Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 4/2
- Fujii-kun and Yamamoto-kun got the SR3 real time model running.
- We received the SR3.
- However Mark and Tanioka-kun found Hirose-san had applied the First Contact patterns on the wrong sides, so we took it to Yamamoto-san's lab and Toyama University and re-applied the FC properly. We also bounced a 1064 nm beam off it to verify that the HR and AR coatings were not also swapped (they were OK).
- We made magnet-standoff assemblies for both SR3 and SRM, and set up for gluing the prisms and magnets. We will attach the prisms and magnet-standoffs on Monday.
- Hirata-san did inventory of the SR3/SRM payload parts received last week and started on the inventory of screws.
- Fujii-kun, Enzo and team finished the preparation, adjustment of the SFs and BFs.
- They calibrated one SF and BF. (The remaining one SF and BF will take about another day. Also, the FR stops need to be checked.)
- Enzo and Kozu-kun finished setting up the SR3 and SRM racks. (The SRM rack still lacks a front-end, and power and network connections, but the SR3 is now ready for testing.)
- Shoda-san worked on getting quotes for the ballast masses, on design of the SRM metal mass, and on splitting the BS model to reduce the load on the front-end computer.
Plan for week of 4/9
- Shoda-san at Mitaka
- Fujii-san at Mitaka
- Tanioka-san at Kamioka, but possibly doing PEM stuff.
- Others at Kamioka
- --
- Finish SRM BF and SF calibration
- Finish IMs and IRMs
- Glue SR3 mirror
Plan for week of 4/16
- Shoda-san at Mitaka
- Fujii-san at Mitaka
- Tanioka-san at Mitaka?
- Others at Kamioka
- --
- Build 1xRM
- Start SR3 Hang
- Align assembly frame.
Plan for week of 4/23
- Shoda-san at Mitaka
- Fujii-san at Mitaka?
- Mark, Enzo at Kamioka
- Hirata-san at Mitaka
- Tanioka-san at Mitaka?
- --
- Clean parts (cable clamp bases, etc, etc).
- Observe KAGRA Phase 1 operations, assist if problems arise.
Plan for week of 4/30
- Golden Week!
To-Do Lists, Schedule
Vacation Info
- Fabian vacation, 3/26-4/27 (then gone).