= VIS Type B Near Term To-Do List = | = VIS Type B BS Near Term To-Do List = |
Line 3: | Line 3: |
[[../ToDoOld|Archived To-Do Items]] | [[../ToDoOldBS|Archived BS To-Do Items]] [[../ToDoSR|SR To-Do Items]] |
Line 8: | Line 10: |
[[#RealBSHang|Preparation for Real BS Hang]] [[#SRPrepTasks|Preparation for SR Installation]] |
|
Line 23: | Line 21: |
== 2017-07-31 == === Facilities === * Re-secure floor panels around tank. * Wipe entire frame; blow dust out of grooves. * Organize new OL for setting BS pitch (Fabian). |
|
Line 29: | Line 22: |
=== Design/Documentation/Planning === * Do version of 3D CAD with final-hang arrangement of suspension and LBB damper stuff (Hirata-san). === Electronics === |
== 2017-10-02 == |
Line 34: | Line 24: |
=== Main Assembly === * Remove dummy BS from RM. * Install coil-only OSEMs. * Measure coil resistances of wide-mouth OSEMs, new coil-only OSEMS (for Michimura-san). * Look up log book to find serial numbers of old coil+sensor RM OSEMs. * 2016-09-07: H1 = #22, H2 = #23, H3 = #25, H4 = #26 * Pack RM coil+sensor OSEMs, label them with original serial numbers, and return them to Akutsu-san. * Remove IM end panel and check centering of IM picos. * Reassemble top of AF. * Check verticality of AF, height of crossbars, centering of optical table. * Move NB-03 jacks at PI level of AF to top level. * Set height, level of IM support screws. * Install IM. |
=== Main Assembly Sequence === * Tidy up and cover things to prepare for SR2 crane slot work. * Replace BS service port covers. * Check for bubble level and other tools in tank. * Remove stickers on IP and clean with ethanol (some were missed last time). * Wipe rusty screws on IP LVDTs and surrounding area with ethanol-soaked wipe. * Check that all in-air cables are labeled. * Fix broken pico adapter cable? * If possible, reroute cable to eliminate need for with feedthrough. * Debug all electronics, especially actuation. * Check IP yaw. * Recheck centering of suspension in assembly frame. * Measure IP period; adjust ballast mass. * Calibrate all LVDTs (Enzo, Mark). --(BF)--, --(SF)--, --(PI-GAS)--, PI-H1, PI-H2, PI-H3 * Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs. * Set all EQ stops to proper clearance. * Get ready for full TFs. |
Line 48: | Line 42: |
=== Time permitting === * Remove LBB rings. * Send rings for recleaning. |
=== Software === * Enter new IP matrices and do safe.snap. * Get pico drive screens fixed (Miyo-kun) * Update real-time model to number channels from #0. * Remove old OL stuff; add link to new OL stuff. * Remove unused screens. * Sort out SVN. |
Line 53: | Line 51: |
== Real BS Hang Tasks == | == Tasks Not To Forget == |
Line 55: | Line 53: |
* Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD. | |
Line 56: | Line 55: |
* LBB ballast mass. * Research real payload. * Do improved mass budget. * Get pico drive screens fixed (Miyo-kun) * Final ballast mass production for BF and SF (Hirata-san). (have quotes) * Design of receptacles for rods with 8 mm heads. * Possible rebuild of BF and/or SF * Set up build/test stand for filters. * Get filter test weights. * Find spare BF blade(s). * Reclean stuff: * PI (remove Kapton tape etc, etc). * LLB damper stuff, especially Cu segments. * Calibrate PI vertical LVDT. * Set yoke on PI vertical LVDT (if necessary). * Calibrate PI horizontal LVDTs. * Unlock BF keystone and try running BF fishing rod to fix sag problem. |
* Figure out how to make PI yaw adjustment reliable. |
Line 78: | Line 61: |
* Swap out temporary ballast mass in BF, SF. | |
Line 82: | Line 64: |
* Wide-mouth OSEMs from RM to Akutsu-san * Adjust height of crossbars below BF. * If possible, fix galled pole in BF level of EQ stop. |
|
Line 86: | Line 65: |
* Check inside SF for lost ruler. * Tighten PI yaw return spring. * Get Cu O-rings for feedthroughs. |
|
Line 91: | Line 67: |
* Decide final in-vacuum and in-air cable routing (Enzo). * Calibrate all LVDTs (Enzo, Mark). * Remove cling wrap in BF and install vacuum-compatible heat shrink. * Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins). * Rewire PI horizontal steppers with vacuum-compatible cable. * Adjust yoke on BF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height). |
|
Line 106: | Line 76: |
* Create a proper DAC Monitor MEDM screen. * Improve ADC Monitor MEDM screen. <<Anchor(SRPrepTasks)>> == SR Prep Tasks == === Design/Purchasing === * Do rough mass budget for SR2/SR3/SRM. * Design SR assembly frame. * Design final SF ballast masses (Fabian). === Electronics === * Get cables/cards for SR3: * 5 DSub-37 cables (tent) * 5 DSub-15M to DSub-9M adapter cables (tent) * 3 DIO cards (tent) * 2 DSub-9 FF gender benders (for LVDTs) * extra ADC card(s)? * extra DAC card(s)? * BNC-LEMO adapter (for LVDTs) * etc |
VIS Type B BS Near Term To-Do List
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2017-10-02
Main Assembly Sequence
- Tidy up and cover things to prepare for SR2 crane slot work.
- Replace BS service port covers.
- Check for bubble level and other tools in tank.
- Remove stickers on IP and clean with ethanol (some were missed last time).
- Wipe rusty screws on IP LVDTs and surrounding area with ethanol-soaked wipe.
- Check that all in-air cables are labeled.
- Fix broken pico adapter cable?
- If possible, reroute cable to eliminate need for with feedthrough.
- Debug all electronics, especially actuation.
- Check IP yaw.
- Recheck centering of suspension in assembly frame.
- Measure IP period; adjust ballast mass.
Calibrate all LVDTs (Enzo, Mark). BF, SF, PI-GAS, PI-H1, PI-H2, PI-H3
- Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
- Set all EQ stops to proper clearance.
- Get ready for full TFs.
Software
- Enter new IP matrices and do safe.snap.
- Get pico drive screens fixed (Miyo-kun)
- Update real-time model to number channels from #0.
- Remove old OL stuff; add link to new OL stuff.
- Remove unused screens.
- Sort out SVN.
Tasks Not To Forget
Major Tasks
- Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
- Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
- Figure out how to make PI yaw adjustment reliable.
Minor Tasks
Mechanical
- Get clean bag laundered.
- Put pointy-tipped screw in RM trolley for BS
- Return/replace borrowed parts:
- Lock washers for LBB dampers
- Temporary ballast mass (dog clamps) in BF.
- Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.
Electrical
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.
- Design and install GAS drift compensation filters.