== 2017-08-16 == === Facilities === * --(Move cardboard box with old BF to storage.)-- * --(Tidy up Hirata-san's stuff in genkan of cleanbooth.)-- |
|
Line 28: | Line 22: |
=== Design/Documentation/Planning === * LBB ballast mass. * Research real payload. * Do improved mass budget. * Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD. |
== 2017-09-25 == |
Line 34: | Line 24: |
=== Electronics === * --(Return spare two Type5-2.2 cables to Sato-san's store.)-- * Recable/test BF LVDT. * --(Rip out remaining old in-air cabling.)-- * Lay new in-air cabling. * Reinstall LVDT chassis. |
=== Main Assembly Sequence === * Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings). * Fix #1 geophone adapter cable. * Fix broken pico adapter cable? * Debug all electronics, starting with IRM OSEMs. * Unlock IP; use jacks and FRs to center. * Check IP yaw. * Recheck centering of suspension in assembly frame. * Measure IP period; adjust ballast mass. * Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs. * LBB stuff (see below). * |
Line 41: | Line 37: |
=== Main Assembly === * Do final trim of IM/RM/TM. * Remove LBB blade assemblies from PI. * Remove LBB blades from holders. * Remove LBB rings. * Send rings for recleaning. |
=== LBB Sequence * Unclamp LBB ring sandwich; fully suspend Cu ring. * Unscrew LBB from tank brackets. * Hook LBB. * Remove TBD amount of spacers from between LBB and tank brackets. * Set LBB blade stops to nominal height. * Extend foot screws on LBB to just barely support LBB. * Adjust height of LBB magnet ring to set proper gap (4 mm??). * Retract LBB foot screws. * Add temporary ballast to LBB until LBB blades just barely sink below stops. * Check distance from LBB to main beam height (or other suitable reference); adjust by screwing receptacles. * Set foot screws to give ≈5 mm (or TBD) movement range of LBB below nominal. * Set stop on LBB blades to give ≈3 mm (or TBD, less than Cu-magnet gap) of LBB above nominal. |
Line 48: | Line 51: |
=== Time permitting === | === In parallel, time permitting === |
Line 51: | Line 54: |
== Real BS Hang Tasks == | == Tasks Not To Forget == |
Line 53: | Line 56: |
* Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD. | |
Line 55: | Line 59: |
* Final ballast mass production for BF and SF (Hirata-san). (have quotes) * Design of receptacles for rods with 8 mm heads. * Possible rebuild of BF and/or SF * Set up build/test stand for filters. * Get filter test weights. * Find spare BF blade(s). * Reclean stuff: * PI (remove Kapton tape etc, etc). * LLB damper stuff, especially Cu segments. * Calibrate PI vertical LVDT. * Set yoke on PI vertical LVDT (if necessary). * Calibrate PI horizontal LVDTs. |
* Figure out how to make PI yaw adjustment reliable. |
Line 72: | Line 65: |
* --(Swap out temporary ballast mass in BF)--, SF. | |
Line 76: | Line 68: |
* Wide-mouth OSEMs from RM to Akutsu-san * --(Adjust height of crossbars below BF.)-- * --(If possible, fix galled pole in BF level of EQ stop.)-- |
|
Line 80: | Line 69: |
* --(Check inside SF for lost ruler.)-- * Tighten PI yaw return spring. * Get Cu O-rings for feedthroughs. |
|
Line 86: | Line 72: |
* Calibrate all LVDTs (Enzo, Mark). * Remove cling wrap in BF and install vacuum-compatible heat shrink. * Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins). * Rewire PI horizontal steppers with vacuum-compatible cable. * Adjust yoke on BF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height). |
* Calibrate all LVDTs (Enzo, Mark). --(BF)--, --(SF)--, --(PI-GAS)--, PI-H1, PI-H2, PI-H3 * Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height). |
Line 100: | Line 83: |
* Create a proper DAC Monitor MEDM screen. * Improve ADC Monitor MEDM screen. <<Anchor(SRPrepTasks)>> == SR Prep Tasks == === Design/Purchasing === * Do rough mass budget for SR2/SR3/SRM. * Design SR assembly frame. * Design final SF ballast masses (Fabian). === Electronics === * Get cables/cards for SR3: * 5 DSub-37 cables (tent) * 5 DSub-15M to DSub-9M adapter cables (tent) * 3 DIO cards (tent) * 2 DSub-9 FF gender benders (for LVDTs) * extra ADC card(s)? * extra DAC card(s)? * BNC-LEMO adapter (for LVDTs) * etc |
VIS Type B BS Near Term To-Do List
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2017-09-25
Main Assembly Sequence
- Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
- Fix #1 geophone adapter cable.
- Fix broken pico adapter cable?
- Debug all electronics, starting with IRM OSEMs.
- Unlock IP; use jacks and FRs to center.
- Check IP yaw.
- Recheck centering of suspension in assembly frame.
- Measure IP period; adjust ballast mass.
- Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
- LBB stuff (see below).
=== LBB Sequence
- Unclamp LBB ring sandwich; fully suspend Cu ring.
- Unscrew LBB from tank brackets.
- Hook LBB.
- Remove TBD amount of spacers from between LBB and tank brackets.
- Set LBB blade stops to nominal height.
- Extend foot screws on LBB to just barely support LBB.
- Adjust height of LBB magnet ring to set proper gap (4 mm??).
- Retract LBB foot screws.
- Add temporary ballast to LBB until LBB blades just barely sink below stops.
- Check distance from LBB to main beam height (or other suitable reference); adjust by screwing receptacles.
- Set foot screws to give ≈5 mm (or TBD) movement range of LBB below nominal.
- Set stop on LBB blades to give ≈3 mm (or TBD, less than Cu-magnet gap) of LBB above nominal.
In parallel, time permitting
Tasks Not To Forget
Major Tasks
- Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
- Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
- Get pico drive screens fixed (Miyo-kun)
- Figure out how to make PI yaw adjustment reliable.
Minor Tasks
Mechanical
- Get clean bag laundered.
- Put pointy-tipped screw in RM trolley for BS
- Return/replace borrowed parts:
- Lock washers for LBB dampers
- Temporary ballast mass (dog clamps) in BF.
- Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.
Electrical
- Decide final in-vacuum and in-air cable routing (Enzo).
Calibrate all LVDTs (Enzo, Mark). BF, SF, PI-GAS, PI-H1, PI-H2, PI-H3
- Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height).
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.
- Design and install GAS drift compensation filters.