Line 21: | Line 21: |
=== 2019-01-21 === |
|
Line 22: | Line 24: |
* Work with Telada-san to get reference height marks on SR tanks. * Work with Simon to get additional OL parts. |
|
Line 25: | Line 25: |
* Open all dead geophones, replace preamps, test, seal, retest. * Get rid of all cable reels. |
|
Line 27: | Line 29: |
* Get new F0 FR working (reassemble carriage in correct order?). * Center new F0 FR (mid-range height is 75 mm). |
* Install a working set of geophones, e.g., from SR3. * Fix touching issue? |
Line 30: | Line 32: |
* Add more arc weights to further improve the IP frequency, and re-center IP as needed. * Re-calibrate the F0 GAS LVDT, measuring down from the ring (nominal 16.5 mm) rather than up from the milled recess (nominal 154.5mm). * Adjust the SF damper spacing? (Currently ≈3.5 mm - 6.5 mm was optimum for SRs.) |
|
Line 34: | Line 33: |
* Immobilize the F0 lock nut and screw used to protect the payload and SF damper. | |
Line 36: | Line 34: |
==== SRM ==== * Open geophones from BS, replace preamps, test, seal, retest. * Check/improve payload alignment and IM OSEMs. Recheck optic pitch with OL as needed. * Get new F0 yaw mechanism working (reassemble carriage in correct order?). |
==== SRM ==== * Raise suspension 3.5 mm on jacks. * Check/improve payload alignment and IM OSEMs. Recheck optic pitch with OL as needed.\ |
Line 41: | Line 38: |
* Measure height of RM/TM relative to SS and height of SS relative to tank or Telada-san's reference. Raise suspension on jacks if necessary. | |
Line 47: | Line 43: |
* Set up OL (needs various parts). ==== SR3 ==== * Adjust height. |
* Set up TILT OL. * Install Enomoto-kun's beam target plate (when available). ==== SR3 ==== * Survey optic height and raise suspension on jacks as necessary. |
Line 55: | Line 51: |
* Wipe inside tank with Vectra-Alpha wipes and IPA. ==== SR2 ==== * Do * Adjust height. |
==== SR2 ==== * Survey optic height and raise suspension on jacks as necessary. |
Line 63: | Line 56: |
* Add camera viewport (when available). | |
Line 65: | Line 57: |
=== 2019-01-21 === ==== BS ==== ==== SRM ==== * Install Enomoto-kun's beam target plate (when available). ==== SR3 ==== |
=== 2019-01-28 === ==== BS ==== ==== SRM ==== * Install camera viewport. (Mirapro will be available 1/28) * Setup LEN OL. ==== SR3 ==== |
Line 72: | Line 65: |
==== SR2 ==== | ==== SR2 ==== * Add camera viewport (when available). |
Line 78: | Line 72: |
=== 2019-01-28 === ==== BS ==== ==== SRM ==== * Install camera viewport. (Mirapro will be available 1/28) ==== SR3 ==== ==== SR2 ==== |
VIS Type B To-Do List
Archived items are at ../ToDoOld.
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2019-01-14
2019-01-21
Etc
- Work with Akutsu-san to get additional two camera viewports (for SR2 and SRM).
- Open all dead geophones, replace preamps, test, seal, retest.
- Get rid of all cable reels.
BS (top priority)
- Install a working set of geophones, e.g., from SR3.
- Fix touching issue?
- Adjust amount of mass on F0 keystone to get correct height, and secure in place.
- Recenter the OL.
SRM
- Raise suspension 3.5 mm on jacks.
- Check/improve payload alignment and IM OSEMs. Recheck optic pitch with OL as needed.\
- Adjust F0 keystone trim to give desired height and secure weights in place.
- Install geophones and arc weights.
- Center and tune IP.
- Hook LBB and add just enough ballast to have it bouncing.
- Add additional ballast to LBB to set desired height (only if someone will be putting stuff on it).
- Wipe inside tank with Vectra-Alpha wipes and IPA.
- Set up TILT OL.
- Install Enomoto-kun's beam target plate (when available).
SR3
- Survey optic height and raise suspension on jacks as necessary.
- Reinstall OL LED (original one borrowed for SR2 - probably use new one to be supplied by Simon), probably change collimator, and realign OL.
- Install camera viewport (already available).
- Measure height of RM/TM relative to SS and height of SS relative to tank or Telada-san's reference. Raise suspension on jacks if necessary.
- Add additional ballast to LBB to set desired height (only if someone will be putting stuff on it).
SR2
- Survey optic height and raise suspension on jacks as necessary.
- Remove tape, writing etc on PI and PI items.
- Add ballast mass to LBB to have it bouncing.
- Measure height of RM/TM relative to SS and height of SS relative to tank or Telada-san's reference. Raise suspension on jacks if necessary.
2019-01-28
BS
SRM
- Install camera viewport. (Mirapro will be available 1/28)
- Setup LEN OL.
SR3
- Install camera.
- Run cables for camera.
SR2
- Add camera viewport (when available).
- Add new feedthrough to lower part of tank (with Izumi-san-tachi)?
- Install cable for MIF pico on LBB (with Izumi-san-tachi)?
- Add additional mass to LBB to have it at the desired height
- Install camera.
- Run cables for camera.
Tasks To Be Scheduled
BS
- Tune BS LBB (adjust table height, damper height) - DON'T BOTHER (unless there's an excuse to open the lower half of the tank).
- Replace BS F0 thrust bearing and yaw adjuster - BIG JOB, DON'T BOTHER (unless lack of yaw adjustment becomes a major problem).
SR2
SR3
SRM
- Find two geophone cables used by Okutomi-san. (I looked in the second floor EXV room but didn't find them - Mark.)
- Find one geophone cable ordered for SRM but missing.
- Rearrange miswired geophone cable.
- Rebuild defective geophone cable.
- Put FC on SRM-W and install it in its holder with 1.4 mm shims ready for possible use.
Tunnel
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Mitaka or remotely
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Install damping filters for SR2.
- Review DAC channel requests.
- Split SRx real-time models?
ASAP
Get picomotor drivers back on line.
Debug BS BIO connections, especially PI IP.
Main Assembly Sequence
- Necessary for phase-I★★★
Modify IP LVDT damping filters to include set point.
TFs.
EXCHANGE YAW/VERT FRs at F0
- Necessary for phase-II★★
- Debug BS geophones.
- Flip circuit boards in BS geophones to make them the same as SRx.
Calibrate IP LVDT actuation against IP LVDT sensing. (Klog 3553? http://klog.icrr.u-tokyo.ac.jp/osl/?r=3553)
- Design PI Sensor blending filter.
- Tune the LVDT sensitivity
- Measure IP period; adjust ballast mass.
- At some point (remotely)★
- Improve OL offloading.
- Improve GAS offloading.
- Spectral analysis of Oplev.
- Design, install angular lock servo using OL. (Almost done for phase-I)
- Adjust gains and debug damping for IM OSEMs and GAS LVDTs. (Almost done for phase-I)
- Subtract DC level of Geophones.
- Spectra analysis of PI sensors (PI LVDTs and Geophones).
- Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
- Set all EQ stops to TBD clearance.
- Modify the model for IP coil driver control
Documentation and Operation Manual
- Add useful info from Enzo's notebook to BSData.
Tasks Not To Forget
Major Tasks
Move safety bars from BS AF area to SR2 area.
- Update circuit diagram.
- (Time permitting) Try adding mass to IP.
- Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
- Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
- Figure out how to make PI yaw adjustment reliable.
Minor Tasks
Mechanical
- Put pointy-tipped screw in RM trolley for BS
Return/replace temporary ballast mass (dog clamps).
- Characterize replacement F0.
Wipe/clean arc weights that were rained on.
Electrical
- Update BS Circuit diagram, D1503600
Note removal of LED/PD on TM OSEMs.
- Organize stepper reset system and watchdog BIO.
- Include information on assignment of channels to feedthrough positions.
- Reflect gender-changers and non-flipping feedthrough adapters.
- Reflect actual cable lengths.
- Include LVDT pin size (1 mm).
- Include Stepper pin size (1.6 mm).
Undo renumbering of IP items.
Page 10: "DIO Card # 0" should be "DIO Card # 1"
Include OutConfigBoards on OL page (Sheet 18).
Update HPCD section to reflect:
All three GAS channels are on HPCD #1 and DIO Card #2, CNB cables, Sheet 13.
Three IP channels are on HPCD #0 and DIO Card #2, CNA cables, Sheet 15.
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.