Size: 1797
Comment:
|
Size: 1519
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Mark, Fabian and Enzo continued BS Test Hang work: * We installed the BF fishing rod stepper motor adaptor cable. * We tried to install the BF LVDT cable but first we encountered trouble routing it, and then several wires broke at the D-Sub end. * We laid 6 in-air cables from the tank to the PR2 rank for BF and SF picos, steppers and LVDTs. * We lifted the BF/IRM/IM/RM/BS section to weigh it and check its balance. * It was 195.6 kg, which is 18 kg(!) less than the capacity of the SF. * There was a major imbalance in roll: with all four built-in trim masses moved up the +Y end, it still needed 270 g of extra trim mass to be level. * Unfortunately when we put the payload, the IM was slightly yawed and ended up on the horizontal EQ stop screws. This let the IM-BF maraging rod go slack, which disturbed the leveling of the IM (because every time it is picked up the maraging rod settles in a different place, giving a different suspension point). We may have to partly disassemble the IRM and rearrange the time mass on the the IM. * We shipped BS mirror box parts to Shoda-san and components for a new LVDT cable to Hirata-san. * We posed for pictures of the BS by a team from National Geographic. * Hirata-san * Did parts and fastener lists for the SR payload. * Did a 3D model with the SR suspension on the BS assembly frame (to help Mark make adjustments to the frame design). * Did 2D drawings of Fabian's concept for BS EQ stop parts. * Did a 3D model of a wire clamp with replaceable jaw parts (to avoid having to reuse parts with scars from pressure). * Did 2D drawings of a new wire clamps for on top of the BS and SR RMs. |
=== Type B (Mark) === ==== Report for week of 4/9 ==== * We packed away the SRM SF and BF. * After several failed attempts with one secondary prism, Mark finished the SR3 prism/magnet gluing. * Tanioka-kun built two IRMs (less OSEMs). * Enzo built an RM. * Kozu-kun and Enzo calibrated one set of 6 IM OSEMs for SR3. (6 OSEMs for SRM remain to be done.) * Hirata-san aligned the assembly frame, installed the interface bars and IM ring, and installed the IM. ==== Plan for week of 4/23 ==== * Hirata-san at Mitaka Mon-Tue, then Kamioka. * Tanioka-san at Kamioka Tue-Thu * Kozu-kun at Kamioka Wed-Fri (but working with PEM on Fri). * Others at Kamioka full week * -- * Start SR3 Hang * Hang optic. * Hang RM. * Cable RM OSEMs. ==== Plan for week of 4/30 ==== * Shoda-san at Mitaka. * Mark, Enzo at Kamioka Mon-Wed or TBD. * Others doing Golden Week stuff. * -- * Observe KAGRA Phase 1 operations, assist if problems arise. * Do BF TFs. * Continue SR3 hang. ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] ==== Vacation Info ==== * Fabian vacation, 3/26-4/27 (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 4/9
- We packed away the SRM SF and BF.
- After several failed attempts with one secondary prism, Mark finished the SR3 prism/magnet gluing.
- Tanioka-kun built two IRMs (less OSEMs).
- Enzo built an RM.
- Kozu-kun and Enzo calibrated one set of 6 IM OSEMs for SR3. (6 OSEMs for SRM remain to be done.)
- Hirata-san aligned the assembly frame, installed the interface bars and IM ring, and installed the IM.
Plan for week of 4/23
- Hirata-san at Mitaka Mon-Tue, then Kamioka.
- Tanioka-san at Kamioka Tue-Thu
- Kozu-kun at Kamioka Wed-Fri (but working with PEM on Fri).
- Others at Kamioka full week
- --
- Start SR3 Hang
- Hang optic.
- Hang RM.
- Cable RM OSEMs.
Plan for week of 4/30
- Shoda-san at Mitaka.
- Mark, Enzo at Kamioka Mon-Wed or TBD.
- Others doing Golden Week stuff.
- --
- Observe KAGRA Phase 1 operations, assist if problems arise.
- Do BF TFs.
- Continue SR3 hang.
To-Do Lists, Schedule
Vacation Info
- Fabian vacation, 3/26-4/27 (then gone).