At Mitaka (Hirata-san): * He got quotes for the SR assembly frame and did cost-reduction negotiations with Aso-san and Mirapro. got quotes for assembly frame. * He did 2D drawings and a parts list for the divided LBB dampers. * He contacted a company about SDC. * He made a 3D model and drawings for the SR wire clamps. ==== Plan for week of 8/28 ==== Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri). * Fix/adjust IRM OSEMs. * Add BF cap; cable and test BF-1 and BF-2 picos. * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass. * Crane in SF. * Suspend BF/IRM/IM/RM/BS. ==== Plan for week of 9/4 ==== * Install SF cap; route cables. * Lift and weigh SF/BF/IRM/IM/RM/BS. * Adjust SF ballast. ==== Vacation Info ==== Mark: TBD Mid-Oct |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun):
- We installed the cut-down ballast mass under the IM and tweaked the IM height and balance.
- We checked the range of the BF FR.
- We adjusted the BF yoke by 2.5 mm to make it give ≈0 output for nominal height.
- We found a good gain setting for the LVDT driver and calibrated the BF LVDT.
- We set up the optical sensors facing the RM.
- We assembled the IRM (with OSEMs) around the IM and got it mostly adjusted.
- We changed the k1visbs model to restore the as-designed mapping of OSEMs to DAQ channels.
- We confirmed that the BF LVDT actuation coil and the TM OSEM coils were working.
- We connected up the IRM OSEMs (with the new Type 5-1.7 cables) but found there was an electrical issue: all the OSEMs are reading back the same constant value, around 1115.
- We left the suspension in a state suitable for TFs from BF GAS actuation to sensing (in vertical) and from RM OSEM actuation to the optical sensors (in horizontal) over the weekend.
At Mitaka (Hirata-san):
- He got quotes for the SR assembly frame and did cost-reduction negotiations with Aso-san and Mirapro.
got quotes for assembly frame.
- He did 2D drawings and a parts list for the divided LBB dampers.
- He contacted a company about SDC.
- He made a 3D model and drawings for the SR wire clamps.
Plan for week of 8/28
Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri).
- Fix/adjust IRM OSEMs.
- Add BF cap; cable and test BF-1 and BF-2 picos.
- Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
- Crane in SF.
- Suspend BF/IRM/IM/RM/BS.
Plan for week of 9/4
- Install SF cap; route cables.
- Lift and weigh SF/BF/IRM/IM/RM/BS.
- Adjust SF ballast.
Vacation Info