Line 22: Line 22:
 * Get additional two camera viewports.
 * Get rid of all cable reels
 * Run cables for cameras (with Kokeyama-san).
 * --(Get additional two camera viewports.)--
 * --(Get rid of SRM cable reel.)--
 * --(Run cables for cameras (with Kokeyama-san).)--
 * --(Install BIO config boards on OL whitening filters for SR2, SR3, SRM)--
 * Get rid of SR2 cable reel (shutdown FE and rack, replug everything into new power strip, start up rack and FE).
 * Wipe inside tanks with Vectra-Alpha wipes and IPA.
Line 27: Line 30:
 * Install BNC cables for stepper remote enable, and debug.  * --(Install BNC cables for stepper remote enable.)--
* Debug stepper remote enable.
 * Debug BS camera.
 
Line 30: Line 36:
 * Check the IP stop height (if there's a excuse to open the tank).
 * Release LBB; add approximate final ballast.
 * Install GAS Filters control loops. '''(Enzo)'''
 * Install IM control loops. '''(Enzo)'''
 * Decide buoyancy correction and pre-apply as much as possible, leaving optic at nominal height.
 * Install BNC cables for stepper remote enable, and debug.
 * Install camera viewport.
 * Install camera.
 * --(Release LBB; add approximate final ballast.)--
 * --(Install IM control loops.)--
 * --(Decide buoyancy correction and pre-apply as much as possible, leaving optic at nominal height.)--
 * --(Install BNC cables for stepper remote enable.)--
 * --(Install camera viewport.)--
 * --(Install camera.)--
 * Install GAS filter control loops.
 * Debug stepper remote enable.
Line 41: Line 47:
 * Release the optical table again.
 *
Adjust LBB damper and rods to give correct height and gap at mid-range on the blades.
 *
Add approximate final ballast.
 *
Install camera viewport.
 *
Install camera.
 * --(Release the optical table again.)--
 * --(
Adjust LBB damper and rods to give correct height and gap at mid-range on the blades.)--
 * --(
Add approximate final ballast.)--
 * --(
Install camera viewport.)--
 * --(
Install camera.)--
Line 50: Line 56:
 * Decide buoyancy correction and pre-apply as much as possible, leaving optic at nominal height.
 *
Install camera (with Kokeyama-san).
 *
Set up TILT OL.
 * --(Decide buoyancy correction and pre-apply as much as possible, leaving optic at nominal height.)--
 * --(
Install camera (with Kokeyama-san).)--
 * --(
Set up TILT OL.)--
 * --(Adjust LBB damper and rods to give correct height and gap at mid-range on the blades.)--
 * --(Add approximate final ballast.)--
 * --(Split model.)--
Line 54: Line 63:
 * Adjust LBB damper and rods to give correct height and gap at mid-range on the blades.
 * Add approximate final ballast.
 * Wipe inside tank with Vectra-Alpha wipes and IPA.
Line 58: Line 64:
 * Install Enomoto-kun's beam target plate (if/when available).
 * Split model.
 * Check BIO connections for possible swap of GAS/IP.
Line 69: Line 74:
 * Install Enomoto-kun's beam target plate (if/when available).
Line 76: Line 82:
 * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
 * Check SR2, SR3 TM coil gains for magnet polarity compensation.
Line 86: Line 90:
== ASAP ==
=== Real-Time Model ===
 * Restart k1vissrmt (Wednesday during maintenance??):
  * Stop SRM Guardian (just stop it dead - don't transition to SAFE; don't let it meddle at all).
  * Make fresh safe.snap.
  * Note all TEST and OPTIC ALIGN offsets.
  * Put large ramp times (≈30++ s) in all DAMP, TEST and OPTICALIGN filters.
  * Turn off all DAMP, TEST, and OPTICALIGN filter offsets and master switch.
  * Restart k1vissrmt. If there are gross problems, consider restarting the whole FE.
  * Restore safe.snap.
  * Debug OVERVIEW and IP screens (check for white channels etc).
  * Restore OPTICALIGN offsets (if necessary), transfer TEST offsets to new ALIGN filters and set long ramp times.
  * Set new WD thresholds for IP LVDT and ACC.
  * Enable all DAMP, ALIGN, and OPTICALIGN offsets.
  * Make sure SRM Guardian is pointing to generic Type B Guardian.
  * Adjust Type B Guardian code to set long ramp times on all DAMP, ALIGN and OPTICALIGN filters. Wrap the
  * Reenable Guardian if/when satisfied.
 * Rebuild and restart k1visbst and initialize/test as for SRM.
 * Create new k1vissr2t, k1vissr2p, k1vissr3t, k1vissr3p based on k1vissrmt and k1vissrmp.
 * Update DCUID numbers in /opt/rtcds/userapps/release/vis/common/medm/vissr2_overview_macro.txt and vissr3_overview_macro.txt.
  * SR2 FECT=54, FECT=55
  * SR3 FECT=56, FECT=57
  * (SRM FECT=58, FECP=59)
 * Rebuild, restart k1vissr2t, k1vissr2p, k1vissr3t, k1vissr3p and initialize/test as for SRM/BS.

VIS Type B To-Do List

Archived items are at ../ToDoOld.

Every Week

Coming Weeks

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

2019-02-04

Etc

  • Get additional two camera viewports.

  • Get rid of SRM cable reel.

  • Run cables for cameras (with Kokeyama-san).

  • Install BIO config boards on OL whitening filters for SR2, SR3, SRM

  • Get rid of SR2 cable reel (shutdown FE and rack, replug everything into new power strip, start up rack and FE).
  • Wipe inside tanks with Vectra-Alpha wipes and IPA.

BS

  • Install BNC cables for stepper remote enable.

  • Debug stepper remote enable.
  • Debug BS camera.

SR2

  • Release LBB; add approximate final ballast.

  • Install IM control loops.

  • Decide buoyancy correction and pre-apply as much as possible, leaving optic at nominal height.

  • Install BNC cables for stepper remote enable.

  • Install camera viewport.

  • Install camera.

  • Install GAS filter control loops.
  • Debug stepper remote enable.
  • Split model.

SR3

  • Release the optical table again.

  • Adjust LBB damper and rods to give correct height and gap at mid-range on the blades.

  • Add approximate final ballast.

  • Install camera viewport.

  • Install camera.

  • Debug stepper remote enable.
  • Split model.

SRM

  • Decide buoyancy correction and pre-apply as much as possible, leaving optic at nominal height.

  • Install camera (with Kokeyama-san).

  • Set up TILT OL.

  • Adjust LBB damper and rods to give correct height and gap at mid-range on the blades.

  • Add approximate final ballast.

  • Split model.

  • Set up LEN OL.
  • Debug stepper remote enable.
  • Check BIO connections for possible swap of GAS/IP.

Tasks To Be Scheduled

BS

  • Tune BS LBB (adjust table height, damper height) - DON'T BOTHER (unless there's an excuse to open the lower half of the tank).
  • Replace BS F0 thrust bearing and yaw adjuster - BIG JOB, DON'T BOTHER (unless lack of yaw adjustment becomes a major problem).

SR2

SR3

SRM

  • Install Enomoto-kun's beam target plate (if/when available).
  • Find two geophone cables used by Okutomi-san. (I looked in the second floor EXV room but didn't find them - Mark.)
  • Find one geophone cable ordered for SRM but missing.
  • Rearrange miswired geophone cable.
  • Rebuild defective geophone cable.
  • Put FC on SRM-W and install it in its holder with 1.4 mm shims ready for possible use.

Tunnel

  • Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

Mitaka or remotely

  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Install damping filters for SR2.
  • Review DAC channel requests.
  • Split SRx real-time models?

Real-Time Model

  • Restart k1vissrmt (Wednesday during maintenance??):
    • Stop SRM Guardian (just stop it dead - don't transition to SAFE; don't let it meddle at all).
    • Make fresh safe.snap.
    • Note all TEST and OPTIC ALIGN offsets.
    • Put large ramp times (≈30++ s) in all DAMP, TEST and OPTICALIGN filters.
    • Turn off all DAMP, TEST, and OPTICALIGN filter offsets and master switch.
    • Restart k1vissrmt. If there are gross problems, consider restarting the whole FE.
    • Restore safe.snap.
    • Debug OVERVIEW and IP screens (check for white channels etc).
    • Restore OPTICALIGN offsets (if necessary), transfer TEST offsets to new ALIGN filters and set long ramp times.
    • Set new WD thresholds for IP LVDT and ACC.
    • Enable all DAMP, ALIGN, and OPTICALIGN offsets.
    • Make sure SRM Guardian is pointing to generic Type B Guardian.
    • Adjust Type B Guardian code to set long ramp times on all DAMP, ALIGN and OPTICALIGN filters. Wrap the
    • Reenable Guardian if/when satisfied.
  • Rebuild and restart k1visbst and initialize/test as for SRM.
  • Create new k1vissr2t, k1vissr2p, k1vissr3t, k1vissr3p based on k1vissrmt and k1vissrmp.
  • Update DCUID numbers in /opt/rtcds/userapps/release/vis/common/medm/vissr2_overview_macro.txt and vissr3_overview_macro.txt.
    • SR2 FECT=54, FECT=55
    • SR3 FECT=56, FECT=57
    • (SRM FECT=58, FECP=59)
  • Rebuild, restart k1vissr2t, k1vissr2p, k1vissr3t, k1vissr3p and initialize/test as for SRM/BS.

Documentation and Operation Manual

  • Add useful info from Enzo's notebook to BSData.

Tasks Not To Forget

Major Tasks

  • Move safety bars from BS AF area to SR2 area.

  • Update circuit diagram.
  • (Time permitting) Try adding mass to IP.
  • Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.

Minor Tasks

Mechanical

  • Put pointy-tipped screw in RM trolley for BS

Electrical

  • Update BS Circuit diagram, D1503600
    • Note removal of LED/PD on TM OSEMs.

    • Organize stepper reset system and watchdog BIO.
    • Include information on assignment of channels to feedthrough positions.
    • Reflect gender-changers and non-flipping feedthrough adapters.
    • Reflect actual cable lengths.
    • Include LVDT pin size (1 mm).
    • Include Stepper pin size (1.6 mm).
    • Undo renumbering of IP items.

    • Page 10: "DIO Card # 0" should be "DIO Card # 1"

    • Include OutConfigBoards on OL page (Sheet 18).

    • Update HPCD section to reflect:

      • All three GAS channels are on HPCD #1 and DIO Card #2, CNB cables, Sheet 13.

      • Three IP channels are on HPCD #0 and DIO Card #2, CNA cables, Sheet 15.

Real-time and SUMCON models

  • Create SUMCON models for full BS and major installation milestones.
  • Create controls design description (cf LIGO-T1100378).

  • Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
  • Understand/document/debug Kokeyama-san's DIO stuff.
  • Measure LPCD and HPCD output filter response.
  • Design and install software compensation filters for LPCD and HPCD output filters.

KAGRA/Subgroups/VIS/TypeB/ToDo (last edited 2019-12-18 12:38:30 by fabian.arellano)