1994
Comment:
|
4587
|
Deletions are marked like this. | Additions are marked like this. |
Line 3: | Line 3: |
2017-03-21 | [[../ToDoOld|Archived To-Do Items]] |
Line 5: | Line 5: |
== Facilities (mostly full team) == | [[#EveryWeek |Every Week]] [[#ComingWeeks |Coming Weeks]] [[#RealBSHang|Preparation for Real BS Hang]] [[#SRPrepTasks|Preparation for SR Installation]] <<Anchor(EveryWeek)>> == Every Week == === Facilities === |
Line 9: | Line 20: |
* Get stuff from [[../WishList]] | |
Line 10: | Line 22: |
== Hanging BF/IRM/IM/RM/BS (mostly Mark, Fabian, Perry) == * Reroute in-vacuum cables up to SF level; remove 40-cm extensions if possible; add in-vacuum extension cables if necessary. |
<<Anchor(ComingWeeks)>> == Coming Weeks 2017-07-24 == === Facilities === |
Line 13: | Line 26: |
== Electronics (mostly Enzo, Mark) == * Make more anti-feedthrough adapters. * Add retaining screws to cables at feedthroughs (mostly done, needs finishing). * Run final 10-m section of cables from third and fourth feedthroughs to rack. * Wire up BF roll/pitch picos * Wire up SF LVDT. * Wire up SF fishing rod stepper. * Work with Miyo-kun to get pico drivers added to BS rack and screens * Grab remaining cables etc per E1605111 and update document * Update E1503600 with DIO card for HPCDs, etc, etc. * Decide final length for BS OSEM cables (Enzo, Mark, Fabian) * Send list of required in-vacuum cables to Takahashi-san |
=== Design/Documentation/Planning === * Organize new OL for setting BS pitch (Fabian). * Do version of 3D CAD with final-hang arrangement of suspension and LBB damper stuff (Hirata-san). * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san). * LBB ballast mass. * Research real payload. * Do improved mass budget. === Electronics === * --(Look for LVDT driver box Syyxx3134.)-- * --(Make sure SR3 boxes have notes on their JGW-S.... document pages.)-- === Main Assembly === * --(Remove BF-SF cables (note which had gender benders and which had extensions).)-- * --(Remove SF.)-- * Remove IRM. * Remove old BF. * Remove RM and dummy BS. * Check centering of IM picos. * Characterize blades (--(1)--,--(2)--,--(3)--,4,5,6). * Rebuild BF. * Check verticality of AF, height of crossbars, centering of optical table. * --(Check gluing result.)-- * --(Cleanup optic after failed secondary prism bonds.)-- * --(Cleanup jigs/prisms after failed secondary prism bonds.)-- * --(Reglue secondary prisms.)-- * Remove LBB rings. * Send rings for recleaning. <<Anchor(RealBSHang)>> == Real BS Hang Tasks == === Major Tasks === * Get pico drive screens fixed (Miyo-kun) * Final ballast mass production for BF and SF (Hirata-san). (have quotes) * Design of receptacles for rods with 8 mm heads. * Possible rebuild of BF and/or SF * Set up build/test stand for filters. * Get filter test weights. * Find spare BF blade(s). * Reclean stuff: * PI (remove Kapton tape etc, etc). * LLB damper stuff, especially Cu segments. * Calibrate PI vertical LVDT. * Set yoke on PI vertical LVDT (if necessary). * Calibrate PI horizontal LVDTs. * Unlock BF keystone and try running BF fishing rod to fix sag problem. === Minor Tasks === ==== Mechanical ==== * Get clean bag laundered. * Put pointy-tipped screw in RM trolley for BS * Swap out temporary ballast mass in BF, SF. * Return/replace borrowed parts: * Lock washers for LBB dampers * Temporary ballast mass (dog clamps) in BF. * Wide-mouth OSEMs from RM to Akutsu-san * Adjust height of crossbars below BF. * If possible, fix galled pole in BF level of EQ stop. * Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match. * Check inside SF for lost ruler. * Tighten PI yaw return spring. * Get Cu O-rings for feedthroughs. ==== Electrical ==== * Decide final in-vacuum and in-air cable routing (Enzo). * Calibrate all LVDTs (Enzo, Mark). * Remove cling wrap in BF and install vacuum-compatible heat shrink. * Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins). * Rewire PI horizontal steppers with vacuum-compatible cable. * Adjust yoke on BF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height). ==== Real-time and SUMCON models ==== * Create SUMCON models for full BS and major installation milestones. * Create controls design description (cf [[https://dcc.ligo.org/LIGO-T1100378/public|LIGO-T1100378]]). |
Line 26: | Line 101: |
* Make spreadsheet on Google Docs or the like with in-vacuum cable inventory (Hirata) == PI Prep (mostly Hirata-san, Mark) == * Inspect PI, compare to CAD and 2D drawings (Hirata, Mark) * Identify missing PI parts (Hirata, Mark) * Find and reattach repaired LVDT coil(s) (Enzo, Hirata, Mark) * Find and install fishing rod. * Remove and pack away the accelerometers. * Find table, weights, etc for use with LBB blade bending jigs. * Install LLB blades. * Install LLB modules. * Check length/gender of connectors against E1503600 (Enzo) == Real-time and SUMCON models (mostly Perry, Mark) == * Get Perry (and Enzo) set up with SUMCON. * Update SUMCON model of full BS. * Do cut-down SUMCON model of just payload hanging from fixed BS. * Compare measured TFs to cut-down model(s). |
* Understand/document/debug Kokeyama-san's DIO stuff. * Measure LPCD and HPCD output filter response. * Design and install software compensation filters for LPCD and HPCD output filters. * Design and install GAS drift compensation filters. |
Line 46: | Line 107: |
<<Anchor(SRPrepTasks)>> == SR Prep Tasks == === Design/Purchasing === * Do rough mass budget for SR2/SR3/SRM. * Design SR assembly frame. * Design final SF ballast masses (Fabian). === Electronics === * Get cables/cards for SR3: * 5 DSub-37 cables (tent) * 5 DSub-15M to DSub-9M adapter cables (tent) * 3 DIO cards (tent) * 2 DSub-9 FF gender benders (for LVDTs) * extra ADC card(s)? * extra DAC card(s)? * BNC-LEMO adapter (for LVDTs) * etc |
VIS Type B Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks 2017-07-24
Facilities
Design/Documentation/Planning
- Organize new OL for setting BS pitch (Fabian).
- Do version of 3D CAD with final-hang arrangement of suspension and LBB damper stuff (Hirata-san).
- Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
- LBB ballast mass.
- Research real payload.
- Do improved mass budget.
Electronics
Look for LVDT driver box Syyxx3134.
Make sure SR3 boxes have notes on their JGW-S.... document pages.
Main Assembly
Remove BF-SF cables (note which had gender benders and which had extensions).
Remove SF.
- Remove IRM.
- Remove old BF.
- Remove RM and dummy BS.
- Check centering of IM picos.
Characterize blades (1,2,3,4,5,6).
- Rebuild BF.
- Check verticality of AF, height of crossbars, centering of optical table.
Check gluing result.
Cleanup optic after failed secondary prism bonds.
Cleanup jigs/prisms after failed secondary prism bonds.
Reglue secondary prisms.
- Remove LBB rings.
- Send rings for recleaning.
Real BS Hang Tasks
Major Tasks
- Get pico drive screens fixed (Miyo-kun)
- Final ballast mass production for BF and SF (Hirata-san). (have quotes)
- Design of receptacles for rods with 8 mm heads.
- Possible rebuild of BF and/or SF
- Set up build/test stand for filters.
- Get filter test weights.
- Find spare BF blade(s).
- Reclean stuff:
- PI (remove Kapton tape etc, etc).
- LLB damper stuff, especially Cu segments.
- Calibrate PI vertical LVDT.
- Set yoke on PI vertical LVDT (if necessary).
- Calibrate PI horizontal LVDTs.
- Unlock BF keystone and try running BF fishing rod to fix sag problem.
Minor Tasks
Mechanical
- Get clean bag laundered.
- Put pointy-tipped screw in RM trolley for BS
- Swap out temporary ballast mass in BF, SF.
- Return/replace borrowed parts:
- Lock washers for LBB dampers
- Temporary ballast mass (dog clamps) in BF.
- Wide-mouth OSEMs from RM to Akutsu-san
- Adjust height of crossbars below BF.
- If possible, fix galled pole in BF level of EQ stop.
- Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.
- Check inside SF for lost ruler.
- Tighten PI yaw return spring.
- Get Cu O-rings for feedthroughs.
Electrical
- Decide final in-vacuum and in-air cable routing (Enzo).
- Calibrate all LVDTs (Enzo, Mark).
- Remove cling wrap in BF and install vacuum-compatible heat shrink.
- Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins).
- Rewire PI horizontal steppers with vacuum-compatible cable.
- Adjust yoke on BF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height).
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.
- Design and install GAS drift compensation filters.
- Create a proper DAC Monitor MEDM screen.
- Improve ADC Monitor MEDM screen.
SR Prep Tasks
Design/Purchasing
- Do rough mass budget for SR2/SR3/SRM.
- Design SR assembly frame.
- Design final SF ballast masses (Fabian).
Electronics
- Get cables/cards for SR3:
- 5 DSub-37 cables (tent)
- 5 DSub-15M to DSub-9M adapter cables (tent)
- 3 DIO cards (tent)
- 2 DSub-9 FF gender benders (for LVDTs)
- extra ADC card(s)?
- extra DAC card(s)?
- BNC-LEMO adapter (for LVDTs)
- etc