Differences between revisions 121 and 123 (spanning 2 versions)
Revision 121 as of 2017-09-03 19:17:28
Size: 4340
Editor: MarkBarton
Comment:
Revision 123 as of 2017-09-03 21:26:31
Size: 3952
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 23: Line 23:
== 2017-08-21 ==
=== Design/Documentation/Planning ===
 * Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
== 2017-09-04 ==
Line 27: Line 25:
=== Main Assembly ===
 * --(Wrap new IM bottom ballast masses (Mozumi).)--
 * --(Install new IM masses.)--
 * --(Set up optical level.)--
 * --(Adjust IM ballast mass to give desired roll/pitch/vertical.)--
 * --(Level BF.)--
 * --(Cable BF LVDT, test and calibrate.)--
 * --(Adjust top of IRM to level.)--
 * --(Install IRM side panels.)--
 * --(Install IRM OSEMs.)--
 * --(Cable IRM OSEMs)-- and test.
 * --(Adjust IRM and IRM OSEMs to get good alignment of IRM OSEMs and IM-IRM stops.)--
 * --(Add extra ballast mass to BF.)--
 * --(Add BF cap but don't anchor cables.)--
 * --(Cable and test BF cap picos.)--
 * --(Lift BF/IRM/IM/RM/BS and weigh.)--
 * --(Adjust BF ballast if necessary.)--
 * --(Crane in SF.)--
 * Hook up BF/IRM/IM/RM/BS.
 * Route cables up to SF.
 * Adjust BF ballast if necessary.
=== Main Assembly Sequence ===
 * Crane out SF.
 * Raise BF cap and retrieve lost hex cable clamp PEEK piece.
 * Crane in SF.
 * Install SF-BF rod with hex cable clamp.
 * Route cables via hex cable clamp up to below SF.
 * Adjust BF ballast mass for total weight and pitch/roll.
 * Look for missing screw from SF damper Cu segment in washed screws bag and reinstall.
 * Calibrate SF LVDT.
 * Install SF main ballast mass.
 * Cable and test SF fishing rod stepper.
 * Add SF cap.
 * Lift and weigh SF/... section.
 
Line 49: Line 40:
=== Time permitting ===
  * Lay more new in-air cabling.
=== In parallel, time permitting ===
 * Rearrange arc weights on PI to allow installation of magic wand.
 * Check that we still have all LBB parts (there was an issue with borrowed lock nuts).
 * Rearrange magnets on SF damper magnet ring for full three Cu segments.
 * Find Ni-plated rods for SF damper magnet ring and do fit check.
 * Find PI-SF rod with 8 mm heads and matching receptacles and do fit check.
 * Lay more new in-air cabling.
 * Wipe LLB damper parts with ethanol.
 * Get Cu O-rings for feedthroughs.
 * Figure out how to tighten PI yaw return spring.
Line 55: Line 54:
 * Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
Line 57: Line 57:
 * --(Final ballast mass production for BF and SF (Hirata-san). )--
 * --(Design of receptacles for rods with 8 mm heads.)--
 * --(Possible rebuild of BF)--
  * --(Set up build/test stand for filters.)--
  * --(Get filter test weights.)--
  * --(Find spare BF blade(s).)--
 * Reclean stuff:
  * PI (remove Kapton tape etc, etc).
  * LLB damper stuff, especially Cu segments.
 * Calibrate SF LVDT.
Line 75: Line 65:
 * --(Swap out temporary ballast mass in BF)--, SF.
Line 83: Line 72:
 * --(Check inside SF for lost ruler.)--
 * Tighten PI yaw return spring.
 * Get Cu O-rings for feedthroughs.

VIS Type B BS Near Term To-Do List

Archived BS To-Do Items

SR To-Do Items

Every Week

Coming Weeks

Preparation for Real BS Hang

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

2017-09-04

Main Assembly Sequence

  • Crane out SF.
  • Raise BF cap and retrieve lost hex cable clamp PEEK piece.
  • Crane in SF.
  • Install SF-BF rod with hex cable clamp.
  • Route cables via hex cable clamp up to below SF.
  • Adjust BF ballast mass for total weight and pitch/roll.
  • Look for missing screw from SF damper Cu segment in washed screws bag and reinstall.
  • Calibrate SF LVDT.
  • Install SF main ballast mass.
  • Cable and test SF fishing rod stepper.
  • Add SF cap.
  • Lift and weigh SF/... section.

In parallel, time permitting

  • Rearrange arc weights on PI to allow installation of magic wand.
  • Check that we still have all LBB parts (there was an issue with borrowed lock nuts).
  • Rearrange magnets on SF damper magnet ring for full three Cu segments.
  • Find Ni-plated rods for SF damper magnet ring and do fit check.
  • Find PI-SF rod with 8 mm heads and matching receptacles and do fit check.
  • Lay more new in-air cabling.
  • Wipe LLB damper parts with ethanol.
  • Get Cu O-rings for feedthroughs.
  • Figure out how to tighten PI yaw return spring.

Real BS Hang Tasks

Major Tasks

  • Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
  • Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
  • Get pico drive screens fixed (Miyo-kun)
  • Calibrate PI vertical LVDT.
  • Set yoke on PI vertical LVDT (if necessary).
  • Calibrate PI horizontal LVDTs.

Minor Tasks

Mechanical

  • Get clean bag laundered.
  • Put pointy-tipped screw in RM trolley for BS
  • Return/replace borrowed parts:
    • Lock washers for LBB dampers
    • Temporary ballast mass (dog clamps) in BF.
    • Wide-mouth OSEMs from RM to Akutsu-san

  • Adjust height of crossbars below BF.

  • If possible, fix galled pole in BF level of EQ stop.

  • Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.

Electrical

  • Decide final in-vacuum and in-air cable routing (Enzo).
  • Calibrate all LVDTs (Enzo, Mark). BF, SF, PI-GAS, PI-H1, PI-H2, PI-H3

  • Remove cling wrap in BF and install vacuum-compatible heat shrink.

  • Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins).

  • Rewire PI horizontal steppers with vacuum-compatible cable.

  • Adjust yoke on BF to put top of secondary at 3.5 mm above top of baseplate (or to give ≈0 counts at nominal height).

  • Adjust yoke on SF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height).
  • Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height).

Real-time and SUMCON models

  • Create SUMCON models for full BS and major installation milestones.
  • Create controls design description (cf LIGO-T1100378).

  • Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
  • Understand/document/debug Kokeyama-san's DIO stuff.
  • Measure LPCD and HPCD output filter response.
  • Design and install software compensation filters for LPCD and HPCD output filters.
  • Design and install GAS drift compensation filters.
  • Create a proper DAC Monitor MEDM screen.

  • Improve ADC Monitor MEDM screen.

KAGRA/Subgroups/VIS/TypeB/ToDoBS (last edited 2019-01-04 15:21:23 by MarkBarton)