Line 3: | Line 3: |
To-Do List 2017-03-13 | 2017-04-03 |
Line 5: | Line 5: |
== Facilities == * Vacuum and roll floor (All) * Wipe ladders (All) * Tidy tools, parts (All) * Find missing light lent to Kokeyama-san (Mark) * Mark/photograph/count peeling patches on the floor. * Mark/photograph/count pillars with bare concrete bases. |
== Facilities (mostly full team) == * Clean up after floor work. * Vacuum and roll floor. * Wipe ladders. * Tidy tools, parts. |
Line 13: | Line 11: |
== Electronics == | == PI Move == * General prep * Decide if air shower needs to be moved. * Triple-check dimensions around second-floor parking spot for PI; decide best place for pallet. * Check for obstacles along path around -X side of cleanbooth. * Find/clean Saito-sensei's PI lifting adapter and any needed fasteners. * Check both crane remote controls (clean and dirty) are charged. * Prepare PI for moving. * Remove accelerometers and store safely. * Remove large weights. (How? With forklift at last minute? Where to?) * Remove arc weights (move some to second floor, wrap rest for storage). * Attach lifting plates. * Wrap with clingwrap, cover with spare cleanbag. * Remove old cabling from PI to rack. * Prepare second floor for receiving PI. * Clean and clingwrap pallet. * Find metal plates and/or duckboards for on top of pallets. * Move BS cables on -Y side of tank off top of beam. * Find shims (about 75 mm high) to put on beam where cables were, to help support pallet. * Clear path to remove PI with forklift. * Move any obstacles identified previously. * Shutdown BS/PR2 racks and move electrical cables. * Move any stored items on -Y side of portable cleanroom. * Move portable cleanroom towards -Y. * Move worktables from next to BS/PR2 racks. * Move PI * Disconnect fan cables, curtain (Miyoki-san). * Unzip ceiling panel. * Crane pallet into cleanbooth. * Lay foil on pallet. * Forklift PI to -X,+Y corner of cleanbooth * Crane PI into clean booth. * Cleanup * Zip up ceiling panel. * Reconnect fan cables, curtain (Miyoki-san). * Replace tables near BS/PR2 racks * Move portable cleanroom back to original spot. * Re-lay electrical cables. * Power up racks. |
Line 15: | Line 51: |
* Wire up BF roll/pitch picos (Enzo) * Work with Miyo-kun to get pico drivers added to BS rack and screens (Enzo, Mark) * Grab remaining cables etc per E1605111 and update document (Enzo) * Update E1503600 with DIO card for HPCDs, etc, etc. (Enzo) |
== Continue PI Prep == * Finish reattaching repaired LVDT coil(s) and redoing connectors with correct gender. * Install fishing rod. * Find table, weights, etc for use with LBB blade bending jigs. * Install LLB blades. * Install LLB blade units in PI. == Hanging BF/IRM/IM/RM/BS (mostly Mark, Fabian, Perry) == * Reroute in-vacuum cables up to SF level; add in-vacuum extension cables if necessary. * Test SF LVDT. * Test SF fishing rod stepper. == Electronics (mostly Enzo, Mark) == * Make more anti-feedthrough adapters. * Add retaining screws to cables at feedthroughs (mostly done, needs finishing). * Work with Miyo-kun to get pico drivers added to BS rack and screens * Update E1503600 with DIO card for HPCDs, etc, etc. |
Line 20: | Line 69: |
* Send list of required in-vacuum cables to Takahashi-san (Enzo, Mark) * Debug 900 Hz noise on BF LVDT output (Enzo, Mark) * Debug excess noise on TM-H3 OSEM (Enzo, Mark) |
* Send list of required in-vacuum cables to Takahashi-san |
Line 26: | Line 73: |
== PI Prep == * Inspect PI, compare to CAD and 2D drawings (Hirata, Mark) * Identify missing PI parts (Hirata, Mark) * Find and reattach repaired LVDT coil(s) (???) == Hanging BF/IRM/IM/RM/BS == * Correct orientation of SF cap (Mark, Fabian, Perry) * Correct orientation of SF (Mark, Fabian, Perry) * Find/attach cable clamps for SF (Fabian) == Real-time and SUMCON models == * Update SUMCON model of full BS (Perry?, Okitomi?, Mark?) * Do cut-down SUMCON model of just payload hanging from fixed BS (Perry?, Okitomi?, Mark?) * Compare measured TFs to cut-down model * Create a proper DAC Monitor MEDM screen * Improve ADC Monitor MEDM screen |
== Real-time and SUMCON models (mostly Perry, Mark) == * Get Perry (and Enzo) set up with SUMCON. * Update SUMCON model of full BS. * Do cut-down SUMCON model of just payload hanging from fixed BS. * Compare measured TFs to cut-down model(s). * Create a proper DAC Monitor MEDM screen. * Improve ADC Monitor MEDM screen. |
VIS Type B Near Term To-Do List
2017-04-03
Facilities (mostly full team)
- Clean up after floor work.
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
PI Move
- General prep
- Decide if air shower needs to be moved.
- Triple-check dimensions around second-floor parking spot for PI; decide best place for pallet.
- Check for obstacles along path around -X side of cleanbooth.
- Find/clean Saito-sensei's PI lifting adapter and any needed fasteners.
- Check both crane remote controls (clean and dirty) are charged.
- Prepare PI for moving.
- Remove accelerometers and store safely.
- Remove large weights. (How? With forklift at last minute? Where to?)
- Remove arc weights (move some to second floor, wrap rest for storage).
- Attach lifting plates.
- Wrap with clingwrap, cover with spare cleanbag.
- Remove old cabling from PI to rack.
- Prepare second floor for receiving PI.
- Clean and clingwrap pallet.
- Find metal plates and/or duckboards for on top of pallets.
- Move BS cables on -Y side of tank off top of beam.
- Find shims (about 75 mm high) to put on beam where cables were, to help support pallet.
- Clear path to remove PI with forklift.
- Move any obstacles identified previously.
- Shutdown BS/PR2 racks and move electrical cables.
- Move any stored items on -Y side of portable cleanroom.
- Move portable cleanroom towards -Y.
- Move worktables from next to BS/PR2 racks.
- Move PI
- Disconnect fan cables, curtain (Miyoki-san).
- Unzip ceiling panel.
- Crane pallet into cleanbooth.
- Lay foil on pallet.
- Forklift PI to -X,+Y corner of cleanbooth
- Crane PI into clean booth.
- Cleanup
- Zip up ceiling panel.
- Reconnect fan cables, curtain (Miyoki-san).
- Replace tables near BS/PR2 racks
- Move portable cleanroom back to original spot.
- Re-lay electrical cables.
- Power up racks.
Continue PI Prep
- Finish reattaching repaired LVDT coil(s) and redoing connectors with correct gender.
- Install fishing rod.
- Find table, weights, etc for use with LBB blade bending jigs.
- Install LLB blades.
- Install LLB blade units in PI.
Hanging BF/IRM/IM/RM/BS (mostly Mark, Fabian, Perry)
- Reroute in-vacuum cables up to SF level; add in-vacuum extension cables if necessary.
- Test SF LVDT.
- Test SF fishing rod stepper.
Electronics (mostly Enzo, Mark)
- Make more anti-feedthrough adapters.
- Add retaining screws to cables at feedthroughs (mostly done, needs finishing).
- Work with Miyo-kun to get pico drivers added to BS rack and screens
- Update E1503600 with DIO card for HPCDs, etc, etc.
- Decide final length for BS OSEM cables (Enzo, Mark, Fabian)
- Send list of required in-vacuum cables to Takahashi-san
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Make spreadsheet on Google Docs or the like with in-vacuum cable inventory (Hirata)
Real-time and SUMCON models (mostly Perry, Mark)
- Get Perry (and Enzo) set up with SUMCON.
- Update SUMCON model of full BS.
- Do cut-down SUMCON model of just payload hanging from fixed BS.
- Compare measured TFs to cut-down model(s).
- Create a proper DAC Monitor MEDM screen.
- Improve ADC Monitor MEDM screen.