Differences between revisions 25 and 26
Revision 25 as of 2019-01-30 12:42:10
Size: 9660
Editor: MarkBarton
Comment:
Revision 26 as of 2019-02-01 19:11:32
Size: 4791
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 19: Line 19:
=== 2019-01-27 ===
=== 2019-02-04 ===
Line 21: Line 22:
 * --(Work with Akutsu-san to get additional two camera viewports (for SR2 and SRM).)-- Scheduled 1/31.  * Get additional two camera viewports.
Line 23: Line 24:
 * Currently we don't know where the SFs' and BFs' stepper motor are. We should decide whether we are going to move them soon or once they are in vacuum and in an stable suitable temperature (25 degrees for BS/SR2 and 24 degrees for SR3 and SRM).
 * --(Open all dead geophones, replace preamps, test, seal, retest.)--
Line 26: Line 25:
==== SR3 ====
 * Move the IP such that the horizontal stepper motors are in their respective mid-ranges. '''(Terrence Monday morning.)'''
 * Set the IP stops to an appropriate position. Confirm with Hirata-san who released the IP the latest.
 * Confirm the jacks supporting the mushroom head of the vacuum chamber must be withdrawn. If so, do it and center the IP again if necessary. '''(Monday.)'''
 * Center the IM in L, T, Y, V and R using the pico-motors. '''(Fabian and Terrence on Monday morning.)'''
 * Work with the alignment team when the yaw adjustment of the optic is required. ''Use the F0 yaw stepper motor''. '''(Maybe Monday.)'''
 * Work with the alignment team when the IM pitch requires adjustment. ''Use the IM pico-motor''. '''(Maybe Monday.)'''
 * Adjust the OSEM to a suitable position in case the pitch adjustment required cannot be achived in their current positions. This requires moving the panels sideways and/or the OSEM bodies in or out.
 * Once the OSEMs have been adjusted hang the optical table again. '''Now it is fixed to allow people sit or stand inside'''.
 * Release the IM/RM/OPT/IP. '''(Fujii-kun and Fabian on Monday afternoon.)'''
==== BS ====
 * Install BNC cables for stepper remote enable, and debug.
Line 37: Line 28:
==== SR2 (Very similar to SR3's with additional items underlined.) ==== ==== SR2 ====
 * Check the IP stop height (if there's a excuse to open the tank).
 * Release LBB; add approximate final ballast.
Line 40: Line 33:
 * --(Add additional mass to LBB to have it at the desired height.)--
 * Move the IP such that the horizontal stepper motors are in their respective mid-ranges. '''(Tuesday.)'''
 * Set the IP stops to an appropriate position. Confirm status with Enzo and Terrence.
 * Confirm the jacks supporting the mushroom head of the vacuum chamber must be withdrawn. If so, do it and center the IP again if necessary. '''(Tuesday.)'''
 * Centrer the IM in L, T, Y, V and R using the pico-motors. '''(Tuesday.)'''
 * Work with the alignment team when the yaw adjustment of the optic is required. ''Use the F0 yaw stepper motor''.
 * Work with the alignment team when the IM pitch requires adjustment. ''Use the IM pico-motor''.
 * __As requested by Enomoto-kun, work with him in the installation and cabling of the pick up mirror system. '''(Hirata-san has been assigned to this already.)''' __
 * __Fix the optical table to prepare for optic cleaning and OSEM adjustment (as per optic alignment requirement.)__
 * Adjust the OSEM to a suitable position in case the pitch adjustment required cannot be achived in their current positions. This requires moving the panels sideways and/or the OSEM bodies in or out.
 * __Liaise with Mirapro in removing the SR2 bellow at the +Y side. '''(Hirata-san.)'''__
 * Work with Hirose-san in cleaning the optic. '''(Hirata-san.)'''
 * __Once the OSEMs have been adjusted and the optic has been cleaned hang the optical table again.__

==== SRM ====
 * --(Fix/test geophones.)--
 * --(Raise suspension 3.5 mm on jacks.)--
 * Check/improve payload alignment and IM OSEMs. Recheck optic pitch with OL as needed.
 * Adjust F0 keystone trim to give desired height and secure weights in place.
 * Install geophones and arc weights.
 * Center and tune IP.
 * Hook LBB and add just enough ballast to have it bouncing.
 * Wipe inside tank with Vectra-Alpha wipes and IPA.
 * Set up TILT OL.

=== 2019-01-21 ===

==== BS (top priority) ====
 * Install last of IP control loops. '''(Enzo)'''
 * Install GAS Filters control loops. '''(Enzo)'''

==== SR3 (priority 2) ====

==== SR2 ====


=== 2019-02-04 ===
==== BS ====
==== SRM ====
 * Decide buoyancy correction and pre-apply as much as possible, leaving optic at nominal height.
 * Install BNC cables for stepper remote enable, and debug.
Line 80: Line 36:
 * Setup LEN OL.
 * Add additional ballast to LBB to set desired height (only if someone will be putting stuff on it).
 * Install Enomoto-kun's beam target plate (when available).

==== SR3 ====
 * Install camera viewport (already available).
 * Add additional ballast to LBB to set desired height (only if someone will be putting stuff on it).
Line 90: Line 39:
==== SR2 ====
 * Add camera viewport (when available).
==== SR3 ====
 * Release the optical table again.
 * Adjust LBB damper and rods to give correct height and gap at mid-range on the blades.
 * Add approximate final ballast.
 * Install camera viewport.
Line 94: Line 46:
 * Debug stepper remote enable.

==== SRM ====
 * Decide buoyancy correction and pre-apply as much as possible, leaving optic at nominal height.
 * Setup camera (with Kokeyama-san).
 * Set up TILT OL.
 * Set up LEN OL.
 * Install Enomoto-kun's beam target plate (if/when available).
 * Adjust LBB damper and rods to give correct height and gap at mid-range on the blades.
 * Add approximate final ballast.
 * Wipe inside tank with Vectra-Alpha wipes and IPA.
 * Debug stepper remote enable.
Line 115: Line 79:
 * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
Line 122: Line 85:
 * --(Get picomotor drivers back on line.)--
 * --(Debug BS BIO connections, especially PI IP.)--
Line 125: Line 86:
=== Main Assembly Sequence ===
 * Necessary for phase-I★★★
  * --(Modify IP LVDT damping filters to include set point.)--
  * --(TFs.)--
  * '''''EXCHANGE YAW/VERT FRs at F0'''''

 * Necessary for phase-II★★
  * Debug BS geophones.
  * Flip circuit boards in BS geophones to make them the same as SRx.
  * Calibrate IP LVDT actuation against IP LVDT sensing. (Klog 3553? http://klog.icrr.u-tokyo.ac.jp/osl/?r=3553)
  * Design PI Sensor blending filter.
  * Tune the LVDT sensitivity
  * Measure IP period; adjust ballast mass.
  * Diagonalization of IM for SR2, SR3, SRM. Is BS one done?'''(When?)'''

 * At some point (remotely)★
  * Improve OL offloading.
  * Improve GAS offloading.
  * Spectral analysis of Oplev.
  * Design, install angular lock servo using OL. (Almost done for phase-I)
  * Adjust gains and debug damping for IM OSEMs and GAS LVDTs. (Almost done for phase-I)
  * Subtract DC level of Geophones.
  * Spectra analysis of PI sensors (PI LVDTs and Geophones).
  * Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
  * Set all EQ stops to TBD clearance.
  * Modify the model for IP coil driver control
Line 163: Line 98:
 * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
 * Figure out how to make PI yaw adjustment reliable.
Line 169: Line 102:
 * --(Return/replace temporary ballast mass (dog clamps).)--
 * Characterize replacement F0.
 * --(Wipe/clean arc weights that were rained on.)--

VIS Type B To-Do List

Archived items are at ../ToDoOld.

Every Week

Coming Weeks

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

2019-02-04

Etc

  • Get additional two camera viewports.
  • Get rid of all cable reels

BS

  • Install BNC cables for stepper remote enable, and debug.

SR2

  • Check the IP stop height (if there's a excuse to open the tank).
  • Release LBB; add approximate final ballast.
  • Install GAS Filters control loops. (Enzo)

  • Install IM control loops. (Enzo)

  • Decide buoyancy correction and pre-apply as much as possible, leaving optic at nominal height.
  • Install BNC cables for stepper remote enable, and debug.
  • Install camera viewport.
  • Install camera.
  • Run cables for camera.

SR3

  • Release the optical table again.
  • Adjust LBB damper and rods to give correct height and gap at mid-range on the blades.
  • Add approximate final ballast.
  • Install camera viewport.
  • Install camera.
  • Run cables for camera.
  • Debug stepper remote enable.

SRM

  • Decide buoyancy correction and pre-apply as much as possible, leaving optic at nominal height.
  • Setup camera (with Kokeyama-san).
  • Set up TILT OL.
  • Set up LEN OL.
  • Install Enomoto-kun's beam target plate (if/when available).
  • Adjust LBB damper and rods to give correct height and gap at mid-range on the blades.
  • Add approximate final ballast.
  • Wipe inside tank with Vectra-Alpha wipes and IPA.
  • Debug stepper remote enable.

Tasks To Be Scheduled

BS

  • Tune BS LBB (adjust table height, damper height) - DON'T BOTHER (unless there's an excuse to open the lower half of the tank).
  • Replace BS F0 thrust bearing and yaw adjuster - BIG JOB, DON'T BOTHER (unless lack of yaw adjustment becomes a major problem).

SR2

SR3

SRM

  • Find two geophone cables used by Okutomi-san. (I looked in the second floor EXV room but didn't find them - Mark.)
  • Find one geophone cable ordered for SRM but missing.
  • Rearrange miswired geophone cable.
  • Rebuild defective geophone cable.
  • Put FC on SRM-W and install it in its holder with 1.4 mm shims ready for possible use.

Tunnel

  • Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
  • Check SR2, SR3 TM coil gains for magnet polarity compensation.
  • Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

Mitaka or remotely

  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Install damping filters for SR2.
  • Review DAC channel requests.
  • Split SRx real-time models?

ASAP

Documentation and Operation Manual

  • Add useful info from Enzo's notebook to BSData.

Tasks Not To Forget

Major Tasks

  • Move safety bars from BS AF area to SR2 area.

  • Update circuit diagram.
  • (Time permitting) Try adding mass to IP.
  • Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.

Minor Tasks

Mechanical

  • Put pointy-tipped screw in RM trolley for BS

Electrical

  • Update BS Circuit diagram, D1503600
    • Note removal of LED/PD on TM OSEMs.

    • Organize stepper reset system and watchdog BIO.
    • Include information on assignment of channels to feedthrough positions.
    • Reflect gender-changers and non-flipping feedthrough adapters.
    • Reflect actual cable lengths.
    • Include LVDT pin size (1 mm).
    • Include Stepper pin size (1.6 mm).
    • Undo renumbering of IP items.

    • Page 10: "DIO Card # 0" should be "DIO Card # 1"

    • Include OutConfigBoards on OL page (Sheet 18).

    • Update HPCD section to reflect:

      • All three GAS channels are on HPCD #1 and DIO Card #2, CNB cables, Sheet 13.

      • Three IP channels are on HPCD #0 and DIO Card #2, CNA cables, Sheet 15.

Real-time and SUMCON models

  • Create SUMCON models for full BS and major installation milestones.
  • Create controls design description (cf LIGO-T1100378).

  • Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
  • Understand/document/debug Kokeyama-san's DIO stuff.
  • Measure LPCD and HPCD output filter response.
  • Design and install software compensation filters for LPCD and HPCD output filters.

KAGRA/Subgroups/VIS/TypeB/ToDo (last edited 2019-12-18 12:38:30 by fabian.arellano)