Line 2: Line 2:
Archived items are at ../ToDoOld.
Line 3: Line 4:
[[#EveryWeek |Every Week]] == Paper ==
 * --(Review Type Bp paper)--
 * --(Choose paper title)-- -> "Vibration isolation systems for the beam splitter and signal recycling mirrors of the KAGRA gravitational wave detector"
 * --(Create JGWDoc number for paper)-- -> [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9836|P1909836]]
 * --(Decide paper author list)-- -> KAGRA Author List 2019?
 * --(Write Type B paper abstract)--
 * --(Write paper outline)--
 * --(Write Type B paper "Introduction")--
 * Vibration isolation systems in KAGRA
  * --(Write "Overview")--
   * Steal or reproduce Type Bp Figure 1 (optic layout)
   * Steal or reproduce Type Bp paper Figure 2 (suspension comparison)
 * Write Requirements for Type B
 * Write "Design of the Type-B suspension"
  * --(Write "Mechanical")--
   * Choose photo of Type B suspension in mid-air
   * Make diagram of Type B in vacuum chamber
  * Write "Sensors and Actuators"
   * Write "Optical Levers"
  * Write "Control and Damping"
   * Make controls diagram like Type Bp paper Figure 7
 * Write "Measured performance"
  * Write "Damping Time"
   * Make decay time plot like Type Bp paper Figure 8
  * Write "Residual Velocity"
  * Write "Residual Angular Fluctuations"
  * Write "Vibration Isolation Performance"
 * Write "Summary"
 * --(Write "Acknowledgments")-- -> Used 2018-09 version - need to check if there's a newer one.
 * Compile "References"
  * --(Find NS-NS detection reference)--
  * --(Find initial detection reference)--
  * Find Type A reference
  * Find cryogenic payload reference
  * Find bKAGRA reference
  * Find LIGO-India reference
Line 5: Line 41:
[[#ComingWeeks |Coming Weeks]] == Tunnel ==
 * Tidy up.
 * Move charging station to more convenient location (e.g., near -X entrance).
 * Find and inventory all gluing tools.
 * Put pointy-tipped screw in RM trolley for BS
 * Put First Contact on SRM-W optic and install it in its holder with 1.4 mm shims ready for possible use.
 * Check all pico drivers are on extension cords that can be unplugged from outside the cleanbooth (in case reset is needed).
=== BS ===
 * Add Tanaka-san's LVDT signal card.
=== SR2 ===
 * Add Tanaka-san's LVDT signal card.
=== SR3 ===
 * Add Tanaka-san's LVDT signal card.
=== SRM ===
 * Add Tanaka-san's LVDT signal card.
Line 7: Line 57:
<<Anchor(EveryWeek)>> == Shakedown/Characterization ==
=== BS ===
 * Measure decay time, rms with and without control.
 * Do geophone blending.
=== SR2 ===
 * --(Measure decay time, rms with and without control.)--
 * Do FEA model of IRM side plates.
 * --(Do geophone blending.)--
Line 9: Line 66:
== Every Week ==
=== Facilities ===
 * Vacuum and roll floor.
 * Wipe ladders.
 * Tidy tools, parts.
 * Get stuff from [[../WishList]]
=== SR3 ===
 * Measure decay time, rms with and without control.
 * Put SR3 cleanbooth electronics in minirack.
 * Check pico adapter cables.
 * Do geophone blending.
Line 16: Line 72:
== December 2018 vent ==
 * Look for cracks in F0 blades.
 * Install new yaw F0 stepper mechanism (if available).
 * Install new double-sided F0 fishing rod (have all parts except blades).
 * Add more mass to IP to get a lower frequency.
 * Service geophones (one has high noise, one has DC offset).
 * Re-calibrate F0 GAS LVDT.
 * Confirm the positions of the IP LVDTs and Actuators.
 * Tune LBB (adjust table height, damper height) - DON'T BOTHER (unless there's an excuse to open the lower half of the tank).
=== SRM ===
 * Check where SRM pico cables came from and make sure there isn't one missing somewhere else.
 * Debug 240 Hz noise in LVDT.
 * Measure decay time, rms with and without control.
 * Check keystone lock screws in BF (on next vent).
 * Do geophone blending.
Line 26: Line 79:
<<Anchor(ComingWeeks)>> == SDF ==
  * Document SDF in Operations Manual
  * Make SDF states for Type B, e.g.:
   * SAFE
   * DCCTRL-ONLY
   * ALIGNED-IN-AIR
   * ALIGNED-IN-VACUUM
Line 28: Line 87:
=== 2018-12-17 ===
==== SRM ====
 * Install/test new yaw mechanism.
 * Adjust height.
 * Check/adjust optic pitch; release LED to SR2.
 * Install Enomoto-kun's beam target plate (if available).
 * Install extension cord for pico drivers.
 * Find two geophone cables used by Okutomi-san. (I looked in the second floor EXV room but didn't find them - Mark.)
 * Find one geophone cable ordered for SRM but missing.
 * Rearrange miswired geophone cable.
 * Rebuild defective geophone cable.
 * Seal geophones.
 * Install geophones and arc weights.
 * Center IP.
==== SR3 ====
 * Install/test new yaw mechanism.
 * Adjust height.
 * Realign OL.
== MEDM ==
 * Fix DAC screen (split model issue).
 * Move overview.txt files from common to k1, edit screens
Line 47: Line 91:
==== SR2 ====
 * Install/test new yaw adjuster.
 * Adjust height.
 * Get top plate reduced?
 * Set up OL cabling.
 * Set up OL.
 * Remove tape, writing etc on PI and PI items.
 * Add new feedthrough to lower part of tank (with Izumi-san-tachi)?
 * Install cable for MIF pico on LBB (with Izumi-san-tachi)?
 * Add ballast mass to LBB.
== Guardian/RTM ==
 * Rethink Guardian to avoid going back to SAFE for minor problems.
 * Consider splitting Type B Guardian into tower and payload sections with possible third monitor Guardian overseeing both.
 * Make cycle times of BS models the same as for SRx.
 * Change the DAQ channel lists per [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=10294|Shoda-san's final design]].
 * Remove TM_OSEM subsystem from payload model.
 * Remove GEOWHITEN from IP of top model.
 * Remove ISIINF->CART2EUL->ISIWIT from IM.
 * Add temperature alarms.
 * Add alarms for LVDT actuation near limit (especially for GAS).
 * Add alarm for integral runaway in DCCTRL loops.
 * Change value of nominal in Guardian to 'ALIGNED' or the like.
 * Add secondary watchdog with lower threshold that puts all outputs to HOLD and then gets Guardian to ramp them down.
Line 58: Line 105:
<<Anchor(SRPrepTasks)>> == Simulation ==
 * Create controls design description (cf [[https://dcc.ligo.org/LIGO-T1100378/public|LIGO-T1100378]]).
 * --(Get a good set of TFs and put them in a common directory:)--
  * --(Directory: /kagra/Dropbox/Subsystems/VIS/TypeBData/SR2/simulation/TF/ )--
  * --(Content: diaggui xml files and regular text files.)--
 * --(Compare the Matlab prediction with the measurements.)--
  * --(In a reasonable way tune the parameters of the simulation in ordet to get a good agreement.)--
  * --(It should include resonant peaks not predicted by the simulation.)--
  * --(Write a klog about this. )--
 * --(Given the fact that Takanori's Matlab simulation provides the TFs in units of [m/N] calculate a calibration factor for each GAS LVDT and IP and IM virtual actuator, which are in units of [µm/cnt]. )--
 * Collect the measurements of LVDT and OSEM readout noise and put them in a common directory:
  * Location: /kagra/Dropbox/Subsystems/VIS/TypeBData/SR2/simulation/sensor_readout_noise/
  * Content: duaggui xml files and regular text files.
 * Check Panwei's measurements of OSEM noise. Pay special attention to the conversion into m/rtHz from V/rtHz.
 * Calculate the readut noise of the virtual sensors from the readout noise of the real ones.
  * --(IP LVDT.)--
  * --(IP Geo: where's the data for SR2 geophones?)-- There's information in entry [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6106|6106]]. For SRM the plots are at [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=8177|8177]] but where's the data?
  * --(GAS LVDT (no virtual sensors) )--
  * --(IM OSEMS )--
  * Oplev
 * Estimate coil driver noise. It seems this is not expected to contribute significantly but we should still know.
 * Convert real actuation noise to virtual actuation noise.
 * --(Check whether the Matlab simulation implements the output of the length sensing oplev)--.
 * Extract the filters designed by Enzo, Terrence and Lucia from the filter bank using Foton and write them in a format compatible with Takanori's simulation: --(IP LVDT)--, IP GEO, --(blending filters)--, --(GAS)--, --(IM)--, optic.
 * Check the whether the oplev takes into account the ground motion movement in
  * --(longitudinal displacement: NO)--
  * Pitch and yaw
 * In the simulation, what are the assumed coupling between
  * LVDT-L ==> OpLev-PTM.
  * IP GEO-L ==> OpLev-PTM.
  * Longitudinal ground motion ==> OpLev-PTM.
  * OSEM-L ==> OpLev-PTM
  * And the above quantities with Oplev-YTM.
 * Does the simulation take into account the 1/300 rads of the tunnel slope?
 * In the software modify the control feedback loop topology in order to have the same as in the real system.
 * Tune the filters in order to account for the differences between simulation and measurement.
 * As sanity check for the simulation, check the stability criteria and compare with Enzo's.
 * Ask whether there is a recent measurement of seismic motion at the the central room.
Line 60: Line 144:
== SR Prep Tasks - To Be Scheduled ==
=== Tunnel ===
 * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
 * Check SR2, SR3 TM coil gains for magnet polarity compensation.
 * Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

=== Mitaka or remotely ===
 * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
 * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
 * Install damping filters for SR2.
 * Review DAC channel requests.
 * Split SRx real-time models?

== ASAP ==
 * --(Get picomotor drivers back on line.)--
 * --(Debug BS BIO connections, especially PI IP.)--

=== Main Assembly Sequence ===
 * Necessary for phase-I★★★
  * --(Modify IP LVDT damping filters to include set point.)--
  * --(TFs.)--
  * '''''EXCHANGE YAW/VERT FRs at F0'''''

 * Necessary for phase-II★★
  * Debug BS geophones.
  * Flip circuit boards in BS geophones to make them the same as SRx.
  * Calibrate IP LVDT actuation against IP LVDT sensing. (Klog 3553? http://klog.icrr.u-tokyo.ac.jp/osl/?r=3553)
  * Design PI Sensor blending filter.
  * Tune the LVDT sensitivity
  * Measure IP period; adjust ballast mass.

 * At some point (remotely)★
  * Improve OL offloading.
  * Improve GAS offloading.
  * Spectral analysis of Oplev.
  * Design, install angular lock servo using OL. (Almost done for phase-I)
  * Adjust gains and debug damping for IM OSEMs and GAS LVDTs. (Almost done for phase-I)
  * Subtract DC level of Geophones.
  * Spectra analysis of PI sensors (PI LVDTs and Geophones).
  * Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
  * Set all EQ stops to TBD clearance.
  * Modify the model for IP coil driver control

=== Documentation and Operation Manual ===
 * Add useful info from Enzo's notebook to BSData.

<<Anchor(RealBSHang)>>
== Tasks Not To Forget ==
=== Major Tasks ===
 * --(Move safety bars from BS AF area to SR2 area.)--
 * Update circuit diagram.
 * (Time permitting) Try adding mass to IP.
 * Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
 * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
 * Figure out how to make PI yaw adjustment reliable.

=== Minor Tasks ===
==== Mechanical ====
 * Put pointy-tipped screw in RM trolley for BS
 * --(Return/replace temporary ballast mass (dog clamps).)--
 * Characterize replacement F0.
 * --(Wipe/clean arc weights that were rained on.)--

<<Anchor(elec)>>
==== Electrical ====
== Electronics ==
 * Pick better resistor values for sat amps (to give closer to 32K open-light values).
 * Install Tanaka-san's LVDT sig gen cards when available). Update [[KAGRA/Subgroups/VIS/TypeB/Status|Status]] and electronic item lists.
 * Install Tanaka-san's hardware watchdogs. Update [[KAGRA/Subgroups/VIS/TypeB/Status|Status]] and electronic item lists.
 * Enable stepper remote enable system (flip enable switches on stepper drivers) and do final test.
Line 126: Line 150:
  * --(Make generic to Type B.)--
Line 127: Line 152:
  * Organize stepper reset system and watchdog BIO.
  * Include information on assignment of channels to feedthrough positions.
  * Reflect gender-changers and non-flipping feedthrough adapters.
  * Reflect actual cable lengths.
  * Include LVDT pin size (1 mm).
  * Include Stepper pin size (1.6 mm).
  * --(Add stepper remote enable system.)--
  * --(Add note about gender-changers and non-flipping feedthrough adapters.)--
  * --(Correct default stepper channel assignments and link to wiki for changes.)--
  * --(Remove note about steppers with limit switches (we didn't use them).)--
  * --(Include LVDT pin size (1 mm).)--
  * --(Include Stepper pin size (1.6 mm).)--
Line 139: Line 164:
  * --(Include blank page for watchdog.)--
  * Include ''actual'' watchdog.
  * Include information on assignment of channels to feedthrough positions (or summarize on wiki and add link).
Line 140: Line 168:
==== Real-time and SUMCON models ====
 * Create SUMCON models for full BS and major installation milestones.
 * Create controls design description (cf [[https://dcc.ligo.org/LIGO-T1100378/public|LIGO-T1100378]]).
 * Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
 * Understand/document/debug Kokeyama-san's DIO stuff.
 * Measure LPCD and HPCD output filter response.
 * Design and install software compensation filters for LPCD and HPCD output filters.
== Documentation and Operation Manual ==
 * Get scan of Enzo's notebook and post to JGWDoc.
 * Get scan of Terrence's notebook and post to JGWDoc.
 * Add useful info from notebooks to BSData/etc.'
 * Improve Thermometers page of Operations Manual.
 * Improve SDF page of Operations Manual.
 * Improve vistools.py page of Operations Manual (Mark).
 * Add Cameras page to Operations Manual.
 * Add ndscope page to Operations Manual.

== OLs ==
 * Design/procure/install permanent hard protective covers.
 * Consider getting camera covers as well (to stop light getting in and IR getting out).
 * Tweak whitening filter gains.

== One Day, If Ever Needed ==
=== BS ===
 * Tune BS LBB (adjust table height, damper height) - DON'T BOTHER (unless there's an excuse to open the lower half of the tank).
 * Replace BS F0 thrust bearing - BIG JOB - NOT WORTH IT.
 * Replace BS F0 yaw adjuster - DO AT NEXT VENT AFTER PARTS ARE AVAILABLE.
 * Consider flipping sign of H2 coil actuator (there is a -1 in COILOUTF for it).

=== SR3 ===
 * Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

=== SRM ===
 * Install Enomoto-kun's beam target plate (if/when available).

VIS Type B To-Do List

Archived items are at ../ToDoOld.

Paper

  • Review Type Bp paper

  • Choose paper title -> "Vibration isolation systems for the beam splitter and signal recycling mirrors of the KAGRA gravitational wave detector"

  • Create JGWDoc number for paper -> P1909836

  • Decide paper author list -> KAGRA Author List 2019?

  • Write Type B paper abstract

  • Write paper outline

  • Write Type B paper "Introduction"

  • Vibration isolation systems in KAGRA
    • Write "Overview"

      • Steal or reproduce Type Bp Figure 1 (optic layout)
      • Steal or reproduce Type Bp paper Figure 2 (suspension comparison)
  • Write Requirements for Type B
  • Write "Design of the Type-B suspension"
    • Write "Mechanical"

      • Choose photo of Type B suspension in mid-air
      • Make diagram of Type B in vacuum chamber
    • Write "Sensors and Actuators"
      • Write "Optical Levers"
    • Write "Control and Damping"
      • Make controls diagram like Type Bp paper Figure 7
  • Write "Measured performance"
    • Write "Damping Time"
      • Make decay time plot like Type Bp paper Figure 8
    • Write "Residual Velocity"
    • Write "Residual Angular Fluctuations"
    • Write "Vibration Isolation Performance"
  • Write "Summary"
  • Write "Acknowledgments" -> Used 2018-09 version - need to check if there's a newer one.

  • Compile "References"
    • Find NS-NS detection reference

    • Find initial detection reference

    • Find Type A reference
    • Find cryogenic payload reference
    • Find bKAGRA reference
    • Find LIGO-India reference

Tunnel

  • Tidy up.
  • Move charging station to more convenient location (e.g., near -X entrance).
  • Find and inventory all gluing tools.
  • Put pointy-tipped screw in RM trolley for BS
  • Put First Contact on SRM-W optic and install it in its holder with 1.4 mm shims ready for possible use.
  • Check all pico drivers are on extension cords that can be unplugged from outside the cleanbooth (in case reset is needed).

BS

  • Add Tanaka-san's LVDT signal card.

SR2

  • Add Tanaka-san's LVDT signal card.

SR3

  • Add Tanaka-san's LVDT signal card.

SRM

  • Add Tanaka-san's LVDT signal card.

Shakedown/Characterization

BS

  • Measure decay time, rms with and without control.
  • Do geophone blending.

SR2

  • Measure decay time, rms with and without control.

  • Do FEA model of IRM side plates.
  • Do geophone blending.

SR3

  • Measure decay time, rms with and without control.
  • Put SR3 cleanbooth electronics in minirack.
  • Check pico adapter cables.
  • Do geophone blending.

SRM

  • Check where SRM pico cables came from and make sure there isn't one missing somewhere else.
  • Debug 240 Hz noise in LVDT.
  • Measure decay time, rms with and without control.
  • Check keystone lock screws in BF (on next vent).
  • Do geophone blending.

SDF

  • Document SDF in Operations Manual
  • Make SDF states for Type B, e.g.:
    • SAFE
    • DCCTRL-ONLY
    • ALIGNED-IN-AIR
    • ALIGNED-IN-VACUUM

MEDM

  • Fix DAC screen (split model issue).
  • Move overview.txt files from common to k1, edit screens

Guardian/RTM

  • Rethink Guardian to avoid going back to SAFE for minor problems.
  • Consider splitting Type B Guardian into tower and payload sections with possible third monitor Guardian overseeing both.
  • Make cycle times of BS models the same as for SRx.
  • Change the DAQ channel lists per Shoda-san's final design.

  • Remove TM_OSEM subsystem from payload model.
  • Remove GEOWHITEN from IP of top model.
  • Remove ISIINF->CART2EUL->ISIWIT from IM.

  • Add temperature alarms.
  • Add alarms for LVDT actuation near limit (especially for GAS).
  • Add alarm for integral runaway in DCCTRL loops.
  • Change value of nominal in Guardian to 'ALIGNED' or the like.
  • Add secondary watchdog with lower threshold that puts all outputs to HOLD and then gets Guardian to ramp them down.

Simulation

  • Create controls design description (cf LIGO-T1100378).

  • Get a good set of TFs and put them in a common directory:

    • Directory: /kagra/Dropbox/Subsystems/VIS/TypeBData/SR2/simulation/TF/

    • Content: diaggui xml files and regular text files.

  • Compare the Matlab prediction with the measurements.

    • In a reasonable way tune the parameters of the simulation in ordet to get a good agreement.

    • It should include resonant peaks not predicted by the simulation.

    • Write a klog about this.

  • Given the fact that Takanori's Matlab simulation provides the TFs in units of [m/N] calculate a calibration factor for each GAS LVDT and IP and IM virtual actuator, which are in units of [µm/cnt].

  • Collect the measurements of LVDT and OSEM readout noise and put them in a common directory:
    • Location: /kagra/Dropbox/Subsystems/VIS/TypeBData/SR2/simulation/sensor_readout_noise/
    • Content: duaggui xml files and regular text files.
  • Check Panwei's measurements of OSEM noise. Pay special attention to the conversion into m/rtHz from V/rtHz.
  • Calculate the readut noise of the virtual sensors from the readout noise of the real ones.
    • IP LVDT.

    • IP Geo: where's the data for SR2 geophones? There's information in entry 6106. For SRM the plots are at 8177 but where's the data?

    • GAS LVDT (no virtual sensors)

    • IM OSEMS

    • Oplev
  • Estimate coil driver noise. It seems this is not expected to contribute significantly but we should still know.
  • Convert real actuation noise to virtual actuation noise.
  • Check whether the Matlab simulation implements the output of the length sensing oplev.

  • Extract the filters designed by Enzo, Terrence and Lucia from the filter bank using Foton and write them in a format compatible with Takanori's simulation: IP LVDT, IP GEO, blending filters, GAS, IM, optic.

  • Check the whether the oplev takes into account the ground motion movement in
    • longitudinal displacement: NO

    • Pitch and yaw
  • In the simulation, what are the assumed coupling between
    • LVDT-L ==> OpLev-PTM.

    • IP GEO-L ==> OpLev-PTM.

    • Longitudinal ground motion ==> OpLev-PTM.

    • OSEM-L ==> OpLev-PTM

    • And the above quantities with Oplev-YTM.
  • Does the simulation take into account the 1/300 rads of the tunnel slope?
  • In the software modify the control feedback loop topology in order to have the same as in the real system.
  • Tune the filters in order to account for the differences between simulation and measurement.
  • As sanity check for the simulation, check the stability criteria and compare with Enzo's.
  • Ask whether there is a recent measurement of seismic motion at the the central room.

Electronics

  • Pick better resistor values for sat amps (to give closer to 32K open-light values).
  • Install Tanaka-san's LVDT sig gen cards when available). Update Status and electronic item lists.

  • Install Tanaka-san's hardware watchdogs. Update Status and electronic item lists.

  • Enable stepper remote enable system (flip enable switches on stepper drivers) and do final test.
  • Update BS Circuit diagram, D1503600
    • Make generic to Type B.

    • Note removal of LED/PD on TM OSEMs.

    • Add stepper remote enable system.

    • Add note about gender-changers and non-flipping feedthrough adapters.

    • Correct default stepper channel assignments and link to wiki for changes.

    • Remove note about steppers with limit switches (we didn't use them).

    • Include LVDT pin size (1 mm).

    • Include Stepper pin size (1.6 mm).

    • Undo renumbering of IP items.

    • Page 10: "DIO Card # 0" should be "DIO Card # 1"

    • Include OutConfigBoards on OL page (Sheet 18).

    • Update HPCD section to reflect:

      • All three GAS channels are on HPCD #1 and DIO Card #2, CNB cables, Sheet 13.

      • Three IP channels are on HPCD #0 and DIO Card #2, CNA cables, Sheet 15.

    • Include blank page for watchdog.

    • Include actual watchdog.

    • Include information on assignment of channels to feedthrough positions (or summarize on wiki and add link).

Documentation and Operation Manual

  • Get scan of Enzo's notebook and post to JGWDoc.
  • Get scan of Terrence's notebook and post to JGWDoc.
  • Add useful info from notebooks to BSData/etc.'
  • Improve Thermometers page of Operations Manual.
  • Improve SDF page of Operations Manual.
  • Improve vistools.py page of Operations Manual (Mark).
  • Add Cameras page to Operations Manual.
  • Add ndscope page to Operations Manual.

OLs

  • Design/procure/install permanent hard protective covers.
  • Consider getting camera covers as well (to stop light getting in and IR getting out).
  • Tweak whitening filter gains.

One Day, If Ever Needed

BS

  • Tune BS LBB (adjust table height, damper height) - DON'T BOTHER (unless there's an excuse to open the lower half of the tank).
  • Replace BS F0 thrust bearing - BIG JOB - NOT WORTH IT.
  • Replace BS F0 yaw adjuster - DO AT NEXT VENT AFTER PARTS ARE AVAILABLE.
  • Consider flipping sign of H2 coil actuator (there is a -1 in COILOUTF for it).

SR3

  • Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

SRM

  • Install Enomoto-kun's beam target plate (if/when available).