Line 19: | Line 19: |
=== 2019-01-21 === | === 2019-02-04 === |
Line 21: | Line 22: |
* Work with Akutsu-san to get additional two camera viewports (for SR2 and SRM). * Open all dead geophones, replace preamps, test, seal, retest. * Get rid of all cable reels. |
* Get additional two camera viewports. * Get rid of all cable reels * Run cables for cameras (with Kokeyama-san). |
Line 25: | Line 26: |
==== BS (top priority) ==== * Fix geophones. '''(Enzo on Wednesday or later.)''' * --(Fix touching issue.)-- * Secure any keystone trim mass. '''(Hirata-san or Fabian on Wednesday of later.)''' * --(Recenter the OL.)-- ==== SR3 (priority 2) ==== * Survey optic height '''(Fabian on Monday) '''and raise suspension on jacks as necessary '''(Enzo, Hirata-san, Terrence and Fabian on Monday)'''.''' ''' * Reinstall OL LED (original one borrowed for SR2 - probably use new one to be supplied by Simon), probably change collimator, and realign OL. '''(Terrence on Monday and/or Tuesday.)''' * Secure any keystone trim mass. '''(Hirata-san or Fabian on Monday.)''' |
==== BS ==== * Install BNC cables for stepper remote enable, and debug. |
Line 37: | Line 30: |
* Survey optic height '''(Fabian on Monday)''' and raise suspension on jacks as necessary. '''(Enzo, Hirata-san, Terrence and Fabian on''' '''Monday and/or Tuesday.)''' * Remove tape, writing etc on PI and PI items. '''(Hirata-san on Monday and/or Tuesday.)''' * Secure any keystone trim mass. '''(Hirata-san or Fabian on Monday and/or Tuesday.)''' |
* Check the IP stop height (if there's a excuse to open the tank). * Release LBB; add approximate final ballast. * Install GAS Filters control loops. '''(Enzo)''' * Install IM control loops. '''(Enzo)''' * Decide buoyancy correction and pre-apply as much as possible, leaving optic at nominal height. * Install BNC cables for stepper remote enable, and debug. * Install camera viewport. * Install camera. * Split model. ==== SR3 ==== * Release the optical table again. * Adjust LBB damper and rods to give correct height and gap at mid-range on the blades. * Add approximate final ballast. * Install camera viewport. * Install camera. * Debug stepper remote enable. * Split model. |
Line 42: | Line 50: |
* Raise suspension 3.5 mm on jacks. * Check/improve payload alignment and IM OSEMs. Recheck optic pitch with OL as needed.\ * Adjust F0 keystone trim to give desired height and secure weights in place. * Install geophones and arc weights. * Center and tune IP. * Hook LBB and add just enough ballast to have it bouncing. |
* Decide buoyancy correction and pre-apply as much as possible, leaving optic at nominal height. * Install camera (with Kokeyama-san). * Set up TILT OL. * Set up LEN OL. * Adjust LBB damper and rods to give correct height and gap at mid-range on the blades. * Add approximate final ballast. |
Line 49: | Line 57: |
* Set up TILT OL. === 2019-01-28 === ==== BS ==== ==== SRM ==== * Install camera viewport. (Mirapro will be available 1/28) * Setup LEN OL. * Add additional ballast to LBB to set desired height (only if someone will be putting stuff on it). * Install Enomoto-kun's beam target plate (when available). ==== SR3 ==== * Install camera viewport (already available). * Add additional ballast to LBB to set desired height (only if someone will be putting stuff on it). * Install camera. * Run cables for camera. ==== SR2 ==== * Add camera viewport (when available). * Add new feedthrough to lower part of tank (with Izumi-san-tachi)? * Install cable for MIF pico on LBB (with Izumi-san-tachi)? * Add additional mass to LBB to have it at the desired height * Install camera. * Run cables for camera. |
* Debug stepper remote enable. * Install Enomoto-kun's beam target plate (if/when available). * Split model. |
Line 93: | Line 81: |
* Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually). | |
Line 100: | Line 87: |
* --(Get picomotor drivers back on line.)-- * --(Debug BS BIO connections, especially PI IP.)-- |
|
Line 103: | Line 88: |
=== Main Assembly Sequence === * Necessary for phase-I★★★ * --(Modify IP LVDT damping filters to include set point.)-- * --(TFs.)-- * '''''EXCHANGE YAW/VERT FRs at F0''''' * Necessary for phase-II★★ * Debug BS geophones. * Flip circuit boards in BS geophones to make them the same as SRx. * Calibrate IP LVDT actuation against IP LVDT sensing. (Klog 3553? http://klog.icrr.u-tokyo.ac.jp/osl/?r=3553) * Design PI Sensor blending filter. * Tune the LVDT sensitivity * Measure IP period; adjust ballast mass. * At some point (remotely)★ * Improve OL offloading. * Improve GAS offloading. * Spectral analysis of Oplev. * Design, install angular lock servo using OL. (Almost done for phase-I) * Adjust gains and debug damping for IM OSEMs and GAS LVDTs. (Almost done for phase-I) * Subtract DC level of Geophones. * Spectra analysis of PI sensors (PI LVDTs and Geophones). * Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs. * Set all EQ stops to TBD clearance. * Modify the model for IP coil driver control |
|
Line 140: | Line 100: |
* Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san). * Figure out how to make PI yaw adjustment reliable. |
|
Line 146: | Line 104: |
* --(Return/replace temporary ballast mass (dog clamps).)-- * Characterize replacement F0. * --(Wipe/clean arc weights that were rained on.)-- |
VIS Type B To-Do List
Archived items are at ../ToDoOld.
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2019-02-04
Etc
- Get additional two camera viewports.
- Get rid of all cable reels
- Run cables for cameras (with Kokeyama-san).
BS
- Install BNC cables for stepper remote enable, and debug.
SR2
- Check the IP stop height (if there's a excuse to open the tank).
- Release LBB; add approximate final ballast.
Install GAS Filters control loops. (Enzo)
Install IM control loops. (Enzo)
- Decide buoyancy correction and pre-apply as much as possible, leaving optic at nominal height.
- Install BNC cables for stepper remote enable, and debug.
- Install camera viewport.
- Install camera.
- Split model.
SR3
- Release the optical table again.
- Adjust LBB damper and rods to give correct height and gap at mid-range on the blades.
- Add approximate final ballast.
- Install camera viewport.
- Install camera.
- Debug stepper remote enable.
- Split model.
SRM
- Decide buoyancy correction and pre-apply as much as possible, leaving optic at nominal height.
- Install camera (with Kokeyama-san).
- Set up TILT OL.
- Set up LEN OL.
- Adjust LBB damper and rods to give correct height and gap at mid-range on the blades.
- Add approximate final ballast.
- Wipe inside tank with Vectra-Alpha wipes and IPA.
- Debug stepper remote enable.
- Install Enomoto-kun's beam target plate (if/when available).
- Split model.
Tasks To Be Scheduled
BS
- Tune BS LBB (adjust table height, damper height) - DON'T BOTHER (unless there's an excuse to open the lower half of the tank).
- Replace BS F0 thrust bearing and yaw adjuster - BIG JOB, DON'T BOTHER (unless lack of yaw adjustment becomes a major problem).
SR2
SR3
SRM
- Find two geophone cables used by Okutomi-san. (I looked in the second floor EXV room but didn't find them - Mark.)
- Find one geophone cable ordered for SRM but missing.
- Rearrange miswired geophone cable.
- Rebuild defective geophone cable.
- Put FC on SRM-W and install it in its holder with 1.4 mm shims ready for possible use.
Tunnel
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Mitaka or remotely
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Install damping filters for SR2.
- Review DAC channel requests.
- Split SRx real-time models?
ASAP
Documentation and Operation Manual
- Add useful info from Enzo's notebook to BSData.
Tasks Not To Forget
Major Tasks
Move safety bars from BS AF area to SR2 area.
- Update circuit diagram.
- (Time permitting) Try adding mass to IP.
- Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
Minor Tasks
Mechanical
- Put pointy-tipped screw in RM trolley for BS
Electrical
- Update BS Circuit diagram, D1503600
Note removal of LED/PD on TM OSEMs.
- Organize stepper reset system and watchdog BIO.
- Include information on assignment of channels to feedthrough positions.
- Reflect gender-changers and non-flipping feedthrough adapters.
- Reflect actual cable lengths.
- Include LVDT pin size (1 mm).
- Include Stepper pin size (1.6 mm).
Undo renumbering of IP items.
Page 10: "DIO Card # 0" should be "DIO Card # 1"
Include OutConfigBoards on OL page (Sheet 18).
Update HPCD section to reflect:
All three GAS channels are on HPCD #1 and DIO Card #2, CNB cables, Sheet 13.
Three IP channels are on HPCD #0 and DIO Card #2, CNA cables, Sheet 15.
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.