6373
Comment:
|
4042
|
Deletions are marked like this. | Additions are marked like this. |
Line 3: | Line 3: |
[[../ToDoOldBS|Archived To-Do Items]] | [[../ToDoOldBS|Archived BS To-Do Items]] [[../ToDoSR|SR To-Do Items]] |
Line 8: | Line 10: |
[[#RealBSHang|Preparation for Real BS Hang]] [[#SRPrepTasks|Preparation for SR Installation]] |
|
Line 23: | Line 21: |
== 2017-08-21 == === Design/Documentation/Planning === * Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD. |
|
Line 27: | Line 22: |
=== Main Assembly === * --(Wrap new IM bottom ballast masses (Mozumi).)-- * --(Install new IM masses.)-- * --(Set up optical level.)-- * --(Adjust IM ballast mass to give desired roll/pitch/vertical.)-- * --(Level BF.)-- * --(Cable BF LVDT, test and calibrate.)-- * --(Adjust top of IRM to level.)-- * --(Install IRM side panels.)-- * --(Install IRM OSEMs.)-- * --(Cable IRM OSEMs)-- and test. * --(Adjust IRM and IRM OSEMs to get good alignment of IRM OSEMs and IM-IRM stops.)-- * Add extra ballast mass to BF. * Add BF cap but don't anchor cables. * Cable and test BF cap picos. * Lift BF/IRM/IM/RM/BS and weigh. * Adjust BF ballast if necessary. * Crane in SF. * Hook up BF/IRM/IM/RM/BS. * Route cables up to SF. * Adjust BF ballast if necessary. |
== 2017-09-19 == (No work Monday 9/18) === Main Assembly Sequence === * Debug BF LVDT actuation. * Check F0 yoke height (top of coil former should be 37.5 mm above bottom of recess in top of baseplate). * Test all PI items: * Yaw stepper (tested, not clearly working). * F0 LVDT sensing * F0 LVDT actuation * Horizontal LVDT sensing * Horizontal LVDT actuation * Geophones (issues with driver, cables, descramblers) * Lock the F0 and SF keystones and measure the resonance frequency of the BF GAS. * Lock the SF and BF keystones and measure the resonance frequency of the F0 GAS. * Double check BS pitch with OL. * Adjust SF damper ring to correct gap. * Install lock nuts on F0 GAS FR at TBD positions. * Lock BF and F0 keystones (but ''not'' SF keystone). * Lock RM to BS and IRM to IM. * Lock RM, IRM and BF (but not SF) to security structure. * Lock IP. * Remove F0 keystone top plate (including yaw stepper) and immobilize SF/... in yaw. * Attach lifting fixture. * Remove BF- and SF-level crossbars. * Remove geophones for craning. * Disconnect in-vacuum cables from feedthrough and coil neatly for craning. * Attach lifting plates. === Tank Preparation Sequence === * Attach Cu segments to LBB damper ring. * Pass halves of LBB magnet ring into tank, join, and make sandwich for craning. * Crane tank lid off. * Crane LBB damper rings to top of tank and suspend. * Crane suspension out of assembly frame. * Attach LBB upper rods to LBB blade tips and rotate suspension 45° clockwise. * Crane suspension into tank and connect upper rods to LBB Cu ring. * Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods. * Install LBB lower rods and hook LBB. * Measure required ballast for LBB. * Unlock suspension and readjust. * Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings). |
Line 49: | Line 63: |
=== Time permitting === * Lay more new in-air cabling. |
=== In parallel, time permitting === * Fix issue with geophone distributor. * Fix #1 geophone adapter cable (and replace borrowed one). * Fix broken pico adapter cable. * Figure out how to tighten PI yaw return spring or otherwise make yaw adjustment reliable. |
Line 53: | Line 70: |
== Real BS Hang Tasks == | == Tasks Not To Forget == |
Line 55: | Line 72: |
* Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD. | |
Line 57: | Line 75: |
* --(Final ballast mass production for BF and SF (Hirata-san). )-- * --(Design of receptacles for rods with 8 mm heads.)-- * --(Possible rebuild of BF)-- * --(Set up build/test stand for filters.)-- * --(Get filter test weights.)-- * --(Find spare BF blade(s).)-- * Reclean stuff: * PI (remove Kapton tape etc, etc). * LLB damper stuff, especially Cu segments. * Calibrate SF LVDT. * Calibrate PI vertical LVDT. * Set yoke on PI vertical LVDT (if necessary). * Calibrate PI horizontal LVDTs. |
|
Line 75: | Line 80: |
* --(Swap out temporary ballast mass in BF)--, SF. | |
Line 79: | Line 83: |
* --(Wide-mouth OSEMs from RM to Akutsu-san)-- * --(Adjust height of crossbars below BF.)-- * --(If possible, fix galled pole in BF level of EQ stop.)-- |
|
Line 83: | Line 84: |
* --(Check inside SF for lost ruler.)-- * Tighten PI yaw return spring. * Get Cu O-rings for feedthroughs. |
|
Line 89: | Line 87: |
* Calibrate all LVDTs (Enzo, Mark). --(BF)--, SF, PI-GAS, PI-H1, PI-H2, PI-H3 * --(Remove cling wrap in BF and install vacuum-compatible heat shrink.)-- * Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins). * Rewire PI horizontal steppers with vacuum-compatible cable. * Adjust yoke on BF to put top of secondary at 3.5 mm above top of baseplate (or to give ≈0 counts at nominal height). * Adjust yoke on SF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height). |
* Calibrate all LVDTs (Enzo, Mark). --(BF)--, --(SF)--, PI-GAS, PI-H1, PI-H2, PI-H3 |
Line 105: | Line 98: |
* Create a proper DAC Monitor MEDM screen. * Improve ADC Monitor MEDM screen. <<Anchor(SRPrepTasks)>> == SR Prep Tasks == === Design/Purchasing === * Do rough mass budget for SR2/SR3/SRM. * Design SR assembly frame. * Design final SF ballast masses (Fabian). ==== Order now ==== * Bread boards for SR -> すぐ見積り依頼 * Include installation work in the contract * Total budget = 5MJPY * PEEK collet for "Small hexagon"(cable clamp) -> すぐ見積り依頼 ==== Need simple design changes ==== * SUS wires(3 types) for the LBB * Change the length -> すぐ見積り依頼 * Receptacles for Bread board damper * There is a mistake in the PROMEC drawing. * Hirata-san will make a new 2D drawing * IM wire clamps for SR * Need to change the height * SR assembly frame -> 月曜日に見積り依頼 * Mark is checking the design from Fabian * We should order the parts necessary to modify the BS assembly frame to the SR2 assembly frame ==== Need Fabian's input ==== * Cable clamps for BF,SF and PI -> 方式を決める * Design change for the PI clamps, because the SR PIs are NIKHEF ones. * Ballast masses for BF and SF * 製作に2週間程度 * 10月頭にTop Filterの最適荷重を実測。それに合わせて発注。それまでにデザインは用意しておく。 * 測定に必要な物品の準備 -> 月曜日に高橋さんと相談 ==== Need more discussion/checks ==== * Blade spring assembly for LBB * Check the load of the LBB and decide the design load of the springs * Correct the length * Scale the width of the current blades to design the new blades -> 高橋さんと相談 * SR用LBBの重さを確認 * Bread board damper rings * Need to check whether we can put a full ring into the chamber from the side flanges or not. -> 至急確認 === Electronics === * Get cables/cards for SR3: * 5 DSub-37 cables (tent) * 5 DSub-15M to DSub-9M adapter cables (tent) * 3 DIO cards (tent) * 2 DSub-9 FF gender benders (for LVDTs) * extra ADC card(s)? * extra DAC card(s)? * BNC-LEMO adapter (for LVDTs) * etc |
VIS Type B BS Near Term To-Do List
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2017-09-19
(No work Monday 9/18)
Main Assembly Sequence
- Debug BF LVDT actuation.
- Check F0 yoke height (top of coil former should be 37.5 mm above bottom of recess in top of baseplate).
- Test all PI items:
- Yaw stepper (tested, not clearly working).
- F0 LVDT sensing
- F0 LVDT actuation
- Horizontal LVDT sensing
- Horizontal LVDT actuation
- Geophones (issues with driver, cables, descramblers)
- Lock the F0 and SF keystones and measure the resonance frequency of the BF GAS.
- Lock the SF and BF keystones and measure the resonance frequency of the F0 GAS.
- Double check BS pitch with OL.
- Adjust SF damper ring to correct gap.
- Install lock nuts on F0 GAS FR at TBD positions.
Lock BF and F0 keystones (but not SF keystone).
- Lock RM to BS and IRM to IM.
- Lock RM, IRM and BF (but not SF) to security structure.
- Lock IP.
- Remove F0 keystone top plate (including yaw stepper) and immobilize SF/... in yaw.
- Attach lifting fixture.
- Remove BF- and SF-level crossbars.
- Remove geophones for craning.
- Disconnect in-vacuum cables from feedthrough and coil neatly for craning.
- Attach lifting plates.
Tank Preparation Sequence
- Attach Cu segments to LBB damper ring.
- Pass halves of LBB magnet ring into tank, join, and make sandwich for craning.
- Crane tank lid off.
- Crane LBB damper rings to top of tank and suspend.
- Crane suspension out of assembly frame.
- Attach LBB upper rods to LBB blade tips and rotate suspension 45° clockwise.
- Crane suspension into tank and connect upper rods to LBB Cu ring.
- Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods.
- Install LBB lower rods and hook LBB.
- Measure required ballast for LBB.
- Unlock suspension and readjust.
- Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
In parallel, time permitting
- Fix issue with geophone distributor.
- Fix #1 geophone adapter cable (and replace borrowed one).
- Fix broken pico adapter cable.
- Figure out how to tighten PI yaw return spring or otherwise make yaw adjustment reliable.
Tasks Not To Forget
Major Tasks
- Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
- Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
- Get pico drive screens fixed (Miyo-kun)
Minor Tasks
Mechanical
- Get clean bag laundered.
- Put pointy-tipped screw in RM trolley for BS
- Return/replace borrowed parts:
- Lock washers for LBB dampers
- Temporary ballast mass (dog clamps) in BF.
- Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.
Electrical
- Decide final in-vacuum and in-air cable routing (Enzo).
Calibrate all LVDTs (Enzo, Mark). BF, SF, PI-GAS, PI-H1, PI-H2, PI-H3
- Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height).
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.
- Design and install GAS drift compensation filters.