Differences between revisions 1 and 27 (spanning 26 versions)
Revision 1 as of 2019-01-04 15:26:07
Size: 5879
Editor: MarkBarton
Comment:
Revision 27 as of 2019-02-01 19:14:46
Size: 4838
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:
Archived items are at ../ToDoOld.
Line 3: Line 4:
[[#EveryWeek |Every Week]] [[#EveryWeek|Every Week]]
Line 5: Line 6:
[[#ComingWeeks |Coming Weeks]] [[#ComingWeeks|Coming Weeks]]
Line 14: Line 15:
 * Get stuff from [[../WishList]]

== December 2018 vent ==
 * Look for cracks in F0 blades.
 * Install new yaw F0 stepper mechanism (if available).
 * Install new double-sided F0 fishing rod (have all parts except blades).
 * Add more mass to IP to get a lower frequency.
 * Service geophones (one has high noise, one has DC offset).
 * Re-calibrate F0 GAS LVDT.
 * Confirm the positions of the IP LVDTs and Actuators.
 * Tune LBB (adjust table height, damper height) - DON'T BOTHER (unless there's an excuse to open the lower half of the tank).
 * Get stuff from ../WishList
Line 28: Line 19:
=== 2018-12-17 ===
=== 2019-02-04 ===
==== Etc ====
 * Get additional two camera viewports.
 * Get rid of all cable reels
 * Run cables for cameras (with Kokeyama-san).

==== BS ====
 * Install BNC cables for stepper remote enable, and debug.

==== SR2 ====
 * Check the IP stop height (if there's a excuse to open the tank).
 * Release LBB; add approximate final ballast.
 * Install GAS Filters control loops. '''(Enzo)'''
 * Install IM control loops. '''(Enzo)'''
 * Decide buoyancy correction and pre-apply as much as possible, leaving optic at nominal height.
 * Install BNC cables for stepper remote enable, and debug.
 * Install camera viewport.
 * Install camera.
 * Split model.

==== SR3 ====
 * Release the optical table again.
 * Adjust LBB damper and rods to give correct height and gap at mid-range on the blades.
 * Add approximate final ballast.
 * Install camera viewport.
 * Install camera.
 * Debug stepper remote enable.
 * Split model.
Line 30: Line 50:
 * Install/test new yaw mechanism.
 * Adjust height.
 * Check/adjust optic pitch; release LED to SR2.
 * Install Enomoto-kun's beam target plate (if available).
 * Install extension cord for pico drivers.
 * Decide buoyancy correction and pre-apply as much as possible, leaving optic at nominal height.
 * Install camera (with Kokeyama-san).
 * Set up TILT OL.
 * Set up LEN OL.
 * Adjust LBB damper and rods to give correct height and gap at mid-range on the blades.
 * Add approximate final ballast.
 * Wipe inside tank with Vectra-Alpha wipes and IPA.
 * Debug stepper remote enable.
 * Install Enomoto-kun's beam target plate (if/when available).
 * Split model.

== Tasks To Be Scheduled ==
==== BS ====
 * Tune BS LBB (adjust table height, damper height) - DON'T BOTHER (unless there's an excuse to open the lower half of the tank).
 * Replace BS F0 thrust bearing and yaw adjuster - BIG JOB, DON'T BOTHER (unless lack of yaw adjustment becomes a major problem).

==== SR2 ====
==== SR3 ====
==== SRM ====
Line 39: Line 73:
 * Seal geophones.
 * Install geophones and arc weights.
 * Center IP.
==== SR3 ====
 * Install/test new yaw mechanism.
 * Adjust height.
 * Realign OL.
 * Put FC on SRM-W and install it in its holder with 1.4 mm shims ready for possible use.
Line 47: Line 75:
==== SR2 ====
 * Install/test new yaw adjuster.
 * Adjust height.
 * Get top plate reduced?
 * Set up OL cabling.
 * Set up OL.
 * Remove tape, writing etc on PI and PI items.
 * Add new feedthrough to lower part of tank (with Izumi-san-tachi)?
 * Install cable for MIF pico on LBB (with Izumi-san-tachi)?
 * Add ballast mass to LBB.

<<Anchor(SRPrepTasks)>>

== SR Prep Tasks - To Be Scheduled ==
Line 63: Line 77:
 * Check SR2, SR3 TM coil gains for magnet polarity compensation.   * Check SR2, SR3 TM coil gains for magnet polarity compensation.
Line 67: Line 81:
 * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
Line 74: Line 87:
 * --(Get picomotor drivers back on line.)--
 * --(Debug BS BIO connections, especially PI IP.)--
Line 77: Line 88:
=== Main Assembly Sequence ===
 * Necessary for phase-I★★★
  * --(Modify IP LVDT damping filters to include set point.)--
  * --(TFs.)--
  * '''''EXCHANGE YAW/VERT FRs at F0'''''

 * Necessary for phase-II★★
  * Debug BS geophones.
  * Flip circuit boards in BS geophones to make them the same as SRx.
  * Calibrate IP LVDT actuation against IP LVDT sensing. (Klog 3553? http://klog.icrr.u-tokyo.ac.jp/osl/?r=3553)
  * Design PI Sensor blending filter.
  * Tune the LVDT sensitivity
  * Measure IP period; adjust ballast mass.

 * At some point (remotely)★
  * Improve OL offloading.
  * Improve GAS offloading.
  * Spectral analysis of Oplev.
  * Design, install angular lock servo using OL. (Almost done for phase-I)
  * Adjust gains and debug damping for IM OSEMs and GAS LVDTs. (Almost done for phase-I)
  * Subtract DC level of Geophones.
  * Spectra analysis of PI sensors (PI LVDTs and Geophones).
  * Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
  * Set all EQ stops to TBD clearance.
  * Modify the model for IP coil driver control
Line 107: Line 93:
Line 113: Line 100:
 * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
 * Figure out how to make PI yaw adjustment reliable.
Line 119: Line 104:
 * --(Return/replace temporary ballast mass (dog clamps).)--
 * Characterize replacement F0.
 * --(Wipe/clean arc weights that were rained on.)--
Line 124: Line 106:

VIS Type B To-Do List

Archived items are at ../ToDoOld.

Every Week

Coming Weeks

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

2019-02-04

Etc

  • Get additional two camera viewports.
  • Get rid of all cable reels
  • Run cables for cameras (with Kokeyama-san).

BS

  • Install BNC cables for stepper remote enable, and debug.

SR2

  • Check the IP stop height (if there's a excuse to open the tank).
  • Release LBB; add approximate final ballast.
  • Install GAS Filters control loops. (Enzo)

  • Install IM control loops. (Enzo)

  • Decide buoyancy correction and pre-apply as much as possible, leaving optic at nominal height.
  • Install BNC cables for stepper remote enable, and debug.
  • Install camera viewport.
  • Install camera.
  • Split model.

SR3

  • Release the optical table again.
  • Adjust LBB damper and rods to give correct height and gap at mid-range on the blades.
  • Add approximate final ballast.
  • Install camera viewport.
  • Install camera.
  • Debug stepper remote enable.
  • Split model.

SRM

  • Decide buoyancy correction and pre-apply as much as possible, leaving optic at nominal height.
  • Install camera (with Kokeyama-san).
  • Set up TILT OL.
  • Set up LEN OL.
  • Adjust LBB damper and rods to give correct height and gap at mid-range on the blades.
  • Add approximate final ballast.
  • Wipe inside tank with Vectra-Alpha wipes and IPA.
  • Debug stepper remote enable.
  • Install Enomoto-kun's beam target plate (if/when available).
  • Split model.

Tasks To Be Scheduled

BS

  • Tune BS LBB (adjust table height, damper height) - DON'T BOTHER (unless there's an excuse to open the lower half of the tank).
  • Replace BS F0 thrust bearing and yaw adjuster - BIG JOB, DON'T BOTHER (unless lack of yaw adjustment becomes a major problem).

SR2

SR3

SRM

  • Find two geophone cables used by Okutomi-san. (I looked in the second floor EXV room but didn't find them - Mark.)
  • Find one geophone cable ordered for SRM but missing.
  • Rearrange miswired geophone cable.
  • Rebuild defective geophone cable.
  • Put FC on SRM-W and install it in its holder with 1.4 mm shims ready for possible use.

Tunnel

  • Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
  • Check SR2, SR3 TM coil gains for magnet polarity compensation.
  • Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

Mitaka or remotely

  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Install damping filters for SR2.
  • Review DAC channel requests.
  • Split SRx real-time models?

ASAP

Documentation and Operation Manual

  • Add useful info from Enzo's notebook to BSData.

Tasks Not To Forget

Major Tasks

  • Move safety bars from BS AF area to SR2 area.

  • Update circuit diagram.
  • (Time permitting) Try adding mass to IP.
  • Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.

Minor Tasks

Mechanical

  • Put pointy-tipped screw in RM trolley for BS

Electrical

  • Update BS Circuit diagram, D1503600
    • Note removal of LED/PD on TM OSEMs.

    • Organize stepper reset system and watchdog BIO.
    • Include information on assignment of channels to feedthrough positions.
    • Reflect gender-changers and non-flipping feedthrough adapters.
    • Reflect actual cable lengths.
    • Include LVDT pin size (1 mm).
    • Include Stepper pin size (1.6 mm).
    • Undo renumbering of IP items.

    • Page 10: "DIO Card # 0" should be "DIO Card # 1"

    • Include OutConfigBoards on OL page (Sheet 18).

    • Update HPCD section to reflect:

      • All three GAS channels are on HPCD #1 and DIO Card #2, CNB cables, Sheet 13.

      • Three IP channels are on HPCD #0 and DIO Card #2, CNA cables, Sheet 15.

Real-time and SUMCON models

  • Create SUMCON models for full BS and major installation milestones.
  • Create controls design description (cf LIGO-T1100378).

  • Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
  • Understand/document/debug Kokeyama-san's DIO stuff.
  • Measure LPCD and HPCD output filter response.
  • Design and install software compensation filters for LPCD and HPCD output filters.

KAGRA/Subgroups/VIS/TypeB/ToDo (last edited 2019-12-18 12:38:30 by fabian.arellano)