## page was renamed from KAGRA/Subgroups/VIS/TypeB/ToDo = VIS Type B Near Term To-Do List = |
= VIS Type B BS Near Term To-Do List = |
Line 4: | Line 3: |
[[../ToDoOld|Archived To-Do Items]] | [[../ToDoOldBS|Archived BS To-Do Items]] [[../ToDoSR|SR To-Do Items]] |
Line 9: | Line 10: |
[[#RealBSHang|Preparation for Real BS Hang]] [[#SRPrepTasks|Preparation for SR Installation]] |
|
Line 24: | Line 21: |
== 2017-08-21 == === Design/Documentation/Planning === * Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD. |
== 2017-09-11 == |
Line 28: | Line 23: |
=== Main Assembly === * --(Wrap new IM bottom ballast masses (Mozumi).)-- * --(Install new IM masses.)-- * --(Set up optical level.)-- * --(Adjust IM ballast mass to give desired roll/pitch/vertical.)-- * --(Level BF.)-- * --(Cable BF LVDT, test and calibrate.)-- * --(Adjust top of IRM to level.)-- * --(Install IRM side panels.)-- * --(Install IRM OSEMs.)-- * --(Cable IRM OSEMs)-- and test. * --(Adjust IRM and IRM OSEMs to get good alignment of IRM OSEMs and IM-IRM stops.)-- * Add extra ballast mass to BF. * Add BF cap but don't anchor cables. * Cable and test BF cap picos. * Lift BF/IRM/IM/RM/BS and weigh. * Adjust BF ballast if necessary. * Crane in SF. * Hook up BF/IRM/IM/RM/BS. * Route cables up to SF. * Adjust BF ballast if necessary. |
=== Main Assembly Sequence === * Debug BF LVDT actuation. * --(Debug other actuation.)-- * --(Remove F0-SF rod and reinstall with hex cable clamp.)-- * --(Route cables up past hex cable clamps.)-- * --(Adjust SF trim mass for pitch/roll/vertical.)-- * --(Route all SF/... cables through to the flange and test.)-- * --(Cable all PI items through to the flange.)-- * --(Disconnect the SS from the AF.)-- * --(Recheck/adjust SF/... yaw.)-- * --(Roughly level the PI so as to make the SS vertical.)-- * --(Unlock the IP and adjust the level of the PI and the horizontal FRs to center the IP.)-- * Check F0 yoke height (top of coil former should be 6 mm above top of baseplate). * Test all PI items: * Yaw stepper. * F0 LVDT sensing * F0 LVDT actuation * --(Horizontal steppers)-- * Horizontal LVDT sensing * Horizontal LVDT actuation * --(Geophones)-- (except one cable broken: #1) * Lock the F0 and SF keystones and measure the resonance frequency of the BF GAS. * --(Lock the F0 and BF keystones and measure the resonance frequency of the SF GAS.)-- 425 mHz * Lock the SF and BF keystones and measure the resonance frequency of the F0 GAS. |
Line 50: | Line 48: |
=== Time permitting === * Lay more new in-air cabling. |
=== In parallel, time permitting === * --(Fix links to ADC_MONITOR screens.)-- * --(Check that all Take/Restore Safe.snap buttons work.)-- * --(Check that we still have all LBB parts (there was an issue with borrowed lock nuts).)-- * --(Wipe LLB damper parts with ethanol.)-- * Figure out how to tighten PI yaw return spring. * --(Install LBB Cu damper ring in tank (less Cu for now).)-- * Fix #1 geophone adapter cable. * Fix broken pico adapter cable == 2017-09-11 == === Main Assembly Sequence === == Dates == * BUMAX countersunk screws for LBB Cu (by 9/20) * SDC screws for LBB half rings: 9/15 (Fri) (have Ag-coated as backup) * LBB Cu segments: 9/19-20 |
Line 54: | Line 68: |
== Real BS Hang Tasks == | == Tasks Not To Forget == |
Line 56: | Line 70: |
* Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD. | |
Line 58: | Line 73: |
* --(Final ballast mass production for BF and SF (Hirata-san). )-- * --(Design of receptacles for rods with 8 mm heads.)-- * --(Possible rebuild of BF)-- * --(Set up build/test stand for filters.)-- * --(Get filter test weights.)-- * --(Find spare BF blade(s).)-- * Reclean stuff: * PI (remove Kapton tape etc, etc). * LLB damper stuff, especially Cu segments. * Calibrate SF LVDT. * Calibrate PI vertical LVDT. * Set yoke on PI vertical LVDT (if necessary). * Calibrate PI horizontal LVDTs. |
|
Line 76: | Line 78: |
* --(Swap out temporary ballast mass in BF)--, SF. | |
Line 80: | Line 81: |
* --(Wide-mouth OSEMs from RM to Akutsu-san)-- * --(Adjust height of crossbars below BF.)-- * --(If possible, fix galled pole in BF level of EQ stop.)-- |
|
Line 84: | Line 82: |
* --(Check inside SF for lost ruler.)-- * Tighten PI yaw return spring. * Get Cu O-rings for feedthroughs. |
|
Line 90: | Line 85: |
* Calibrate all LVDTs (Enzo, Mark). --(BF)--, SF, PI-GAS, PI-H1, PI-H2, PI-H3 * --(Remove cling wrap in BF and install vacuum-compatible heat shrink.)-- * Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins). * Rewire PI horizontal steppers with vacuum-compatible cable. * Adjust yoke on BF to put top of secondary at 3.5 mm above top of baseplate (or to give ≈0 counts at nominal height). * Adjust yoke on SF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height). |
* Calibrate all LVDTs (Enzo, Mark). --(BF)--, --(SF)--, PI-GAS, PI-H1, PI-H2, PI-H3 |
Line 106: | Line 96: |
* Create a proper DAC Monitor MEDM screen. * Improve ADC Monitor MEDM screen. <<Anchor(SRPrepTasks)>> == SR Prep Tasks == === Design/Purchasing === * Do rough mass budget for SR2/SR3/SRM. * Design SR assembly frame. * Design final SF ballast masses (Fabian). ==== Order now ==== * Bread boards for SR -> すぐ見積り依頼 * Include installation work in the contract * Total budget = 5MJPY * PEEK collet for "Small hexagon"(cable clamp) -> すぐ見積り依頼 ==== Need simple design changes ==== * SUS wires(3 types) for the LBB * Change the length -> すぐ見積り依頼 * Receptacles for Bread board damper * There is a mistake in the PROMEC drawing. * Hirata-san will make a new 2D drawing * IM wire clamps for SR * Need to change the height * SR assembly frame -> 月曜日に見積り依頼 * Mark is checking the design from Fabian * We should order the parts necessary to modify the BS assembly frame to the SR2 assembly frame ==== Need Fabian's input ==== * Cable clamps for BF,SF and PI -> 方式を決める * Design change for the PI clamps, because the SR PIs are NIKHEF ones. * Ballast masses for BF and SF * 製作に2週間程度 * 10月頭にTop Filterの最適荷重を実測。それに合わせて発注。それまでにデザインは用意しておく。 * 測定に必要な物品の準備 -> 月曜日に高橋さんと相談 ==== Need more discussion/checks ==== * Blade spring assembly for LBB * Check the load of the LBB and decide the design load of the springs * Correct the length * Scale the width of the current blades to design the new blades -> 高橋さんと相談 * SR用LBBの重さを確認 * Bread board damper rings * Need to check whether we can put a full ring into the chamber from the side flanges or not. -> 至急確認 === Electronics === * Get cables/cards for SR3: * 5 DSub-37 cables (tent) * 5 DSub-15M to DSub-9M adapter cables (tent) * 3 DIO cards (tent) * 2 DSub-9 FF gender benders (for LVDTs) * extra ADC card(s)? * extra DAC card(s)? * BNC-LEMO adapter (for LVDTs) * etc |
VIS Type B BS Near Term To-Do List
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2017-09-11
Main Assembly Sequence
- Debug BF LVDT actuation.
Debug other actuation.
Remove F0-SF rod and reinstall with hex cable clamp.
Route cables up past hex cable clamps.
Adjust SF trim mass for pitch/roll/vertical.
Route all SF/... cables through to the flange and test.
Cable all PI items through to the flange.
Disconnect the SS from the AF.
Recheck/adjust SF/... yaw.
Roughly level the PI so as to make the SS vertical.
Unlock the IP and adjust the level of the PI and the horizontal FRs to center the IP.
- Check F0 yoke height (top of coil former should be 6 mm above top of baseplate).
- Test all PI items:
- Yaw stepper.
- F0 LVDT sensing
- F0 LVDT actuation
Horizontal steppers
- Horizontal LVDT sensing
- Horizontal LVDT actuation
Geophones (except one cable broken: #1)
- Lock the F0 and SF keystones and measure the resonance frequency of the BF GAS.
Lock the F0 and BF keystones and measure the resonance frequency of the SF GAS. 425 mHz
- Lock the SF and BF keystones and measure the resonance frequency of the F0 GAS.
In parallel, time permitting
Fix links to ADC_MONITOR screens.
Check that all Take/Restore Safe.snap buttons work.
Check that we still have all LBB parts (there was an issue with borrowed lock nuts).
Wipe LLB damper parts with ethanol.
- Figure out how to tighten PI yaw return spring.
Install LBB Cu damper ring in tank (less Cu for now).
- Fix #1 geophone adapter cable.
- Fix broken pico adapter cable
2017-09-11
Main Assembly Sequence
Dates
- BUMAX countersunk screws for LBB Cu (by 9/20)
- SDC screws for LBB half rings: 9/15 (Fri) (have Ag-coated as backup)
- LBB Cu segments: 9/19-20
Tasks Not To Forget
Major Tasks
- Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
- Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
- Get pico drive screens fixed (Miyo-kun)
Minor Tasks
Mechanical
- Get clean bag laundered.
- Put pointy-tipped screw in RM trolley for BS
- Return/replace borrowed parts:
- Lock washers for LBB dampers
- Temporary ballast mass (dog clamps) in BF.
- Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.
Electrical
- Decide final in-vacuum and in-air cable routing (Enzo).
Calibrate all LVDTs (Enzo, Mark). BF, SF, PI-GAS, PI-H1, PI-H2, PI-H3
- Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height).
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.
- Design and install GAS drift compensation filters.