Differences between revisions 1 and 49 (spanning 48 versions)
Revision 1 as of 2019-01-04 15:26:07
Size: 5879
Editor: MarkBarton
Comment:
Revision 49 as of 2019-03-04 14:26:26
Size: 6362
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:
Archived items are at ../ToDoOld.
Line 3: Line 4:
[[#EveryWeek |Every Week]] [[#EveryWeek|Every Week]]
Line 5: Line 6:
[[#ComingWeeks |Coming Weeks]] [[#ComingWeeks|Coming Weeks]]
Line 8: Line 9:

== Paper ==
 * --(Review Type Bp paper)--
 * --(Choose paper title)-- -> "Vibration isolation systems for the beam splitter and signal recycling mirrors of the KAGRA gravitational wave detector"?
 * --(Create JGWDoc number for paper)-- -> [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9836|P1909836]]
 * --(Decide paper author list)-- -> KAGRA Author List 2019?
 * Write Type B paper abstract
 * Write paper outline
 * Write Type B paper Section 1 Introduction
 * Vibration isolation systems in KAGRA
  * Write Section 2.1 Overview
   * Steal or reproduce Type Bp Figure 1 (optic layout)
   * Steal or reproduce Type Bp paper Figure 2 (suspension comparison)
 * Write Section 2.2 Requirements for Type B
 * Write Section 3 Design of the Type-B suspension
  * Write Section 3.1 Mechanical
   * Choose photo of Type B suspension in mid-air
   * Make diagram of Type B in vacuum chamber
  * Write Section 3.2 Sensors and Actuators
  * Write Section 3.3 Control and Damping
   * Make controls diagram like Type Bp paper Figure 7
 * Write Section 4 Measured performance
  * Write Section 4.1 Damping Time
   * Make decay time plot like Type Bp paper Figure 8
  * Write Section 4.2 Residual Velocity
  * Write Section 4.3 Residual Angular Fluctuations
  * Write Section 4.4 Vibration Isolation Performance
 * Write Section 5 Summary
 * Write Section 6 Acknowledgments
 * Write References Section
Line 14: Line 46:
 * Get stuff from [[../WishList]]

== December 2018 vent ==
 * Look for cracks in F0 blades.
 * Install new yaw F0 stepper mechanism (if available).
 * Install new double-sided F0 fishing rod (have all parts except blades).
 * Add more mass to IP to get a lower frequency.
 * Service geophones (one has high noise, one has DC offset).
 * Re-calibrate F0 GAS LVDT.
 * Confirm the positions of the IP LVDTs and Actuators.
 * Tune LBB (adjust table height, damper height) - DON'T BOTHER (unless there's an excuse to open the lower half of the tank).
 * Get stuff from ../WishList
Line 28: Line 50:
=== 2018-12-17 ===
=== 2019-02-12 ===
 * Monday is public holiday.
==== Etc ====

==== All ====
 * --(Debug stepper remote enable.)--
 * --(Do survey of numbering of coil drivers and corresponding Contec assignments.)--
 * Choose optimum BIO Config board switch settings for all OLs. See [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=2081| D1302081]] for what each switch does. Four of them are gain stages (24 dB, 12 dB, 6 dB, 3 dB), and three are filters (all 1 Hz zero, 10 Hz pole). Please clarify the switch numbering and functions (switch "1" = circuit board B0 = group 1, filter A1; position 1 = enable?), make a cheat sheet and put a copy in each rack.

==== BS ====
 * Offload large IM/IRM yaw to IP or F0 yaw.
 
==== SR2 ====
 * --(Install GAS filter control loops.)--

==== SR3 ====
Line 30: Line 69:
 * Install/test new yaw mechanism.
 * Adjust height.
 * Check/adjust optic pitch; release LED to SR2.
 * Install Enomoto-kun's beam target plate (if available).
 * Install extension cord for pico drivers.
 * Find two geophone cables used by Okutomi-san. (I looked in the second floor EXV room but didn't find them - Mark.)
 * Find one geophone cable ordered for SRM but missing.
 * Rearrange miswired geophone cable.
 * Rebuild defective geophone cable.
 * Seal geophones.
 * Install geophones and arc weights.
 * Center IP.
==== SR3 ====
 * Install/test new yaw mechanism.
 * Adjust height.
 * Realign OL.
 * --(Debug geophone channels!!!)--
 * Debug OL, especially whitening filter. Note that WF S1808108 has a mysterious note on its JGWDoc page suggesting it may have a fault.
 * Set up LEN OL (if/when 3D QPD stage arrives).
 * --(Check BIO connections for possible swap of GAS/IP.)--
Line 47: Line 74:
==== SR2 ====
 * Install/test new yaw adjuster.
 * Adjust height.
 * Get top plate reduced?
 * Set up OL cabling.
 * Set up OL.
 * Remove tape, writing etc on PI and PI items.
 * Add new feedthrough to lower part of tank (with Izumi-san-tachi)?
 * Install cable for MIF pico on LBB (with Izumi-san-tachi)?
 * Add ballast mass to LBB.

<<Anchor(SRPrepTasks)>>

== SR Prep Tasks - To Be Scheduled ==
=== Tunnel ===
 * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
 * Check SR2, SR3 TM coil gains for magnet polarity compensation.
 * Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

=== Mitaka or remotely ===
 * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
 * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
 * Install damping filters for SR2.
 * Review DAC channel requests.
 * Split SRx real-time models?

== ASAP ==
 * --(Get picomotor drivers back on line.)--
 * --(Debug BS BIO connections, especially PI IP.)--

=== Main Assembly Sequence ===
 * Necessary for phase-I★★★
  * --(Modify IP LVDT damping filters to include set point.)--
  * --(TFs.)--
  * '''''EXCHANGE YAW/VERT FRs at F0'''''

 * Necessary for phase-II★★
  * Debug BS geophones.
  * Flip circuit boards in BS geophones to make them the same as SRx.
  * Calibrate IP LVDT actuation against IP LVDT sensing. (Klog 3553? http://klog.icrr.u-tokyo.ac.jp/osl/?r=3553)
  * Design PI Sensor blending filter.
  * Tune the LVDT sensitivity
  * Measure IP period; adjust ballast mass.

 * At some point (remotely)★
  * Improve OL offloading.
  * Improve GAS offloading.
  * Spectral analysis of Oplev.
  * Design, install angular lock servo using OL. (Almost done for phase-I)
  * Adjust gains and debug damping for IM OSEMs and GAS LVDTs. (Almost done for phase-I)
  * Subtract DC level of Geophones.
  * Spectra analysis of PI sensors (PI LVDTs and Geophones).
  * Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
  * Set all EQ stops to TBD clearance.
  * Modify the model for IP coil driver control
=== Real-Time Model/Guardian ===
 * See [[KAGRA/Subgroups/VIS/OpsManual/Simulink]]
 * --(Work out what IM1 and IM2 items of BIO section are actually driving based on the rack survey.)--
 * --(Correct all user-facing text on BIO MEDM screen (e.g., "SRM IM-H MONITORS LPCD #1 = Contec #1L") to reflect reality.)--
 * --(Rename all IM1 and IM2 items in RTM to IMH and IMV per above.)--
 * --(Do a new BIO screen that points to new IMH and IMV channels (use search and replace in GEDIT), but keep the old version for the time being.)--
 * --(Finalize models.)--
 *
 * Make a new Type B Guardian and edit it to drive all the new model features and ignore the removed bits.
  * --(-ALIGN blocks)--
  * --(-OPTICALIGN blocks.)--
  * --(+SET blocks.)--
  * --(+DCCTRL blocks)--
 * --(Have the transition from the SAFE state to the DAMPED state load the ALIGN offsets with long ramp times.)--
 * --(Have the transition from the DAMPED state to the ALIGNED state load the OPTICALIGN offsets with long ramp times and also enable damping).)--
Line 106: Line 93:
<<Anchor(RealBSHang)>>
== Tasks Not To Forget ==
=== Major Tasks ===
 * --(Move safety bars from BS AF area to SR2 area.)--
 * Update circuit diagram.
 * (Time permitting) Try adding mass to IP.
 * Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
 * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
 * Figure out how to make PI yaw adjustment reliable.
Line 119: Line 96:
 * --(Return/replace temporary ballast mass (dog clamps).)--
 * Characterize replacement F0.
 * --(Wipe/clean arc weights that were rained on.)--
Line 124: Line 98:
==== Electrical ====
== Electrical ==
Line 140: Line 115:
==== Real-time and SUMCON models ==== == Real-time and SUMCON models ==
Line 147: Line 122:

== One Day, If Ever Needed ==
==== BS ====
 * Tune BS LBB (adjust table height, damper height) - DON'T BOTHER (unless there's an excuse to open the lower half of the tank).
 * Replace BS F0 thrust bearing and yaw adjuster - BIG JOB, DON'T BOTHER (unless lack of yaw adjustment becomes a major problem).
 * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
==== SR3 ====
 * Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
==== SRM ====
 * Install Enomoto-kun's beam target plate (if/when available).
 * Find two geophone cables used by Okutomi-san. (I looked in the second floor EXV room but didn't find them - Mark.)
 * Find one geophone cable ordered for SRM but missing.
 * Rearrange miswired geophone cable.
 * Rebuild defective geophone cable.
 * Put FC on SRM-W and install it in its holder with 1.4 mm shims ready for possible use.

VIS Type B To-Do List

Archived items are at ../ToDoOld.

Every Week

Coming Weeks

Paper

  • Review Type Bp paper

  • Choose paper title -> "Vibration isolation systems for the beam splitter and signal recycling mirrors of the KAGRA gravitational wave detector"?

  • Create JGWDoc number for paper -> P1909836

  • Decide paper author list -> KAGRA Author List 2019?

  • Write Type B paper abstract
  • Write paper outline
  • Write Type B paper Section 1 Introduction
  • Vibration isolation systems in KAGRA
    • Write Section 2.1 Overview
      • Steal or reproduce Type Bp Figure 1 (optic layout)
      • Steal or reproduce Type Bp paper Figure 2 (suspension comparison)
  • Write Section 2.2 Requirements for Type B
  • Write Section 3 Design of the Type-B suspension
    • Write Section 3.1 Mechanical
      • Choose photo of Type B suspension in mid-air
      • Make diagram of Type B in vacuum chamber
    • Write Section 3.2 Sensors and Actuators
    • Write Section 3.3 Control and Damping
      • Make controls diagram like Type Bp paper Figure 7
  • Write Section 4 Measured performance
    • Write Section 4.1 Damping Time
      • Make decay time plot like Type Bp paper Figure 8
    • Write Section 4.2 Residual Velocity
    • Write Section 4.3 Residual Angular Fluctuations
    • Write Section 4.4 Vibration Isolation Performance
  • Write Section 5 Summary
  • Write Section 6 Acknowledgments
  • Write References Section

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

2019-02-12

  • Monday is public holiday.

Etc

All

  • Debug stepper remote enable.

  • Do survey of numbering of coil drivers and corresponding Contec assignments.

  • Choose optimum BIO Config board switch settings for all OLs. See D1302081 for what each switch does. Four of them are gain stages (24 dB, 12 dB, 6 dB, 3 dB), and three are filters (all 1 Hz zero, 10 Hz pole). Please clarify the switch numbering and functions (switch "1" = circuit board B0 = group 1, filter A1; position 1 = enable?), make a cheat sheet and put a copy in each rack.

BS

  • Offload large IM/IRM yaw to IP or F0 yaw.

SR2

  • Install GAS filter control loops.

SR3

SRM

  • Debug geophone channels!!!

  • Debug OL, especially whitening filter. Note that WF S1808108 has a mysterious note on its JGWDoc page suggesting it may have a fault.
  • Set up LEN OL (if/when 3D QPD stage arrives).
  • Check BIO connections for possible swap of GAS/IP.

Real-Time Model/Guardian

  • See KAGRA/Subgroups/VIS/OpsManual/Simulink

  • Work out what IM1 and IM2 items of BIO section are actually driving based on the rack survey.

  • Correct all user-facing text on BIO MEDM screen (e.g., "SRM IM-H MONITORS LPCD #1 = Contec #1L") to reflect reality.

  • Rename all IM1 and IM2 items in RTM to IMH and IMV per above.

  • Do a new BIO screen that points to new IMH and IMV channels (use search and replace in GEDIT), but keep the old version for the time being.

  • Finalize models.

  • Make a new Type B Guardian and edit it to drive all the new model features and ignore the removed bits.
    • -ALIGN blocks

    • -OPTICALIGN blocks.

    • +SET blocks.

    • +DCCTRL blocks

  • Have the transition from the SAFE state to the DAMPED state load the ALIGN offsets with long ramp times.

  • Have the transition from the DAMPED state to the ALIGNED state load the OPTICALIGN offsets with long ramp times and also enable damping).

Documentation and Operation Manual

  • Add useful info from Enzo's notebook to BSData.

Minor Tasks

Mechanical

  • Put pointy-tipped screw in RM trolley for BS

Electrical

  • Update BS Circuit diagram, D1503600
    • Note removal of LED/PD on TM OSEMs.

    • Organize stepper reset system and watchdog BIO.
    • Include information on assignment of channels to feedthrough positions.
    • Reflect gender-changers and non-flipping feedthrough adapters.
    • Reflect actual cable lengths.
    • Include LVDT pin size (1 mm).
    • Include Stepper pin size (1.6 mm).
    • Undo renumbering of IP items.

    • Page 10: "DIO Card # 0" should be "DIO Card # 1"

    • Include OutConfigBoards on OL page (Sheet 18).

    • Update HPCD section to reflect:

      • All three GAS channels are on HPCD #1 and DIO Card #2, CNB cables, Sheet 13.

      • Three IP channels are on HPCD #0 and DIO Card #2, CNA cables, Sheet 15.

Real-time and SUMCON models

  • Create SUMCON models for full BS and major installation milestones.
  • Create controls design description (cf LIGO-T1100378).

  • Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
  • Understand/document/debug Kokeyama-san's DIO stuff.
  • Measure LPCD and HPCD output filter response.
  • Design and install software compensation filters for LPCD and HPCD output filters.

One Day, If Ever Needed

BS

  • Tune BS LBB (adjust table height, damper height) - DON'T BOTHER (unless there's an excuse to open the lower half of the tank).
  • Replace BS F0 thrust bearing and yaw adjuster - BIG JOB, DON'T BOTHER (unless lack of yaw adjustment becomes a major problem).
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.

SR3

  • Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

SRM

  • Install Enomoto-kun's beam target plate (if/when available).
  • Find two geophone cables used by Okutomi-san. (I looked in the second floor EXV room but didn't find them - Mark.)
  • Find one geophone cable ordered for SRM but missing.
  • Rearrange miswired geophone cable.
  • Rebuild defective geophone cable.
  • Put FC on SRM-W and install it in its holder with 1.4 mm shims ready for possible use.

KAGRA/Subgroups/VIS/TypeB/ToDo (last edited 2019-12-18 12:38:30 by fabian.arellano)