Line 1: | Line 1: |
= VIS Type B Near Term To-Do List = | = VIS Type B BS Near Term To-Do List = |
Line 3: | Line 3: |
[[../ToDoOld|Archived To-Do Items]] | [[../ToDoOldBS|Archived BS To-Do Items]] [[../ToDoSR|SR To-Do Items]] |
Line 8: | Line 10: |
[[#RealBSHang|Preparation for Real BS Hang]] [[#SRPrepTasks|Preparation for SR Installation]] |
|
Line 23: | Line 21: |
== 2017-08-21 == * Wrap new IM bottom ballast masses (Mozumi). * Install new IM masses. * Set up optical level. * Adjust IM ballast mass to give desired roll/pitch/vertical. * Level BF. * Cable BF LVDT, test and calibrate. * Adjust top of IRM to level. * Install IRM side panels. * Install IRM OSEMs. * Cable IRM OSEMs and test. * Adjust IRM and IRM OSEMs to get good alignment of IRM OSEMs and IM-IRM stops. * Add extra ballast mass to BF. * Add BF cap but don't anchor cables. * Cable and test BF cap picos. * Lift BF/IRM/IM/RM/BS and weigh. * Adjust BF ballast if necessary. * Crane in SF. * Hook up BF/IRM/IM/RM/BS. * Route cables up to SF. * Adjust BF ballast if necessary. |
|
Line 45: | Line 22: |
== 2017-08-16 (file me) == === Facilities === * --(Move cardboard box with old BF to storage.)-- * --(Tidy up Hirata-san's stuff in genkan of cleanbooth.)-- |
== 2017-09-19 == (No work Monday 9/18) === Main Assembly Sequence === * --(Debug BF LVDT actuation)--. |
Line 50: | Line 27: |
=== Design/Documentation/Planning === * LBB ballast mass. * Research real payload. * Do improved mass budget. * Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD. |
---- /!\ '''Edit conflict - other version:''' ---- * --(Check F0 yoke height (top of coil former should be 37.5 mm above bottom of recess in top of baseplate))-- 36mm. * Test all PI items: * Yaw stepper (tested, not clearly working). * --(F0 LVDT sensing)-- * --(F0 LVDT actuation)-- * Calibrate F0 LVDT. * Horizontal LVDT sensing * Horizontal LVDT actuation * --(Geophones (issues with driver, cables, descramblers))-- * --(Lock the F0 and SF keystones and measure the resonance frequency of the BF GAS)-- 2 Measurements: f1=0.443 Hz, f2=0.454 Hz. * --(Lock the SF and BF keystones and measure the resonance frequency of the F0 GAS)-- 2 Measurements: f1=0.208 Hz, f2=0.210 Hz. * --(Double check BS pitch with OL.)-- * --(Adjust SF damper ring to correct gap.)-- * --(Install lock nuts on F0 GAS FR at TBD positions.)-- * Lock BF and F0 keystones (but ''not'' SF keystone). * Lock RM to BS and IRM to IM. * Lock RM, IRM and BF (but not SF) to security structure. * Lock IP. * Remove F0 keystone top plate (including yaw stepper) and immobilize SF/... in yaw. * Attach lifting fixture. |
Line 56: | Line 49: |
=== Electronics === * --(Return spare two Type5-2.2 cables to Sato-san's store.)-- * Recable/test BF LVDT. * --(Rip out remaining old in-air cabling.)-- * Lay new in-air cabling. * Reinstall LVDT chassis. |
|
Line 63: | Line 50: |
=== Main Assembly === * Do final trim of IM/RM/TM. * Remove LBB blade assemblies from PI. * Remove LBB blades from holders. * Remove LBB rings. * Send rings for recleaning. |
* Remove BF- and SF-level crossbars. * Remove geophones for craning. * Disconnect in-vacuum cables from feedthrough and coil neatly for craning. * --(Attach lifting plates.)-- === Tank Preparation Sequence === * Attach Cu segments to LBB damper ring. * Pass halves of LBB magnet ring into tank, join, and make sandwich for craning. * Crane tank lid off. * Crane LBB damper rings to top of tank and suspend. * Crane suspension out of assembly frame. * Attach LBB upper rods to LBB blade tips and rotate suspension 45° clockwise. * Crane suspension into tank and connect upper rods to LBB Cu ring. * Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods. * Install LBB lower rods and hook LBB. * Measure required ballast for LBB. * Unlock suspension and readjust. * Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings). |
Line 70: | Line 68: |
=== Time permitting === | === In parallel, time permitting === * --(Fix issue with geophone distributor.)-- * Fix #1 geophone adapter cable (and replace borrowed one). * Fix broken pico adapter cable. * Figure out how to tighten PI yaw return spring or otherwise make yaw adjustment reliable. |
Line 73: | Line 75: |
== Real BS Hang Tasks == | == Tasks Not To Forget == |
Line 75: | Line 77: |
* Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD. | |
Line 77: | Line 80: |
* Final ballast mass production for BF and SF (Hirata-san). (have quotes) * Design of receptacles for rods with 8 mm heads. * Possible rebuild of BF and/or SF * Set up build/test stand for filters. * Get filter test weights. * Find spare BF blade(s). * Reclean stuff: * PI (remove Kapton tape etc, etc). * LLB damper stuff, especially Cu segments. * Calibrate PI vertical LVDT. * Set yoke on PI vertical LVDT (if necessary). * Calibrate PI horizontal LVDTs. |
|
Line 94: | Line 85: |
* --(Swap out temporary ballast mass in BF)--, SF. | |
Line 98: | Line 88: |
* Wide-mouth OSEMs from RM to Akutsu-san * --(Adjust height of crossbars below BF.)-- * --(If possible, fix galled pole in BF level of EQ stop.)-- |
|
Line 102: | Line 89: |
* --(Check inside SF for lost ruler.)-- * Tighten PI yaw return spring. * Get Cu O-rings for feedthroughs. |
|
Line 108: | Line 92: |
* Calibrate all LVDTs (Enzo, Mark). * Remove cling wrap in BF and install vacuum-compatible heat shrink. * Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins). * Rewire PI horizontal steppers with vacuum-compatible cable. * Adjust yoke on BF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height). |
* Calibrate all LVDTs (Enzo, Mark). --(BF)--, --(SF)--, --(PI-GAS)--, PI-H1, PI-H2, PI-H3 * Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height). |
Line 122: | Line 103: |
* Create a proper DAC Monitor MEDM screen. * Improve ADC Monitor MEDM screen. <<Anchor(SRPrepTasks)>> == SR Prep Tasks == === Design/Purchasing === * Do rough mass budget for SR2/SR3/SRM. * Design SR assembly frame. * Design final SF ballast masses (Fabian). ==== Order now ==== * Bread boards for SR -> すぐ見積り依頼 * Include installation work in the contract * Total budget = 5MJPY * PEEK collet for "Small hexagon"(cable clamp) -> すぐ見積り依頼 ==== Need simple design changes ==== * SUS wires(3 types) for the LBB * Change the length -> すぐ見積り依頼 * Receptacles for Bread board damper * There is a mistake in the PROMEC drawing. * Hirata-san will make a new 2D drawing * IM wire clamps for SR * Need to change the height * SR assembly frame -> 月曜日に見積り依頼 * Mark is checking the design from Fabian * We should order the parts necessary to modify the BS assembly frame to the SR2 assembly frame ==== Need Fabian's input ==== * Cable clamps for BF,SF and PI -> 方式を決める * Design change for the PI clamps, because the SR PIs are NIKHEF ones. * Ballast masses for BF and SF * 製作に2週間程度 * 10月頭にTop Filterの最適荷重を実測。それに合わせて発注。それまでにデザインは用意しておく。 * 測定に必要な物品の準備 -> 月曜日に高橋さんと相談 ==== Need more discussion/checks ==== * Blade spring assembly for LBB * Check the load of the LBB and decide the design load of the springs * Correct the length * Scale the width of the current blades to design the new blades -> 高橋さんと相談 * SR用LBBの重さを確認 * Bread board damper rings * Need to check whether we can put a full ring into the chamber from the side flanges or not. -> 至急確認 === Electronics === * Get cables/cards for SR3: * 5 DSub-37 cables (tent) * 5 DSub-15M to DSub-9M adapter cables (tent) * 3 DIO cards (tent) * 2 DSub-9 FF gender benders (for LVDTs) * extra ADC card(s)? * extra DAC card(s)? * BNC-LEMO adapter (for LVDTs) * etc |
VIS Type B BS Near Term To-Do List
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2017-09-19
(No work Monday 9/18)
Main Assembly Sequence
Debug BF LVDT actuation.
Edit conflict - other version:
Check F0 yoke height (top of coil former should be 37.5 mm above bottom of recess in top of baseplate) 36mm.
- Test all PI items:
- Yaw stepper (tested, not clearly working).
F0 LVDT sensing
F0 LVDT actuation
- Calibrate F0 LVDT.
- Horizontal LVDT sensing
- Horizontal LVDT actuation
Geophones (issues with driver, cables, descramblers)
Lock the F0 and SF keystones and measure the resonance frequency of the BF GAS 2 Measurements: f1=0.443 Hz, f2=0.454 Hz.
Lock the SF and BF keystones and measure the resonance frequency of the F0 GAS 2 Measurements: f1=0.208 Hz, f2=0.210 Hz.
Double check BS pitch with OL.
Adjust SF damper ring to correct gap.
Install lock nuts on F0 GAS FR at TBD positions.
Lock BF and F0 keystones (but not SF keystone).
- Lock RM to BS and IRM to IM.
- Lock RM, IRM and BF (but not SF) to security structure.
- Lock IP.
- Remove F0 keystone top plate (including yaw stepper) and immobilize SF/... in yaw.
- Attach lifting fixture.
- Remove BF- and SF-level crossbars.
- Remove geophones for craning.
- Disconnect in-vacuum cables from feedthrough and coil neatly for craning.
Attach lifting plates.
Tank Preparation Sequence
- Attach Cu segments to LBB damper ring.
- Pass halves of LBB magnet ring into tank, join, and make sandwich for craning.
- Crane tank lid off.
- Crane LBB damper rings to top of tank and suspend.
- Crane suspension out of assembly frame.
- Attach LBB upper rods to LBB blade tips and rotate suspension 45° clockwise.
- Crane suspension into tank and connect upper rods to LBB Cu ring.
- Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods.
- Install LBB lower rods and hook LBB.
- Measure required ballast for LBB.
- Unlock suspension and readjust.
- Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
In parallel, time permitting
Fix issue with geophone distributor.
- Fix #1 geophone adapter cable (and replace borrowed one).
- Fix broken pico adapter cable.
- Figure out how to tighten PI yaw return spring or otherwise make yaw adjustment reliable.
Tasks Not To Forget
Major Tasks
- Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
- Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
- Get pico drive screens fixed (Miyo-kun)
Minor Tasks
Mechanical
- Get clean bag laundered.
- Put pointy-tipped screw in RM trolley for BS
- Return/replace borrowed parts:
- Lock washers for LBB dampers
- Temporary ballast mass (dog clamps) in BF.
- Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.
Electrical
- Decide final in-vacuum and in-air cable routing (Enzo).
Calibrate all LVDTs (Enzo, Mark). BF, SF, PI-GAS, PI-H1, PI-H2, PI-H3
- Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height).
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.
- Design and install GAS drift compensation filters.