 * Activity report for week of 12/12
  * Mark, Fabian and Enzo continued BS Test Hang work:
   * We shipped BS mirror box parts to Shoda-san and components for a new LVDT cable to Hirata-san.
   * We posed for pictures of the BS by a team from National Geographic.
   * We installed the BF fishing rod stepper motor adaptor cable.
   * We tried to install the BF LVDT cable but first we encountered trouble routing it, and then several wires broke at the D-Sub end.
   * We laid 6 in-air cables from the tank to the PR2 rank for BF and SF picos, steppers and LVDTs.
   * We lifted the BF/IRM/IM/RM/BS section to weigh it and check its balance.
    * It was 195.6 kg, which is 18 kg(!) less than the capacity of the SF.
    * There was a major imbalance in roll: with all four built-in trim masses moved up the +Y end, it still needed 270 g of extra trim mass to be level. This can probably be made up easily by designing the 18 kg of extra mass appropriately.
   * Unfortunately when we put the payload, the IM was slightly yawed and ended up on the horizontal EQ stop screws. This let the IM-BF maraging rod go slack, which disturbed the leveling of the IM (because every time it is picked up the maraging rod settles in a different place, giving a different suspension point).
   * We removed the end panels of the IRM to get access to the IM and rearranged the trim mass on the the IM to get it balance to bubble-level precision. (We still need to do fine pitch adjustment with the OL so that the BS is at the right angle, secure the trim mass properly and replace the IRM panels and OSEMs.)
  * Miyakawa-san and Yamamoto-san redid the cabling from the computer room to the PR2 rack and expected to finish by lunchtime on Friday.
  * Hirata-san
   * Did parts and fastener lists for the SR payload.
   * Did a 3D model with the SR suspension on the BS assembly frame (to help Mark make adjustments to the frame design).
   * Did 2D drawings of Fabian's concept for BS EQ stop parts.
   * Did a 3D model of a wire clamp with replaceable jaw parts (to avoid having to reuse parts with scars from pressure).
   * Did 2D drawings of a new wire clamps for on top of the BS and SR RMs.
 * BF issue
  * The BF has three issues that may or may not be related:
   * The keystone is sitting at an angle, which means:
    * The bottom of the keystone just barely clears the magnet yoke without rubbing.
    * The suspension point for the IM rod is offset, so the BF does not hang level, even with all built-in trim masses moved to their limits (an additional 270 g stacked on the +Y side of the cap is required).
   * The load capacity is slightly less than measured by Hirata-san during tuning at the ATC.
   * The frequency is rather higher than measured by Hirata-san.
  * Also, the BF/IRM/IM/RM/BS system is 18.1 kg light (195.6 kg) compared to the load capacity of the SF (213.7 kg).
=== Type B (Mark) ===
==== Report for week of 12/25 ====
 * Hirata-san got the L-brackets machined and washed, and installed them on the IM ring bars.
 * Shoda-san recovered the BS from the power outage on 12/25.
 * Miyakawa-san fixed an issue with the SR2 RTM which had prevented it from running.
 * Shoda-san, Hirata-san and Kozu-kun weighed the IM without ballast masses, and then added the lower masses and installed the IM on the assembly frame.
 * They cleaned the assembly frame and installed new jack receptacles on the load gauge adapter.
 * They installed the winch system on the IM, and inspected the clamp pieces for possible scratches.
 * They ran cables for the SR2 steppers and OSEMs.
 * They calibrated the BF LVDT.

==== Report for week of 1/4 ====
 * Mark fixed a number of errors with the Type B screens.

==== Report for week of 1/9 ====
 * We weighed the mirror in its box (and later the empty box), and the RM.
 * Fabian worked on the SR2/SR3/SRM mass budget and did an inventory of spare ballast masses.
 * We hung the SR2 and RM.
 * We assembled the bottom section of the security structure below the RM.
 * Hirata-san gave up on waiting for a third quote for the blades and blade parts and started the ordering process.
 * Hirata-san got rod cable clamp parts from Takahashi-san and worked on drawings for the improved BS vertical and yaw adjusters.

==== Plan for week of 1/15 ====
 * Shoda-san at Mitaka making OSEMs.
 *
==== Plan for week of 1/22 ====

==== Plan for week of 1/22 ====
 * Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
 * Hang SR and RM.

==== Vacation Info ====
 * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
 * Kozu-kun 1/29-2/2

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 12/25

  • Hirata-san got the L-brackets machined and washed, and installed them on the IM ring bars.
  • Shoda-san recovered the BS from the power outage on 12/25.
  • Miyakawa-san fixed an issue with the SR2 RTM which had prevented it from running.
  • Shoda-san, Hirata-san and Kozu-kun weighed the IM without ballast masses, and then added the lower masses and installed the IM on the assembly frame.
  • They cleaned the assembly frame and installed new jack receptacles on the load gauge adapter.
  • They installed the winch system on the IM, and inspected the clamp pieces for possible scratches.
  • They ran cables for the SR2 steppers and OSEMs.
  • They calibrated the BF LVDT.

Report for week of 1/4

  • Mark fixed a number of errors with the Type B screens.

Report for week of 1/9

  • We weighed the mirror in its box (and later the empty box), and the RM.
  • Fabian worked on the SR2/SR3/SRM mass budget and did an inventory of spare ballast masses.
  • We hung the SR2 and RM.
  • We assembled the bottom section of the security structure below the RM.
  • Hirata-san gave up on waiting for a third quote for the blades and blade parts and started the ordering process.
  • Hirata-san got rod cable clamp parts from Takahashi-san and worked on drawings for the improved BS vertical and yaw adjusters.

Plan for week of 1/15

  • Shoda-san at Mitaka making OSEMs.

Plan for week of 1/22

Plan for week of 1/22

  • Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
  • Hang SR and RM.

Vacation Info

  • Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
  • Kozu-kun 1/29-2/2