VIS Type B To-Do List
Archived items are at ../ToDoOld.
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2019-01-07,14,21
BS (top priority)
- Check that the suspension is floating.
- Re-center OL and log value to capture yaw position.
- Look for cracks in F0 blades.
Install new double-sided F0 fishing rod (need to get blades) and (if necessary) auxiliary CuBe spring.
- Check that current defective yaw adjuster is at least locating the suspension in yaw.
- Remove and service or swap out geophones (one has high noise, one has DC offset, all have flipped pinouts). Could use new geophones originally intended for SRM to save time.
- Replace geophones and add more arc weights to IP to get a lower frequency.
- Re-calibrate F0 GAS LVDT.
- Adjust amount of mass on F0 keystone to get correct height, and secure in place.
- Confirm the positions of the IP LVDTs and Actuators, and update T1707205 if necessary.
- Install camera viewport???
SRM
- Test new yaw mechanism.
- Adjust F0 keystone mass to give desired height and secure weights in place.
- Measure height of RM/TM relative to SS and height of SS relative to tank or Telada-san's reference. Raise suspension on jacks if necessary.
- Borrow LED from SR2 and check/adjust optic pitch; return LED to SR2.
- Install Enomoto-kun's beam target plate (if available).
- Seal geophones.
- Install geophones and arc weights.
- Center and tune IP.
- Install OL viewport (already available).
- Install camera viewport if available. (At a minimum, remove flange cover temporarily and check that there is a good view of the HR surface.)
- Hook LBB and add just enough ballast to have it bouncing.
- Add additional ballast to LBB to set desired height (only if someone will be putting stuff on it).
- Set up OL (needs various parts).
SR3
- Install/test new yaw mechanism.
- Adjust height.
- Realign OL.
- Install camera viewport (already available).
- Measure height of RM/TM relative to SS and height of SS relative to tank or Telada-san's reference. Raise suspension on jacks if necessary.
- Add additional ballast to LBB to set desired height (only if someone will be putting stuff on it).
SR2
- Adjust height.
- Remove tape, writing etc on PI and PI items.
- Add new feedthrough to lower part of tank (with Izumi-san-tachi)?
- Install cable for MIF pico on LBB (with Izumi-san-tachi)?
- Add ballast mass to LBB.
- Measure height of RM/TM relative to SS and height of SS relative to tank or Telada-san's reference. Raise suspension on jacks if necessary.
Tasks To Be Scheduled
BS
- Tune BS LBB (adjust table height, damper height) - DON'T BOTHER (unless there's an excuse to open the lower half of the tank).
- Replace BS F0 thrust bearing and yaw adjuster - BIG JOB, DON'T BOTHER (unless lack of yaw adjustment becomes a major problem).
SR2
SR3
SRM
- Find two geophone cables used by Okutomi-san. (I looked in the second floor EXV room but didn't find them - Mark.)
- Find one geophone cable ordered for SRM but missing.
- Rearrange miswired geophone cable.
- Rebuild defective geophone cable.
Tunnel
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Mitaka or remotely
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Install damping filters for SR2.
- Review DAC channel requests.
- Split SRx real-time models?
ASAP
Get picomotor drivers back on line.
Debug BS BIO connections, especially PI IP.
Main Assembly Sequence
- Necessary for phase-I★★★
Modify IP LVDT damping filters to include set point.
TFs.
EXCHANGE YAW/VERT FRs at F0
- Necessary for phase-II★★
- Debug BS geophones.
- Flip circuit boards in BS geophones to make them the same as SRx.
Calibrate IP LVDT actuation against IP LVDT sensing. (Klog 3553? http://klog.icrr.u-tokyo.ac.jp/osl/?r=3553)
- Design PI Sensor blending filter.
- Tune the LVDT sensitivity
- Measure IP period; adjust ballast mass.
- At some point (remotely)★
- Improve OL offloading.
- Improve GAS offloading.
- Spectral analysis of Oplev.
- Design, install angular lock servo using OL. (Almost done for phase-I)
- Adjust gains and debug damping for IM OSEMs and GAS LVDTs. (Almost done for phase-I)
- Subtract DC level of Geophones.
- Spectra analysis of PI sensors (PI LVDTs and Geophones).
- Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
- Set all EQ stops to TBD clearance.
- Modify the model for IP coil driver control
Documentation and Operation Manual
- Add useful info from Enzo's notebook to BSData.
Tasks Not To Forget
Major Tasks
Move safety bars from BS AF area to SR2 area.
- Update circuit diagram.
- (Time permitting) Try adding mass to IP.
- Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
- Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
- Figure out how to make PI yaw adjustment reliable.
Minor Tasks
Mechanical
- Put pointy-tipped screw in RM trolley for BS
Return/replace temporary ballast mass (dog clamps).
- Characterize replacement F0.
Wipe/clean arc weights that were rained on.
Electrical
- Update BS Circuit diagram, D1503600
Note removal of LED/PD on TM OSEMs.
- Organize stepper reset system and watchdog BIO.
- Include information on assignment of channels to feedthrough positions.
- Reflect gender-changers and non-flipping feedthrough adapters.
- Reflect actual cable lengths.
- Include LVDT pin size (1 mm).
- Include Stepper pin size (1.6 mm).
Undo renumbering of IP items.
Page 10: "DIO Card # 0" should be "DIO Card # 1"
Include OutConfigBoards on OL page (Sheet 18).
Update HPCD section to reflect:
All three GAS channels are on HPCD #1 and DIO Card #2, CNB cables, Sheet 13.
Three IP channels are on HPCD #0 and DIO Card #2, CNA cables, Sheet 15.
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.